National Aeronautics and Space Administration

Major NASA Development Programs

Program Cost Estimates

This special section of the FY 1998 budget justifications provides information about major NASA programs that are either in the design and development phase or have not completed their initial operational phase. In several instances, information about programs which are not "major" but are of special interest has been included. The budgetary estimates are expressed in millions of dollars of budget authority. * Estimates of the FY 1996 and prior fiscal year budget authority are the "actual" amounts. The

FY 1997 amounts are consistent with the proposed NASA Operating Plan as of December 1996. The amounts for FY 1998 and future fiscal years are expressed in "real year" economics, that is, they include an adjusting factor for the future inflation expected to be experienced. If the term "constant dollars" is used in the budget justifications, that phraseology indicates that the numbers do not include inflationary adjustments beyond the fiscal year referenced (e.g., "constant FY 1994 dollars").

The estimates provided below are intended to be comprehensive, including all related mission-unique costs, but there are limitations. The direct and indirect costs incurred by foreign governments or other federal agencies in support of these missions have not been included. (The reader is referred to the NASA Program Status Reports, a biannual document published by NASA, for the most accurate information available to NASA on the amounts incurred or to be incurred.) The estimates of civil service costs have been included, but these estimates should be considered preliminary, and they will continue to be refined as the agency moves toward full cost accounting over the next two years.

High Speed Research Program Mars Pathfinder
Advanced Subsonic Technology Near-Earth Asteriod Rendezvous (NEAR)
International Space Station Lunar Prospector
Alternate Turbopump Development Stardust
Super Lightweight Tank Mars Surveyor Program
Advanced X-Ray Astrophysics Facility Mars Global Surveyor
Space Infrared Telescope Facility (SIRTF) 98 Mars Orbiter/Lander
Relativity Mission/Gravity Probe-B Future Surveyor Missions
Thermosphere, Ionosphere, Mesosphere Energetics and Dynamics (TIMED) New Millennium Spacecraft
Global Geospace Science Missions Deep Space I
Collaborative Solar Terrestrial Research Program Deep Space II
The Explorer Program Earth Observing System
X-Ray Timing Explorer Earth Probes
Advanced Composition Explorer EOS New Millennium Program and Technology Infusion
Far Ultraviolet Spectroscopy Explorer Scatterometer
Stratospheric Observatory for Infrared Astronomy Total Ozone Mapping Spectrometer
CASSINITropical Rainfall Measuring Mission
Discovery Missions TDRS Replenishment Spacecraft Program
X-33 Advanced Technology Demonstrator


* Budget authority is a term used to represent the amounts appropriated by the Congress in a given fiscal year; budget authority provides government agencies with the authority to obligate funds. The ensuing obligations, cost incurrence, and expenditures (outlays) can differ in timing from the fiscal year in which Congress provides the budget authority in an appropriations act. Budget authority in this section is expressed in millions of dollars.


High Speed Research Program

The High Speed Research Program is a cooperative government-industry program to develop the technologies required by U.S. firms to design and build an environmentally compatible and economically competitive high-speed civil transport aircraft for the post-2000 period. The program consists of two phases. Phase I was initiated in FY 1990. Research was initiated at that time into environmental issues, such as atmospheric effects (e.g., ozone depletion), take-off and landing noise levels, and sonic booms for overland flight. Potential technology solutions have also been investigated. Phase II began in FY 1994, following a presentation of the encouraging preliminary results from Phase I activities. This phase involves both government funding and industry contributions of facilities, personnel, and supporting R&D. Development and validation of specific airframe and engine designs, design tools, and technologies for manufacturing processes are underway. This phase will conclude in 2002. It should be noted that the government funding does not provide for the development of a prototype aircraft.

The HSR program previously included the Environmental Research Aircraft and Remote Sensor Technology (ERAST) project element, with the objective of developing the technology for remotely piloted aircraft to serve as platforms to sample the stratospheric atmosphere for exhaust gases and particulates. The technology was not developing fast enough to meet the timelines of HSR, so the ERAST program was replanned to develop and commercialize remotely piloted aircraft. The objectives of ERAST no longer support the primary HSR objectives. ERAST has therefore been transferred from HSR into the R&T base, and the associated funding has been deleted from the HSR program accordingly.

The budgetary estimates provided below are the amounts included in the specific budget justification within the Aeronautics section in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts being contributed by industry, or for the use of government facilities and general support used to carry out the research. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative.

(Budget Authority in Millions of Dollars)
High Speed Research ProgramPRIOR 19961997 19981999 20002001 2002Balance TOTAL
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)658.1 233.3243.1 245.0174.0 91.260.2 60.2-- 1,765.1
(ESTIMATED CIVIL SERVICE FTEs)(1849) (568)(573) (566)(584) (514)(481) (468)-- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)112.7 41.0 44.2 45.946.2 41.439.7 41.0-- --


Advanced Subsonic Technology

The Advanced Subsonic Technology (AST) program is a cooperative government-industry program to develop technologies in areas where such developments will facilitate the economic and technological competitiveness of U.S. subsonic aircraft producers. These developments include not only airframe, engine, and avionics technology improvements, but also short-haul aircraft, environmental studies, efficiency and safety improvements, advanced air traffic technology, and aircraft design and manufacturing tools. This systems technology program was preceded by activities funded within the research and technology base for many years; the decision to create a focused program was made in the FY 1991 budget. The specific objectives set forth for this program are intended to be completed by FY 2004.

In FY 1996, the Fly-by-light/Power-by-Wire (FBL/PBW) element of AST program was terminated and the out-year composite fuselage project was eliminated. Funding for the AST program has been reduced to reflect these changes. In addition, a new change in the AST program is being is being discussed that will shift the emphasis from economics to revolutionary advances in the software tools necessary to design, manufacture and certify aviation systems in order to provide significant reductions in the cost of aircraft.

The budgetary estimates provided below are the amounts included in the specific budget justification within the Aeronautics section in the Science, Aeronautics and Technology appropriation for this program. As such, they do not include the amounts being contributed by industry, or for the use of government facilities and general and administrative support used to carry out the research. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative.


