NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
CONSTRUCTION OF FACILITIES
FISCAL YEAR 1996 ESTIMATES
SUMMARY
REHABILITATION AND MODIFICATION
Summary of Project Amounts by Location: Amount
Ames Research Center....................................... $3,740,000
Dryden Flight Research Center.............................. 900,000
Goddard Space Flight Center................................ 2,920,000
Jet Propulsion Laboratory.................................. 3,000,000
Johnson Space Center....................................... 3,250,000
Kennedy Space Center....................................... 3,160,000
Langley Research Center.................................... 3,360,000
Lewis Research Center...................................... 3,260,000
Marshall Space Flight Center............................... 3,580,000
Michoud Assembly Facility.................................. 1,350,000
Stennis Space Center....................................... 2,400,000
Wallops Flight Facility.................................... 890,000
Various Locations.......................................... 2,710,000
Miscellaneous Projects Not in Excess of $250,000 Each...... 480,000
Total................................................ $35,000,000
CONSTRUCTION OF FACILITIES
FISCAL YEAR 1996 ESTIMATES
PROJECT TITLE: Rehabilitation and Modification of Facilities,
Not in Excess of $1,500,000 Per Project
INSTALLATION: Various Locations
FY 1996 Estimate: $35,000,000
FY 1994: $36,000,000 FY 1995: $30,000,000
COGNIZANT INSTALLATIONS/LOCATIONS OF PROJECT: Various Locations
COGNIZANT HEADQUARTERS OFFICE: Office of Management Systems and Facilities
SUMMARY PURPOSE AND SCOPE:
These resources will provide for the rehabilitation and modification of facilities at NASA
field Installations and Government-owned facilities at industrial plants and universities
supporting NASA activities. Included in this request are those facility rehabilitation and
modification needs for FY 1996 that have been fully identified at the time of the submission
of these estimates and are estimated not to exceed $1.5 million per project. The purpose of
this program may include some restoration of current functional capability but also includes
enhancement of the condition of a facility so that it can more effectively accomplish its
designated purpose or increase its functional capability.
PROJECT JUSTIFICATION:
The NASA physical plant has a capital investment of $5.5 billion and has a current replacement
value of more than $15 billion. A continuing program of rehabilitation and modification of
these facilities is required to accomplish the following:
a. Protect the capital investment in these facilities by minimizing the cumulative effects of
wear and deterioration.
b. Ensure that these facilities are continuously available and that they operate at peak
efficiency.
c. Improve the capabilities and usefulness of these facilities and thereby mitigate the
effects of obsolescence.
d. Provide a better and safer environment for all personnel.
This program includes only facility rehabilitation and modification work having an estimated
cost not in excess of $1.5 million. The work is of such a nature and magnitude that it cannot
be accomplished by routine day-to-day facility maintenance or by related routine facility work
efforts.
PROJECT DESCRIPTION:
Proposed rehabilitation and modification projects for FY 1996 totaling $35 million are described
under PROJECT COST ESTIMATE. The total program of $35 million has been distilled from requests
of $58 million and represents only a modest request in relation to the backlog of this type of work.
Based on relative urgency and expected return on investment, the projects that comprise this request
are the highest priority requirements. Deferral of this mission-essential work would adversely affect
the availability of critical facilities, program schedules, and energy-conservation objectives.
Projects estimated to cost not in excess of $250,000 have not been described individually or
identified by center. The total request for this category is $480,000.
During the course of the year, some rearrangement of priorities may be necessary. This may
force a change in some of the items to be accomplished. Any such change will be accomplished
within available resources. The following broad categories of work are described further
in the PROJECT COST ESTIMATE:
a. Utility Systems $5,715,000
b. Fire Detection/Protection Systems 4,505,000
c. General Purpose Buildings 7,655,000
d. Technical Buildings/Structures 17,125,000
PROJECT COST ESTIMATE:
A. Ames Research Center (ARC)........................................ $3,740,000
1. Rehabilitation and Modification of the Bioscience
Lab HVAC System (N236).......................................... 390,000
This project includes removal and replacement of two main and one backup chilled
water plants in the Bioscience Laboratory. It includes system controls, mechanical
room chilled water piping, and pumps. Temperature control is critical in this building,
which houses research animals and laboratories. The equipment is at the end of its
useful life and in poor condition. Replacement parts cannot be obtained and the
required temperatures cannot be consistently maintained.