(Budget Authority in Millions of Dollars)
Advanced SubsonicTechnologyPRIOR 19961997 19981999 20002001 2002Balance TOTAL
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)232.5 169.8173.6 211.1187.0 144.2163.3 94.0107.1 1,482.6
(ESTIMATED CIVIL SERVICE FTEs)(830) (536)(597) (541)(493) (443)(389) (342)-- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)53.4 38.746.1 43.939.1 35.732.1 30.0-- --


International Space Station

In FY 1983, NASA received approval to enter into a preliminary definition phase of a space station. A cost target was established at that time by President Reagan; this target provided guidance to the team undertaking the definition of what capabilities a space station could have for this amount of money. Due to the uncertainty of future inflation, the target was expressed in constant 1984 dollars. The target value of $8 billion was intended to cover the costs which would be incurred to perform the preliminary definition and the development of space station hardware and ground systems. The President also directed NASA to solicit the involvement of international parties in the space station.

After three years studying numerous design concepts, a final reference design was established by NASA and our international partners--Japan, Canada, and the member nations of the European Space Agency. Prior to requesting from the Administration and Congress the authority to proceed into the development phase, NASA undertook a comprehensive cost estimate. The resultant estimate of $14.5 billion (expressed in 1984 dollars for comparison purposes) was presented to the Administration in early 1987. After consideration, the Administration directed a National Research Council (NRC) review of the reference design and the cost estimate. The NRC reported back that the space station could be built in two phases, with the second phase adding the dual keel configuration, the co-orbiting platform, servicing capabilities, and additional solar dynamic power modules. The NRC included in its estimate of $21.0-25.0 billion (1984 dollars), a number of additional cost elements : operations, marginal Shuttle flight costs, a crew rescue vehicle, civil service salaries and expenses, facilities, and provision for additional testing and backup hardware. These estimates were furnished to the Congress in mid-1987 for their review prior to action on NASA's FY 1988 appropriation.

Over each ensuing year, Congress approved continuation of the Space Station Freedom program, but reduced each year's appropriations request. On several occasions, Congress directed NASA to redesign the Station to conform not only to the reduced appropriations request in that year but also to reduced projections of future funding availability for NASA's overall budget. In early 1993, President Clinton directed NASA to undertake a 90 day study of lower cost redesign options for the Space Station, and appointed an Advisory Committee on the Redesign of the Space Station. In June 1993, upon receiving the final reports and the Advisory Committee's recommendations, President Clinton selected an option (A) from the three options presented and directed NASA to execute the Space Station program for no greater than $2.1 billion per year. This figure encompassed not only the development and operational costs of the Space Station itself but also the costs for a program of precursor scientific research, the expenses for integrating the Space Shuttle and the Space Station and the development of experimental facilities and capabilities for the Space Station. The cap excluded the costs of civil service salaries and expenses, Space Shuttle operational flight costs, and performance improvements to the Shuttle.

In the Fall of 1993, President Clinton invited the Russian Government to become a participant in the program. The Russians offered access to their Mir space station in the interim period between 1995 and the beginning of the international Space Station's

assembly. The Congress and Administration agreed in late 1993 that the $100 million amount to be paid annually to the Russian

Space Agency for hardware and services over the FY 1994-97 period was outside the $2.1 billion annual cap. Since late 1993, the U.S. and the newly expanded set of international partners have proceeded with the final design and hardware development for an international Space Station with significantly greater capabilities for research than those which would have been provided on Space Station Freedom or the option selected in the redesign process.

The budgetary estimates provided below include the amounts for this program in the Human Space Flight appropriation. Previous budgets provided funding for Space Station related research and payloads in the Science, Aeronautics and Technology appropriation. This past year NASA consolidated the management of Space Station research and technology, science utilization, and payload development with the Space Station development and operations program in order to enhance the integrated management of the total content of the annual $2.1 billion budget. The FY 1998 budget reflects that consolidation by funding the total annual $2.1 billion budget within the Space Station budget line of the Human Space Flight appropriation account. The research and technology elements of the program, including Mir research and support, utilization support, life and microgravity sciences payloads and research, and the station-related space product development activities, are now included in the Research line. The FY 1998 budget proposes multi-year appropriations for the development of the Space Station.

The totals provide the current estimate for the costs to be incurred through the date when the completion of the U.S. element assembly milestone in June 2002 is accomplished. They do not include the amounts being contributed by the international partners, the $400 million contract with the Russian Space Agency, the costs of the non-program unique NASA facilities, Shuttle performance improvements and flight operations costs, and the general and administrative support used to execute the program. The present cost estimate for the average costs of the 18 Space Shuttle flights for assembly of the U.S. elements by June 2002 is $7.4 billion. Four flights largely dedicated to partner elements are estimated at $1.7 billion. An additional 6 Shuttle flights will be made for research and technology utilization purposes during the assembly period; at average costs, these utilization flights are estimated at $2.5 billion. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the budget justifications for the Space Station.


International Space Station


(Budget Authority in Millions of Dollars)
International Space StationPRIOR 19941995 19961997 19981999 20002001 Balance to June 2002 * TOTAL
PROGRAM ELEMENTS WITHIN $2.1 BILLION ANNUAL FUNDING CAP --2,106.0 2,112.92,143.6 2,148.62,121.3 2,109.21,914.6 1,596.81,147.0 17,400.0
HUMAN SPACE FLIGHT **10,234.1 2,106.02,112.9 2,143.62,148.6 2,121.32,109.2 1,914.61,596.8 1,147.027,634.1
SPACE STATION10,234.1 2,106.02,112.9 2,143.62,148.6 2,121.32,109.2 1,914.61,596.8 1,147.027,634.1
DEVELOPMENT9,190.4 1,918.21,749.4 1,746.21,766.3 1,386.1898.4 651.5285.1 105.519,697.1
OPERATIONS-- --108.9 120.0177.6 490.1714.6 750.6750.6 637.43749.8
RESEARCH121.0 187.8254.6 277.4204.7 245.1496.2 512.5561.1 404.13264.5
OTHER922.7 ---- ---- ---- ---- --922.7
(ESTIMATED CIVIL SERVICE FTEs)(3,245) (1,283)(1,441) (1,934)(2,188) (2,425)(2,309) (2,195)(2,166) (1,586)--
CIVIL SERVICE COMPENSATION ESTIMATE ($M) *** 164.585.9 102.6139.6 168.8196.6 182.8176.7 179.0-- 139.0

* Balance of estimate is for 9 months of the fiscal year, through June 2002 (U.S. assembly complete)

** The amounts shown have been restated to include the funds appropriated in FY 1997 and prior years to the Science. Aeronautics and Technology, Construction

of Facilities and Research and Development appropriations.

*** Civil Service estimates include only FTEs for the International Space Station within Human Space Flight


Alternate Turbopump Development

Funding to begin development of an alternate design for the two turbopumps driving the Space Shuttle's Main Engine was initiated in FY 1987. The development of a new high-pressure oxygen turbopump and hydrogen fuel turbopump was undertaken to improve the safety, reliability, producibility, and maintainability of the current turbopumps. After an initial period of design and development, problems experienced in early development testing and accompanying increased costs resulted in suspension of the fuel turbopump's development, while development activities concentrated on the oxygen turbopump. Although further development problems were encountered with the oxygen turbopump, their successful resolution led to Congress agreeing in Spring 1994 to resumption of the fuel turbopump's development. The first flight of the oxygen turbopump occurred in 1995, and the initial flight of the fuel pump will be in early FY 1998. The budgetary estimates provided below include not only the funding required for the design, development, and extensive testing of these two types of turbopumps, but also the funding needed to produce the flight turbopumps for installation into the main engines for the four-orbiter fleet. The runout budget estimate of $970.6 million reflects a decrease of $59.8 million from the FY 1997 budget estimate. The decrease is due to a reduction of project reserves, consistent with expected technical progress. The reserves will remain available at the program level, however, should they be required.

The budgetary estimates provided below are the amounts included in the Human Space Flight appropriation for this program. They do not include the amounts for the use of government facilities and general and administrative support used to carry out the development. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the Space Shuttle program.


(Budget Authority in Millions of Dollars)
Alternate Turbo Pump DevelopmentPRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT554.8 68.746.7 46.722.110.8 ---- --749.8
IMPLEMENTATION58.4 28.348.7 49.528.2 7.7-- ---- 220.8
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)613.2 97.095.4 96.250.3 18.5-- ---- 970.6
(ESTIMATED CIVIL SERVICE FTEs)(410) (55)(51) (26)(16) (16)-- ---- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)22.5 4.03.9 2.11.3 1.2-- ---- --


Super Lightweight Tank

The design and development of a lighter external tank for the Space Shuttle was undertaken in 1993 after tests of new aluminum-lithium materials indicated that a significantly lighter external tank could be produced. The anticipated weight savings of approximately 7500 pounds would recover some of the ascent performance losses resulting from safety and reliability improvements instituted after the Challenger disaster. Coupled with other performance gains, the super lightweight tank will facilitate the Space Shuttle's operations at new higher inclination orbit established in 1993 for the international Space Station. The first launch of a Space Shuttle with the new tank is planned for late 1997. In addition to the design and development costs, the figures shown below as "recurring cost" provide the estimate of the funding required for the external tank program's production of the new tanks. The estimates include the additional material cost which will be incurred in the production of subsequent tanks. The aluminum-lithium material is a specialty metal produced to rigorous specifications and accordingly costs more than the aluminum used at present.

The budgetary estimates provided below are the amounts included in the Human Space Flight appropriation for this program. They do not include the amounts for the use of government facilities and general and administrative support used to carry out the development activities. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the Space Shuttle program.


(Budget Authority in Millions of Dollars)
Super Lightweight TankPRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT COST92.0 30.717.5 9.26.8 ---- --*43.8 200.0
RECURRING COST28.7 27.331.9 33.133.1 8.5-- --Cont. 162.6
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)120.7 58.049.4 42.339.9 8.5-- --43.8 362.6
*- Undistributed reserve
(ESTIMATED CIVIL SERVICE FTEs)(73) (78)(68) (64)(37) (43)-- ---- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)5.2 5.65.3 5.22.9 3.5-- ---- --


Advanced X-Ray Astrophysics Facility

The design and development of the Advanced X-Ray Astrophysics Facility (AXAF) was approved by Congress in the FY 1989 budget. The AXAF is the third of the four "Great Observatories" intended to observe the universe in four electromagnetic spectrum regions: visible, infrared, gamma ray, and x-ray. The initial phase of the AXAF's development was limited to a feasibility demonstration of the new mirror technology required to achieve the AXAF's objectives. A specially designed x-ray calibration facility was constructed to assure the mirrors meet their design specifications. The second phase was approved by Congress after the demonstration mirrors were successfully tested. In 1992, NASA management directed the restructuring of the AXAF program to reduce projected future funding requirements. A two-spacecraft approach was selected, a large imaging spacecraft (AXAF-Imaging) and a smaller spectroscopy spacecraft (AXAF-Spectroscopy). In 1993, Congress directed the elimination of the AXAF-S. The launch of the AXAF-I spacecraft is scheduled for September 1998 aboard the Space Shuttle, with an Inertial Upper Stage (IUS) providing delivery into a highly elliptical orbit around the Earth. The budgetary estimates provided below encompass: the early development of the mirror technology; the design and development phase; establishment of a mission-unique science center and preflight ground system development, followed by a five-year period (1998-2002) of mission operations and science data analysis; the purchase of the IUS and integration activities; the average cost (including recurring costs for improvements and upgrades) of an FY 1998 Space Shuttle flight; mission-unique tracking and data support costs; and, the construction of the X-Ray Calibration Facility.

The estimates provided below include a pro forma distribution of the average costs of a Space Shuttle. They do not include the amounts being contributed by international participants, or for the use of non-program-unique government facilities and general and administrative support used to carry out the research and development activities. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.