2. Rehabilitation and Modification of Fire Suppression System,
Flight Guidance and Simulation Laboratory (N243)................. 630,000
This project will install a new wet pipe automatic sprinkler system in the Flight
Guidance and Simulation Laboratory. Exit corridors will be reconfigured to meet
safety egress requirements. Work includes sprinklers, flow alarms, associated piping,
and corridor modifications. This building contains 10,000 square meters of unsprinklered
offices, computer rooms, and test laboratories. The existing fire alarm system is not
audible in all areas. Completion of this project will protect occupants from fire-related
injury and will protect the facility against destruction due to fire.
3. Rehabilitate Physical Science Research Laboratory
for Seismic Safety (N230)........................................ 260,000
This project provides for lateral structural reinforcement of the south window wall
and for strengthening of the roof diaphragm of the Physical Science Research Laboratory.
After the 1989 Loma Prieta Earthquake, Ames Research Center began studies to evaluate
the seismic resistance of center buildings. These studies show that this facility does
not meet minimum seismic safety standards. The occupants of the facility are endangered
because the building shear walls are not adequately braced in the lateral direction.
This structural defect will be corrected in this project.
4. Restore Flow Control in Arc Jet Laboratory (N-238)............... 900,000
This project will replace air and argon flow control systems for the Panel Test
Facility (PTF) and the Interactive Heating Facility (IHF) in the Arc Jet Laboratory.
The existing systems have been in operation since the early 1970Õs. Critical
parameters, such as energy enthalpy, are unobtainable with the obsolete control
systems. Replacement parts are no longer available. Principal investigators have
been unable to obtain critically needed flow data required for energy balance
measurements due to equipment failure and inaccurate instrumentation. This project
will increase flow measurement accuracy and decrease downtime.
5. Modify Steam System, Moffett Field ............................... 860,000
This project provides for installation of individual boilers in Buildings 14, 16, 19,
and 45 to replace the existing central steam heating system. The existing system
was built in 1945, requires frequent repairs, and must be monitored 24 hours/day.
Due to the high operational cost, it is more cost-effective to replace the existing
system with individual units than to replace it in kind.
6. Rehabilitation and Modification of Experiment
Support Facilities (N239A)......................................... 700,000
This project will rehabilitate and modify the Experiment Support Facilities in the
south central portion of the Life Sciences Research Laboratory High Bay. Existing
research areas will be consolidated and the Four-Foot centrifuge will be relocated.
The consolidation and relocation of the experimental support facilities proposed in
this project improve efficiency, expand the capability of ongoing programs, and enable
new research approaches with both animal and human subjects.
B. Dryden Flight Research Center (DFRC)................................ $900,000
1. Rehabilitation and Modification of Fire Alarm System.............. 900,000
This project includes replacement of 175 field sensors, replacement/installation
of Fire Alarm Control Panels in approximately 20 buildings, replacement of the
Central Reporting System at Security Post #1, and other rehabilitation as necessary
to comply with NASA and NFPA fire and life safety codes. The existing fire alarm
system is uncoordinated and unreliable. It is a hodgepodge of systems, some antiquated
and no longer supported by their manufacturer, and some are incompatible with the
buildingsÕ present uses. The increasing frequency of false alarms and the difficulty
of troubleshooting and maintenance makes rehabilitation and modification imperative.
C. Goddard Space Flight Center (GSFC).................................$2,920,000
1. Rehabilitation of Utility Control System......................... 850,000
This project will replace obsolete portions of the existing Utility Control System
(UCS) for Buildings 23 and 25 with a state-of-the-art Direct Digital Control UCS
System. Pneumatic automatic temperature controls and sensors will be replaced with
new digital systems to provide reliable inputs and independent local control of air
conditioning systems. This project is critical to providing effective energy
conservation. The existing obsolete UCS is primarily a monitoring system and has
incurred numerous operational problems such as software failures and inaccurate
sensor inputs. The new digital system will provide for an efficient, reliable,
and maintainable air conditioning control system.
2. Modification of Fire Detection Systems, Various Buildings......... 400,000
This project provides for the modification and upgrade to the existing fire detection
systems in Buildings 4, 11, 12, 20, 22, 24, 27, 28, Area 200, and Area 300. The
upgraded systems will include the fire alarm control panel, annunciator panels,
fire detectors, manual stations, alarms, and all wire and conduit. A master control
console will be installed in Building 24 for the fire alarm systems. The existing
fire detection systems are obsolete and replacement parts are not available. In order
to comply with current safety standards and provide reliable operation, upgrading the
fire alarm systems and replacing obsolete equipment are required.
3. Modification to Fire Protection Systems,
Building 16W and Optics Test Site.................................. 400,000
This project provides for modifications to the fire protection systems in Building
16W and at the Optics Test Site (200 Area). Modifications in Building 16W include
replacing inadequate standpipes, painting sprinkler piping for identification, and
correcting other deficiencies. At the Optics Test Site the existing fire pump and
water storage tank will be replaced. Building 16W has undersized standpipes and fire
department connections. The storage tank and fire pump at the Optics Test Site have
deteriorated and have become increasingly unreliable and difficult to maintain. This
project will provide for the increased safety of the building occupants and the
protection of property.
4. Rehabilitation and Modification of Anechoic Chamber (19).......... 900,000
This project provides for rehabilitation of the Anechoic Chamber located in Building
19, Room N2. The project scope includes removing the existing chamber superstructure
and microwave absorber, modifying its configuration, providing new pyramidal absorbers,
and providing a new antenna positioner within the chamber. The resultant chamber will
meet operating conditions at all projected frequencies of interest. Support spaces,
including a control room and a preparation room, will be provided. Required mechanical,
electrical, and fire protection system changes are included. The existing anechoic
chamber is aging and in need of rehabilitation. This project is necessary in order
to ensure efficient antenna development and testing.
5. Rehabilitation of Main Sewer System............................... 370,000
This project provides for rehabilitation of the main sewer system. The work includes
installing an additional 20 centimeter diameter pipe connection from the centers main
sewer to the Washington Sanitary Sewer Commission sewer, cleaning and inspecting
segments of the sewer system, resupporting dislocated pipe sections, providing a
sewage meter, and replacing various sewage ejector pumps. Recent studies indicate
that by 1997 the existing 20 centimeter diameter main sewer discharge will be
inadequate for the center. This project is required to rehabilitate the existing
sewer system and to meet additional demands on the system.
D. Jet Propulsion Laboratory (JPL)...................................$3,000,000
1. Modify Mirror Refurbishment Building (313)
for Environmental Testing....................................... 600,000
The project will modify Building 313 to allow installation of six thermo-vacuum
and temperature-humidity chambers currently located in Building 144. The work
includes constructing a concrete floor with removable hatchway over the 7 meter
diameter central pit, a central air conditioning system, a free standing shed to
protect mechanical equipment for the chambers, and a 750 kVA substation with
disconnect switch and 600 and 400 ampere switch boards.
The project includes construction of a compressed air line from an existing line
at Pioneer Road, addition of cooling water and return lines, and two secondary pumps
from a closed loop system. The project will provide a liquid nitrogen distribution
system to all thermal-vacuum chambers. Also, it will provide three instrumentation
and communications conduits from manhole-53 to interior of building 313. This project
is required to eliminate a potentially hazardous work environment due to overcrowding
for the safe handling, set up of operations, and testing of flight gear.
2. Modify Uninterruptible Power Supply (UPS),
Space Flight Operations (230)................................... 750,000
The project will install a third, approximately 450 kw, battery bank including
bus duct and switchgear. An existing workshop, Room 27, will be modified to accept
this equipment and existing electrical panels, transformers, and other work shop
equipment will be relocated to Room 20. Room 20 will be modified and reconfigured
to accommodate the personnel and equipment from Room 27. The project is required
to improve overall UPS system reliability. Each UPS module will become a stand alone
system. The additional battery string will significantly extend the UPS capability
to support JPL Deep Space Network operations with lower risk from power outages.
3. Modify Information Systems Development Building (126)............ 900,000
The project will modify three floors of this building. The project will also
upgrade the passenger elevator, relocate the machine room, and construct a corridor
from the elevator to the entrance lobby. A stairway will be constructed to serve
the first and second floors from the lobby area. The second and third floor restrooms
will be modified for access by the disabled. Work includes new carpeting;
modifications to the ceiling systems; and modifying the HVAC, power, lighting, and
fire sprinkler systems. A new restroom facility to accommodate the disabled will be
added to the first floor. The project is needed to house multiple and varied project
requirements, and to satisfy building code and disabled accessibility requirements.