(Budget Authority in Millions of Dollars)
Advanced X-Ray Astrophysics Facility PRIOR1996 19971998 19992000 20012002 BTCTOTAL
ADVANCED TECH DEVELOPMENT54.2 ---- ---- ---- ---- 54.2
DEVELOPMENT 943.8 237.6178.6 92.2-- ---- ---- 1,452.2
MISSION OPS & DATA ANALYSIS52.5 40.441.3 45.463.6 63.367.3 69.976.3 520.0
UPPER STAGE32.6 15.314.5 5.3-- ---- ---- 67.7
STS LAUNCH SUPPORT-- 216.786.6 130.0-- ---- ---- 433.3
TRACKING & DATA SUPPORT.3 .5.4 .3.2 .2.2 .21.4 3.7
CONSTRUCTION OF FACILITIES17.7 ---- ---- ---- ---- 17.7
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)1,101.1 510.5321.4 273.263.8 63.567.5 70.177.7 2,548.8
(ESTIMATED CIVIL SERVICE FTEs)-- (1052)(269) (235)(183) (70)(36) (36)(36) --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)-- 61.519.4 18.114.8 5.52.9 3.03.2 --


Space Infrared Telescope Facility (SIRTF)

The purpose of the Space Infrared Telescope Facility (SIRTF) mission is to explore the nature of the cosmos through the unique windows available in the infrared portion of the electromagnetic spectrum. SIRTF is the fourth of NASA's Great Observatories, which include the Hubble Space Telescope, the Compton Gamma Ray Observatory, and the Advanced X-Ray Astrophysics Facility. The funding plan provided below reflects a dramatic restructuring of the SIRTF design concept carried for many years. Rather than simply "descoping" the "Great Observatory" concept to fit within a $400 million (FY94 $) cost ceiling imposed by NASA, scientists and engineers have instead redesigned SIRTF from the bottom-up. The goal was to substantially reduce costs associated with every element of SIRTF -- the telescope, instruments, spacecraft, ground system, mission operations, and project management. The Jet Propulsion Laboratory (JPL) was assigned responsibility for managing the SIRTF project. SIRTF is planned for launch on a Delta launch vehicle during FY 2002. The FY 1998 budget proposes multi-year appropriations for development of SIRTF. This will ensure the stability to manage and execute this program within its budget and schedule commitments.

The budgetary estimates below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts for the definition phase studies carried out prior to FY 96. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.

(Budget Authority in Millions of Dollars)
Space Infrared Telescope Facility (SIRTF)
PRIOR1996 19971998 19992000 20012002 BTCTOTAL
ATD--15.0 24.9-- ---- ---- --39.9
DEVELOPMENT-- ---- 81.4126.5 108.197.6 19.2-- 432.8
MISSION OPS & DATA ANALYSIS-- ---- ---- ---- 20.0101.2 121.2
LAUNCH SUPPORT-- ---- --8.0 21.919.7 6.6-- 56.2
TRACKING & DATA SUPPORT-- ---- ---- ---- ---- TBD
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)-- 15.024.9 81.4134.5 130.0117.3 45.8101.2 650.1
(ESTIMATED CIVIL SERVICE FTEs)-- --(3) (2)(2) (2)(2) (2)(2) --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)-- --0.2 0.20.2 0.20.2 0.20.2 --


Relativity Mission/Gravity Probe-B

The development of the Relativity mission began in 1993, after many years of studying mission design alternatives and developing the advanced technologies required for this mission to verify Einstein's theory of general relativity. The award of the spacecraft development contract was made in 1994. The scheduled launch date is October 2000, using a Delta II launch vehicle. The estimates provided below include funding for the experiment development activities, a minimum of 16 months of mission operations, and the launch services.

The budgetary estimates below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts for the definition phase studies carried out from FY 1985-87, but they do provide the amounts for the Shuttle Test of Relativity Experiment program initiated in FY 1988 and subsequently restructured into a ground test program only. The estimates also exclude the non-program-unique government facilities and general and administrative support used to carry out the research and development activities. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.


(Budget Authority in Millions of Dollars)
Relativity Mission/Gravity Probe-BPRIOR 19961997 19981999 20002001 2002BTC TOTAL
DEVELOPMENT219.851.5 59.645.6 44.035.8 4.1-- --460.4
MISSION OPS & DATA ANALYSIS-- ------ ---- 20.8-- --20.8
LAUNCH SUPPORT ---- 6.814.7 18.816.7 .2-- --57.2
TRACKING & DATA SUPPORT-- ---- ---- --TBD ---- TBD
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)219.8 51.566.4 60.362.8 52.525.1 ---- 538.4
(ESTIMATED CIVIL SERVICE FTEs)(62) (15)(13) (13)(13) (12)(12) ---- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)3.5 1.11.0 1.11.0 1.01.0 ---- --


Thermosphere, Ionosphere, Mesosphere Energetics and Dynamics (TIMED)

The TIMED mission is the first science mission in the Solar Terrestrial Probes (STP) Program, and is part of NASA's initiative aimed at providing cost-efficient scientific investigation and more frequent access to space. The development cost for the TIMED mission is capped at $100 million in FY 1994 dollars. TIMED will be developed for NASA by the Johns Hopkins University Applied Physics Laboratory (APL). The Aerospace Corporation, the University of Michigan, NASA's Langley Research Center with the Utah State University's Space Dynamics Laboratory, and the National Center for Atmospheric Research will provide instruments for the TIMED mission.

TIMED is scheduled for launch in January 2000 aboard a Med-Lite Class launch vehicle. TIMED will begin its 36-month C/D development period in April 1997. The budgetary estimates below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts for the definition phase studies carried out from April 1996 to April 1997.