4. Modification to Low Temperature Physics Facility (79)............ 750,000
This project will rehabilitate approximately 650 square meters of deteriorated
space in the western half of Building 79 and make provisions for access by the
disabled. Exposed electrical conduits and HVAC duct work will be rerouted and
abandoned conduits will be eliminated. Worn carpets and old deteriorated ceiling
and lighting systems will be replaced. Low corridor ceilings will be raised and
sloping floors on the second floor will be removed. New ceiling and lighting will
be provided to replace the deteriorated system. Window awnings will be provided
to the southwest end of the building to provide shade from direct sun light. A
lift for the disabled will be installed, the restrooms will be enlarged,
and additional fixtures added to comply with the uniform plumbing code.
The corridor system will be widened and reconfigured to meet building and disabled
accessibility codes. Approximately 260 square meters of eroding roadway will be
replaced with new concrete curbs and swales.
E. Johnson Space Center (JSC).......................................$3,250,000
1. Upgrade Mission Support Chillers (48).......................... 900,000
This project provides for the replacement of a 2,460 kW chiller, with a 3,516 kW
chiller and replacing the chloroflorocarbon (CFC) refrigerant on the remaining
three chillers (two 2,110 kW and one 3,516 kW) in the Emergency Power Building,
building 48. The work also includes replacing deteriorated structural steel
members and installing two 37,850 liter diesel storage tanks. This upgrade is
required because the existing chillers are too small to satisfy mission support
requirements and the chillers use CFC refrigerant which must be replaced to meet
environmental regulations. This project is necessary to stay within mission-critical
guidelines.
2. Modifications to Photographic Technology Laboratory (8)........ 900,000
This project provides for modifications to the mechanical, electrical, and
architectural systems in the building. Work includes replacing six air handlers,
six exhaust fans, five condensing units, and associated piping. The fire suppression
system will be expanded and upgraded. Also, included will be the replacement of area
ceilings and installation of new lighting. Spot asbestos abatement will be performed
as required. Past methods of processing photographic images have caused damage to the
facility. This project is required to repair this damage and comply with Life Safety
and Uniform Building Code requirements.
3. Modifications to Mission Simulation and Training Facility (5).... 550,000
This project provides for modifications to the mechanical, electrical, and
architectural systems in the facility. Work includes modifications to support
the installation of International Space Station mockups and a cupola. Structural
platforms and a new stairway are required for the cupola installation. The project
is required to support activities which include the transition form a single operator
console to multi-operator workstations, the introduction of fiber optics, and
additional workstation console requirements to support the glass cockpit to be
utilized in Space Station simulators. This project supports verification and
training programs. The existing facilities and equipment are not configured
to support planned programs.
4. Modifications for Efficient Small Engine Testing, WSTF........... 900,000
This project provides for the modification to the existing 400 Area gaseous
nitrogen altitude simulation system by using steam instead of gaseous nitrogen
as the working medium. The steam supply system will incorporate water treatment,
de-aeration, transfer pumps, boilers, and a fuel supply. The replacement system
will be housed in an approximately 370 square meter pre-engineered building near
the diesel pump pad in the 400 Area. The existing gaseous nitrogen supply system
will be disconnected and the steam will be piped to new individual first stage and
second stage ejectors. Operation of the steam system will be controlled from a
control console and at the ejectors. Other services required (gaseous nitrogen,
power, communications and paging, fire alarms, etc.) will be extended from the
existing facility systems to the pre-engineered building housing the steam system.
Currently, long duration tests of engines up to 4,450 newtons thrust use the 400
Area altitude system. This modification will provide a significant operational
cost savings.
F. Kennedy Space Center (KSC)$3,160,000
1. Upgrade Operations and Checkout Building Elevators and Controls... 400,000
This project replaces obsolete controls, valves, motors, and cables associated
with elevators 2, 3, and 4 in the Operations and Checkout Building. New components
are state of the art and will reduce maintenance and power consumption. Further,
handicapped and fire alarm modifications will enhance personnel safety and result
in the elevators complying with applicable codes.
2. Upgrade Facilities to Accommodate People With Disabilities,
Various Locations................................................ 500,000
This project modifies various buildings to make the facilities more accessible
to the disabled. This effort reflects the increasing population of people with
disabilities at KSC, and is intended to meet the requirements of Title 28, Code
of Federal Regulations, Part 36. Work includes specialized parking, removal of
curbs, installation of automatic entry doors, and lowered light switches/fire
alarm stations. Restrooms, drinking fountains, and public telephones will be
modified. Special signage, visual alarms, and audio alarms will be installed.