(Budget Authority in Millions of Dollars)
Thermosphere, Ionosphere, Mesosphere Energetics and Dynamics (TIMED PRIOR1996 19971998 19992000 20012002 BTCTOTAL
DEVELOPMENT---- 18.248.2 47.315.6 ---- --129.3
MISSION OPS & DATA ANALYSIS-- ---- ---- 9.212.8 9.07.2 38.2
LAUNCH SUPPORT ---- --8.7 11.56.1 ---- --26.3
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)-- --18.2 56.958.8 30.912.8 9.07.2 193.8
(ESTIMATED CIVIL SERVICE FTEs)-- (7)(14) (19)(19) (18)(8) (8)-- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)-- 0.51.1 1.51.5 1.50.7 0.8-- --


Global Geospace Science Missions

The development of the two Global Geospace Science (GGS) missions was approved by Congress in the budget for 1989. The Wind and Polar spacecraft are parts of a coordinated international science program to improve our understanding of the complex interactions between the sun and the Earth. Nineteen instruments aboard the two spacecraft will make measurements of the interaction between the solar wind with the Earth's magnetic field. The Wind spacecraft was launched successfully on a Delta II launch vehicle in November 1994. The Polar spacecraft was launched successfully in February 1996, also on a Delta II. The budgetary estimates provide for the experiment and spacecraft development, a 2.5-year period of mission operations, the launch services, and unique tracking and data acquisition support required during the mission.

The budgetary estimates provided below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts being contributed by international participants, or for the use of non-program-unique government facilities and general and administrative support used to carry out the research and development activities. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.


(Budget Authority in Millions of Dollars)
Global Geospace Science Missions
PRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT452.7-- ---- ---- ---- --452.7
MISSION OPS & DATA ANALYSIS17.2 26.525.5 15.7-- ---- ---- 84.9
LAUNCH SUPPORT 116.6 3.0-- ---- ---- ---- 119.6
TRACKING & DATA SUPPORT26.1 0.60.1 0.10.1 ---- ---- 27.0
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)612.6 30.125.6 15.80.1 ---- ---- 684.2
(ESTIMATED CIVIL SERVICE FTEs)(684) (22)(5) (10)(10) ---- ---- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)38.7 1.60.4 0.80.8 ---- ---- --


Collaborative Solar Terrestrial Research Program

The Collaborative Solar Terrestrial Research (COSTR) program is another key U.S. contribution to the international solar terrestrial research program. Beginning in FY 1987, funding provided for this program has enabled NASA to provide instruments and launch support for international spacecraft. In return, the U.S. obtains access to the science data collected by the five European Space Agency spacecraft and one Japanese spacecraft. The initial launch was carried out in July 1992 with the launch of the Japanese Geotail spacecraft on a U.S.-funded Delta II. The December 1995 launch of the ESA Solar and Heliospheric Observatory (SOHO) was on a U.S.-funded Atlas IIAS. Mission operations and data analysis provides for spacecraft operations, the operations support to the U.S. furnished instruments and the analysis of the scientific data gathered by them.

The four Cluster spacecraft were launched in May 1996, on an Ariane V; however the launch failed and the payload was lost. Options for recovery of the Cluster mission science are under review by NASA and ESA.

The budgetary estimates provided below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts being contributed by international participants, and the use of non-program-unique government facilities and general and administrative support used to carry out the research and development activities. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.

(Budget Authority in Millions of Dollars)
Collaborative Solar Terrestrial Research Program PRIOR1996 19971998 19992000 20012002 BalanceTOTAL
DEVELOPMENT331.0-- ---- ---- ------ 331.0
MISSION OPS & DATA ANALYSIS28.9 31.928.4 8.5-- ---- ---- 97.7
LAUNCH SUPPORT176.1 ---- ---- ------ --176.1
TRACKING & DATA SUPPORT38.8 1.20.1 0.1-- ---- ---- 40.2
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)574.8 33.128.5 8.6-- ---- ---- 645.0
(ESTIMATED CIVIL SERVICE FTEs)(446) (25)(26) (24)(14) (12)-- ---- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)25.2 1.82.0 1.91.1 1.0-- ---- --


The Explorer Program

The Explorer program consists of small to mid-sized spacecraft conducting investigations in all space physics and astrophysics disciplines. The program provides for frequent, relatively low-cost missions to be undertaken as funding availability permits within an essentially level overall funding profile for the program. The funding profile provided below covers the design and development phase, launch services, mission-unique tracking and data acquisition support, mission operations and data analysis. It does not include costs for the use of government facilities and general and administrative support required to implement the program. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.

(Budget Authority in Millions of Dollars)
The Explorer ProgramPRIOR 19961997 19981999 20002001 2002BTC TOTAL
X-Ray Timing Explorer253.1 11.610.2 7.34.8 3.3-- ---- 290.3
Advanced Composition Explorer110.2 33.735.9 12.67.5 7.73.7 3.9-- 215.2
Far Ultraviolet Spectroscopy Explorer.5 70.822.6 42.19.6 9.49.4 7.0-- 171.4
Medium Explorers-- 13.745.2 62.487.8 103.3101.8 118.5CONT --
Small Explorers--50.8 59.756.8 65.774.5 85.586.8 CONT--
University Explorers-- 12.37.1 13.311.8 8.36.5 10.6CONT --
Planning & Future Developments-- 6.75.7 6.08.3 5.34.9 5.6CONT --
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)-- 199.6186.4 200.5195.5 211.8211.8 232.4CONT --
(ESTIMATED CIVIL SERVICE FTEs)(1,248) (100)(97) (85)(79) (78)(78) (78)(Cont.) --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)71.8 7.27.5 6.96.3 6.36.4 6.8Cont. --


X-Ray Timing Explorer

Development on the X-Ray Timing Explorer (XTE) began in FY 1990. The spacecraft was an in-house build at the Goddard Space Flight Center; instruments were developed by the principal investigators. The XTE was launched successfully in December 1995 on a Delta II launch vehicle.


(Budget Authority in Millions of Dollars)
X-Ray Timing ExplorerPRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT194.2-- ---- ---- ---- --194.2
MISSION OPS & DATA ANALYSIS1.0 10.09.9 7.04.8 3.3-- ---- 36.0
LAUNCH SUPPORT45.5 ---- ---- ---- ---- 45.5
TRACKING & DATA SUPPORT12.4 1.60.3 0.3-- ---- ---- 14.6
TOTAL253.111.6 10.27.3 4.83.3 ---- --290.3


Advanced Composition Explorer

Development on the Advanced Composition Explorer (ACE) began in FY 1994. The spacecraft is being built by the Johns Hopkins Applied Physics Lab; instruments are being managed by the California Institute of Technology. ACE is scheduled for launch between August 1997 and December 1997 on a Delta II launch vehicle.

(Budget Authority in Millions of Dollars)
Advanced Composition ExplorerPRIOR 19961997 19981999 20002001 2002BTC TOTAL
DEVELOPMENT77.318.5 18.75.5 ---- ---- --120.0
MISSION OPS & DATA ANALYSIS-- --1.6 6.37.2 7.43.6 3.8-- 29.9
LAUNCH SUPPORT 28.6 10.912.0 ---- ---- ---- 51.5
TRACKING & DATA SUPPORT4.3 4.33.6 .8.3 .3.1 .1-- 13.8
TOTAl110.233.7 35.912.6 7.57.7 3.73.9 --215.2


Far Ultraviolet Spectroscopic Explorer

Development on the Far Ultraviolet Spectroscopy Explorer (FUSE) began in FY 1996. The FUSE mission has been restructured from a Delta-class explorer in order to reduce costs and accelerate the launch date from CY 2000 to November 1998. FUSE is being managed by Johns Hopkins University, with contributions from the University of Colorado, the University of California-Berkeley, Orbital Sciences Corp., Canada and France.

(Budget Authority in Millions of Dollars)
Far Ultraviolet Spectroscopic ExplorerPRIOR 19961997 19981999 20002001 2002BTC TOTAL
DEVELOPMENT--56.6 22.026.8 2.6-- ---- --108.0
MISSION OPS & DATA ANALYSIS-- ---- --7.0 9.49.4 7.0-- 32.8
LAUNCH SUPPORT .514.2 .615.3 ---- ---- --30.6
TOTAL.570.8 22.642.1 9.69.4 9.47.0 --171.4


Stratospheric Observatory for Infrared Astronomy

The initial development funding for the Stratospheric Observatory for Infrared Astronomy (SOFIA) was requested in the

FY 1996 budget. This new airborne observatory will provide a significant increase in scientific capabilities over the Kuiper Airborne Observatory, which was retired in October, 1995. The Kuiper was a Lockheed C-141A aircraft with a 0.9-meter reflecting telescope, used to conduct scientific investigations at infrared and submillimeter wavelengths. The SOFIA will be accommodated in a Boeing 747 and will feature a 2.5-meter infrared telescope to be provided by the German Space Agency (DARA). The initial operational date for SOFIA will be at the end of 2000. The FY 1998 budget proposes multi-year appropriations for development of SOFIA. This will ensure the stability to manage and execute this program within its budget and schedule commitments.

The budget estimates provided below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the costs of preliminary design studies carried out in previous years, the amounts being contributed by the international participants, or costs for the use of government facilities and general and administrative support used to carry out the research and development activities. A more detailed exposition of the program goals, objectives and activities is provided in the specific budget justification narrative for the Suborbital program within the Space Science section.

(Budget Authority in Millions of Dollars)
Stratospheric Observatory for Infrared Astronomy
PRIOR1996 19971998 19992000 20012002 BTCTOTAL
DEVELOPMENT--30.0 21.345.8 56.548.8 32.4-- --234.8
MISSION OPERATIONS-- ---- ---- ---- 36.6CONT. CONT.
TOTAL EXCLUDING CIVIL SERVICE COSTS-- 30.021.3 45.856.5 48.832.4 36.6-- --
(ESTIMATED CIVIL SERVICE FTEs)(6) (13)(15) (15)(15) (15)(15) (10)-- --
-CIVIL SERVICE COMPENSATION ESTIMATE ($M)0.5 0.91.1 1.21.2 1.21.2 0.9-- --


CASSINI

The Cassini mission will provide intensive, long term observations of Saturn's atmosphere, rings, magnetosphere and moons. The Huygens Probe will conduct direct physical and chemical analyses of the atmosphere of Saturn's moon, Titan. Cassini was approved as a new start by Congress in the FY 1990 budget. At the time it was initiated, a second spacecraft, the Comet Rendezvous and Asteroid Flyby (CRAF) was included. Congressionally-imposed reductions to FY 1992-93 funding requirements led to the termination of the CRAF mission and the deferral of the Cassini launch from April 1996 to October 1997. The Cassini program later underwent a significant redesign in early 1992 to reduce total program cost, mass and power requirements, while maintaining the October 1997 launch aboard a Titan IV launch vehicle. The spacecraft will arrive at Saturn in 2004 and begin a four year study of the Saturnian system. The program involves significant cooperation from international partners as well as U.S. government partners. The European Space Agency is providing the Huygens Probe and the Italian Space Agency is contributing the High Gain/Low Gain antenna for the spacecraft. There are twelve science instruments on the orbiter and six on the probe from international Principal Investigators. The Titan IV launch vehicle is being procured from the Department of Defense, and the Radioisotope Heater Units (RHUs) and Radioisotope Thermoelectric Generators (RTGs) are being procured by NASA from the Department of Energy.

The budgetary estimates provided below are the amounts included in the Science, Aeronautics and Technology appropriation for this program. They do not include the amounts being contributed by the international participants, or for the use of government facilities and general and administrative support required to implement the program. A more detailed description of the program goals, objectives and activities is provided in the specific budget justification narrative for the program within the Space Science section.