3. Upgrade Fire Protection System in Logistics Warehouse Area...... 600,000
This project will upgrade the fire alarm and fire fighting features of the
KSC Logistics Warehouse and Petroleum/Oil/Lubricant (POL) storage area, bringing
them into compliance with applicable fire codes. Sprinkler heads will be added,
extended, replaced, and relocated; fire pump controls and monitoring systems
will be upgraded; fire alarm panels will be rearranged for improved access;
and various hazardous material enclosures will be upgraded to a higher fire rating.
4. Rehabilitate Hypergol Maintenance Facility Firex Pump Station.... 710,000
This project rehabilitates the Hypergol Maintenance Facilities firex pump station,
including replacement of the 37 year old fire pump engines and upgrade of the 20
year old control systems. Increasing potential for firex system failure and extended
downtime for maintenance due to a lack of availability of spare parts is intolerable.
Facilities protected by this fire system directly support Space Shuttle and Expendable
Launch Vehicle payload processing and are mission critical.
5. Restore Heavy Equipment Facility Maintenance Yard................ 500,000
This project will restore approximately 13,000 square meters in the vicinity of
the heavy equipment storage area. Part of the area will be paved with asphaltic
or portland cement concrete. The remainder of the area will be resurfaced with
stabilized gravel. This project will allow percolation of storm water falling
on the parking areas, eliminating direct runoff into existing wetlands, in violation
of St. JohnÕs River Water Management District regulations. The new pavement
eliminates problems associated with sandy materials that invade the parked heavy
equipment, thus increasing maintenance and shortening component life.
6. Replace Lighting in Launch Control Center Firing Rooms 1-4....... 450,000
This project replaces approximately 850 lighting fixtures in the KSC Launch
Control Center Firing Rooms 1-4 with an improved state-of-the-art system.
The improved lighting system will enhance reliability of illumination in these
launch-critical areas and lower maintenance costs. The new system will also
provide significant energy efficiency which is part of a center-wide effort to
comply with the executive order to reduce power consumption 20% by the year 2000.
G. Langley Research Center (LaRC)...................................$3,360,000
1. Modifications to the 60-Foot Space Simulator (1295)............ 820,000
This project provides for the installation of a new steam ejector system at the
60-Foot Space Simulator facility. The new steam ejector system will include all
controls, pumps, valves, and instrumentation, as well as connection to the existing
cooling tower water system, steam and condensate systems, and the vacuum system
which currently serves the facility. The present system requires approximately
3 hours to evacuate the three spheres from 33,350 Pa to 1,330 Pa. This project
will reduce the pump down time for these three vacuum spheres by a factor of six,
thereby significantly increasing the productivity of the two hypersonic wind
tunnels it serves.
2. Modifications to Upgrade Forced Oscillation Test Rig (1212C)..... 680,000
This project provides for upgrades of the forced oscillation model test rig in
the 14- by 22-Foot Tunnel. The new rig will be capable of handling models up
to 90 kilograms with motion accuracy of plus or minus 0.17 degrees over an
oscillation amplitude ranging from 0 to plus or minus 30 degrees. The existing
20 year old rig is badly worn and excessive motion between components is adversely
affecting data accuracy. The new forced oscillation rig will provide increased
data accuracy and reliability, as well as increased productivity due to reduced
setup time.
3. Modifications to the 15-Inch
Mach 6 High Temperature Tunnel (1251A)........................... 400,000
This project provides modifications to the 15-Inch Mach 6 High Temperature
Tunnel located in Building 1251A. The modifications include a new flow
collector downstream of the nozzle exit, a variable area diffuser and
associated controls, a new after-cooler, and associated modifications to
the vacuum piping connecting the test section to the vacuum sphere. The
subject diffuser is needed to provide the capability to test larger models.
Productivity and efficiency of this heavily utilized facility will be
enhanced by implementation of these modifications.
4. Modifications to Building 1221C for the Combustion
Diagnostics Laboratory........................................... 750,000
This project provides for modifications to Building 1221C to create a new
Combustion Diagnostics Laboratory. The modifications will include construction
of the new 125 square meter laboratory within Room 123 of Building 1221C and
installation of all utilities necessary for the laboratory. The utilities will
include combustion air, fuel, oxygen, exhaust system, instrumentation and controls,
electrical power, air conditioning, and cooling water. The Combustion Diagnostic
Laboratory will provide ÒbreadboardingÓ space for development of techniques for
nonintrusive combustion diagnostics. The laboratory will provide steady state
flame sources and/or supersonic reacting flow for definition of the operating
characteristics of various nonintrusive combustion diagnostic devices.