(Budget Authority in Millions of Dollars)
CASSINIPRIOR 19961997 19981999 20002001 2002BTC TOTAL
DEVELOPMENT1,109.8 191.589.6 9.0-- ---- ---- 1,399.9
MISSION OPS & DATA ANALYSIS-- ---- 38.155.8 55.056.6 63.8466.7 736.0
LAUNCH SUPPORT206.1 88.295.2 39.6-- ---- ---- 429.1
TRACKING & DATA SUPPORT19.6 1.83.0 4.78.8 6.24.5 5.0-- 53.6
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)1,335.5 281.5187.8 91.464.6 61.261.1 68.8466.7 2,618.6
(ESTIMATED CIVIL SERVICE FTEs)(389) (84)(24) (3)(3) (3)(3) (3)-- --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)23.7 6.11.9 0.20.2 0.20.2 0.3-- --


Discovery Missions

Discovery missions are planetary exploration missions designed with focused science objectives that can be met with limited resources. Total development costs are not to exceed $150 million in constant FY 1992 dollars, and development schedules are limited to three years or less. Two Discovery missions have been launched: NEAR in February 1996 and Mars Pathfinder in December 1996. In addition, there are two approved Discovery missions in development: the Lunar Prospector and Stardust. Future missions will be undertaken after selection through a peer review process.

The budgetary estimates provided below are the amounts included in the specific budget justification for this program within the Space Science section in the Science, Aeronautics and Technology appropriation. Under the specific mission descriptions, see below, other direct program cost elements are included: the development of the spacecraft and experiments, one year of mission operations, the launch services, and unique tracking and data acquisition services. They do not include costs for the use of government facilities and general and administrative support required to implement the program. A more detailed description of the program goals, objectives and activities is provided in the specific budget justification narrative for the program.

(Budget Authority in Millions of Dollars)
Discovery MissionsPRIOR 19961997 19981999 20002001 2002BTC TOTAL
NEAR156.716.9 1.69.7 15.08.8 .2.3 --209.2
MARS PATHFINDER188.8 55.815.0 6.0.1 ---- ---- 265.7
LUNAR PROSPECTOR-- 36.420.6 4.32.2 .0.0 .0.0 63.5
STARDUST--27.7 62.756.2 23.93.4 3.33.3 25.6206.1
FUTURE MISSIONS DEVELOPMENT-- .74.8 64.2120.7 127.5132.6 137.6CONT --
FUTURE MISSIONS MO&DA-- ---- --3.2 9.411.0 11.4CONT --
FUTURE MISSIONS ELVs-- ---- 6.019.6 36.543.5 67.2CONT --
TOTAL--137.5 104.7146.4 184.7185.6 190.6219.8 CONT--
(ESTIMATED CIVIL SERVICE FTEs)(31) (2)(7) (7)(7) (7)(7) (7)(Cont.) --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)2.2 0.10.5 0.60.6 0.60.6 0.6Cont. --


Mars Pathfinder

The Mars Pathfinder was approved as a new start in FY 1994 as one of the initial missions in the Discovery Program. The Mars Pathfinder mission will demonstrate a unique cruise, entry, descent, and landing system approach that will be available for future missions to Mars. Mars Pathfinder was launched in December 1996 on a Delta II expendable launch vehicle. The mission is being conducted as an in-house effort at the Jet Propulsion Laboratory. Portions of the science instruments were provided by Germany and Denmark.

(Budget Authority in Millions of Dollars)
Mars PathfinderPRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT140.533.7 ---- ---- ---- --174.2
MICROROVER17.25.8 2.0-- ---- ---- --25.0
MISSION OPS & DATA ANALYSIS-- --9.65.8 0.1-- ---- --15.5
LAUNCH SUPPORT31.0 16.13.2 ---- ---- ---- 50.3
TRACKING & DATA SUPPORT0.1 0.20.2 0.2-- ---- ---- 0.7
TOTAL188.855.8 156.0 2.0-- ---- --265.7


Near-Earth Asteroid Rendezvous (NEAR)

The NEAR was approved as a new start in FY 1994 as one of the initial Discovery Program missions. The NEAR mission was conducted as an in-house effort at the Applied Physics Laboratory, with many subcontracted subsystems. The NEAR spacecraft will conduct a comprehensive study of the near-Earth asteroid 433 EROS, including its physical and geological properties and its chemical and mineralogical composition. The NEAR spacecraft was launched February 17,1996 on a Delta II launch vehicle.


(Budget Authority in Millions of Dollars)
Near-Earth Asteroid Rendezvous (NEAR)PRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT116.68.3 ---- ---- ---- --124.9
MISSION OPS & DATA ANALYSIS-- 4.91.4 9.514.8 8.6-- ---- 39.2
LAUNCH SUPPORT40.0 3.5-- ---- ---- ---- 43.5
TRACKING & DATA SUPPORT0.1 0.20.2 0.20.2 0.20.2 0.3-- 1.6
TOTAL156.716.9 1.69.7 15.08.8 0.20.3 --209.2


Lunar Prospector

Lunar Prospector was selected as the third Discovery mission in FY 1995, and Phase C/D development started in the first quarter of FY 1996. The mission is designed to search for resources on the Moon, with special emphasis on the search for water in the shaded polar regions. Ames Research Center is managing the mission, and Lockheed Martin will provide the spacecraft, instruments, launch and operations. Launch will be on a Lockheed Launch Vehicle-II (LLV-II) and is planned for September 1997. Launch costs are included in the development cost. Tracking and communications support will be provided by the Deep Space Network.


(Budget Authority in Millions of Dollars)
Lunar ProspectorPRIOR 19961997 19981999 20002001 2002BTC TOTAL
DEVELOPMENT--36.4 19.8-- ---- ---- --56.2
MISSION OPS & DATA ANALYSIS-- --.8 4.32.2 ---- ---- 7.3
TOTAL--36.4 20.64.3 2.2-- ---- --63.5


Stardust

The Stardust mission was selected as the fourth Discovery mission in November 1995, with mission management from the Jet Propulsion Laboratory. The mission team has completed the Phase B analysis, and Stardust was approved for implementation in October, 1996. The mission is designed to gather samples of dust from the comet Wild-2 and return the samples to Earth for detailed analysis. The mission will also gather and return samples of interstellar dust that the spacecraft encounters during its trip through the Solar System to fly by the comet. Stardust will use a new material called aerogel to capture the dust samples. In addition to the aerogel collectors, the spacecraft will carry three additional scientific instruments. An optical camera will return images of the comet; the Cometary and Interstellar Dust Analyzer (CIDA) is provided by Germany to perform basic compositional analysis of the samples while in flight; and a dust flux monitor will be used to sense particle impacts on the spacecraft. Stardust will be launched on the Med-Lite expendable launch vehicle in February 1999 with return of the samples to Earth in January 2006.

(Budget Authority in Millions of Dollars)
StardustPRIOR 19961997 19981999 20002001 2002BTC TOTAL
PHASE A/B--9.6 ---- ---- ------ 9.6
DEVELOPMENT--13.5 52.242.3 9.8-- ---- --117.8
MISSION OPS & DATA ANALYSIS---- ---- 1.63.4 3.33.3 25.637.2
LAUNCH SUPPORT--4.6 10.513.9 12.5-- ---- --41.5
TOTAL--27.7 62.756.2 23.93.4 3.33.3 25.6206.1


Mars Surveyor Program

The Mars Surveyor program is a series of small missions designed to resume the detailed exploration of Mars. The first mission in this program, the Mars Global Surveyor mission, was approved as a new start in FY 1994. The follow-on Mars Surveyor 98 Orbiter and Lander were approved in FY 1995. Future small missions are targeted for launch in the launch windows that occur approximately every two years.

The budgetary estimates below are the amounts indicated in the budget justification within the Space Science section in the Science, Aeronautics and Technology appropriation. The specific write-ups for the Mars Global Surveyor and Mars 98 Orbiter/Lander missions include the amounts for the development of the spacecraft and instruments, two years of mission operations, and launch services. They do not include costs for the use of government facilities and general and administrative support used to carry out the program. A more detailed description of the program goals, objectives and activities is provided in the specific budget justification narrative.

(Budget Authority in Millions of Dollars)
Mars Surveyor ProgramPRIOR 19961997 19981999 20002001 2002Balance TOTAL
MARS GLOBAL SURVEYOR94.8 82.923.1 19.910.6 ---- ---- 231.3
98 MARS ORBITER/LANDER-- 59.8116.7 79.330.9 21.722.2 22.7-- 353.3
FUTURE MISSIONS--1.4 3.1103.3 151.6212.1 215.4214.7 Cont.901.6
TOTAL EXCLUDING CIVIL SERVICE COSTS ($M)94.8 145.1142.9 202.5193.1 233.8237.6 237.4-- 1487.2
(ESTIMATED CIVIL SERVICE FTEs)(37) (6)(8) (7)(7) (7)(7) (7)(Cont.) --
CIVIL SERVICE COMPENSATION ESTIMATE ($M)2.6 0.40.6 0.60.6 0.60.6 0.6Cont. --


Mars Global Surveyor

This mission will obtain a majority of the expected science return from the lost Mars Observer mission by flying a science payload comprised of spare Mars Observer instruments aboard a small, industry-developed spacecraft. Launch occurred in November 1996 on a Delta II launch vehicle. The funding estimates provided below do not include the previous expenditures on spare Mars Observer instruments or the amount recovered from the prime contractor after the Mars Observer failure.


(Budget Authority in Millions of Dollars)
Mars Global SurveyorPRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT72.658.1 ---- ---- ---- --130.7
MISSION OPS & DATA ANALYSIS-- --16.4 19.610.4 ---- ---- 46.4
LAUNCH SUPPORT21.8 24.46.4 ---- ---- ---- 52.6
TRACKING & DATA SUPPORT0.4 0.40.3 0.30.2 ---- ---- 1.6
TOTAL94.882.9 23.119.9 10.6-- ---- --231.3


98 Mars Orbiter/Lander

The 98 Mars Orbiter and Lander are the first follow-on missions in the Mars Surveyor program. The Orbiter will be launched on a Med-Lite launcher in December 1998, and the Lander will be launched on a Med-Lite in January 1999. Lockheed Martin Aerospace, Denver, was selected competitively to develop these spacecraft. The Orbiter will carry a color imager and a Pressure Modulater Infrared Radiometer (PMIRR), which was also a Mars Observer payload. The Lander will carry a descent imager, a comprehensive volatiles and climate payload, and a Russian LIDAR atmospheric instrument.

(Budget Authority in Millions of Dollars)
98 Mars Orbiter/LanderPRIOR 19961997 19981999 20002001 2002Balance TOTAL
DEVELOPMENT--52.4 86.940.5 13.3-- ---- --193.1
MISSION OPS & DATA ANALYSIS-- ------ 10.321.3 21.922.7 --76.2
LAUNCH SUPPORT--7.4 29.838.8 7.1-- ---- --83.1
TRACKING & DATA SUPPORT-- ---- --0.2 0.40.3 ---- 0.9
TOTAL--59.8 116.779.3 30.921.7 22.222.7 --353.3


Future Surveyor Missions

The Mars Surveyor landers planned in future years -- 2001, 2003 and beyond -- will capitalize on the experience of the Mars Pathfinder lander mission launched in November 1996. The small orbiter to be launched in 2003 will draw on the experience of Mars Global Surveyor and carry other scientific instruments into orbit to complete Mars Global Surveyor's science missions. A Mars sample return mission is being considered for the FY 2005 opportunity.

(Budget Authority in Millions of Dollars)
Future Surveyor MissionsPRIOR 19961997 19981999 20002001 2002BTC TOTAL
DEVELOPMENT--1.4 3.199.2 122.7167.7 170.3173.9 --738.3
MISSION OPS & DATA ANALYSIS-- ---- ---- ---- ---- --
LAUNCH SUPPORT---- --4.1 28.944.4 45.140.8 CONT--
TRACKING & DATA SUPPORT-- ---- ---- ---- --TBD TBD
TOTAL--1.4 3.1103.3 151.6212.1 215.4214.7 ----


Space Science New Millennium Spacecraft

The New Millennium program is an advanced development effort started in FY 1996 to demonstrate how complex scientific spacecraft--such as those required for planetary missions--can be built for lower missio