5. Rehabilitation of Instrumentation and Calibration Labs, Shop,
and HVAC System at Building 648................................ 440,000
This project provides for rehabilitation of the instrumentation and calibration
labs and shop at Building 648, which houses the Transonic Dynamics Tunnel, to
provide space for wind-tunnel and model instrumentation development, model static
testing and calibration, and model preparation and assembly. The rehabilitation
will include enclosing an existing area to provide an instrumentation lab,
refurbishing the model calibration lab and shop, and upgrading the HVAC through
the northeast portion of the building. The project will include replacement
of floor tiles, wall treatment, ceiling, and lights; modifications to entrances
and walls; removal of an obsolete air lock; and upgrade of electrical panel boards.
The rehabilitation project will enhance the support activities for the tunnel
and provide improved efficiency and productivity.
6. Rehabilitation of Fabrication Shop (1232A)..................... 270,000
This project provides for modifications to and rehabilitation of the 50 year
old Fabrication Shop in Building 1232A. The modifications include constructing
a sound barrier wall between the shop area and the techniciansÕ work bench area,
installing a masonry wall where roll-up doors currently exist in Rooms 129 and
130 and installing new air conditioning system(s) for those rooms, and installing
circulation fans in the high bay area. The rehabilitation of the building includes
reworking the first floor restroom to include a restroom for women and replacing
the overhead steam coil heating units in the shop area. This project will bring
conditions into compliance with current standards and provide a safe and efficient
facility.
H. Lewis Research Center (LeRC).....................................$3,260,000
1. Rehabilitation of Mechanical Systems,
Development Engineering Building (500)......................... 900,000
This project provides for the rehabilitation of the mechanical systems in the
Development Engineering Building (DEB) (500). This work includes replacement
of two existing 260 ton, R-12 refrigerant chillers with two new 1,230 kilowatt
chillers that will operate with an environmentally safe refrigerant. This project
will also replace fan coil units, chilled water lines, and remove related asbestos
insulation. The existing 30-year-old chillers are undersized and inefficient for
air handling needs of the air conditioning system.
2. Rehabilitation of 10X10 Wind Tunnel Office Building (86)........ 860,000
This project provides for rehabilitation of the 10X10 Supersonic Wind Tunnel Office
and Control Building. The work includes rehabilitation of the building electrical
power, office lighting and ceiling systems, and compliance with life safety
requirements. The building is underpowered and the electrical system contains
a number of code violations. This project will upgrade the electrical system
to comply with present codes and provide sufficient power and efficient lighting
for this facility.
3. Modifications of Chilled Water Plant (94)....................... 900,000
This project will provide modifications to the Chilled Water Plant at Building 94.
The work includes replacement of the two existing inoperable 180 ton chillers and
associated pumps, piping, and electrical services with a new 4,220 kilowatt chiller.
Presently, the connected cooling loads exceed the chiller capacity available in
Building 94. The new chiller will increase the plant efficiency and capacity to
meet the current institutional and research loads.
4. Rehabilitation of Mechanical and Electrical Systems,
Energy Conversion Laboratory (302).............................. 600,000
This project provides for the rehabilitation of the mechanical and electrical
systems in the Energy Conversion Laboratory (ECL) (302). This work includes
installation of two heating hot water boilers and controls, four air handler
units, coils and piping ductwork, and controls for first and second floor labs.
This project will also replace approximately 25-30 lab exhaust fans and provide
an electrical system upgrade to support new boilers, air handlers, and exhaust fans.
The existing air handlers in the ECL (302) are 30 years old and in constant need
of maintenance. The new electrical and mechanical systems will provide efficient,
reliable, and economical operations for the ECL.
I. Marshall Space Flight Center (MSFC)..............................$3,580,000
1. Rehabilitate Exterior of Office and Testing Facility (4732).... 900,000
This project provides for the rehabilitation of the exterior of Building 4732.
Work includes providing thermal protection to exterior walls by installing
insulation, face brick, and insulated glass windows. Also included is the
installation of a sloped standing-seam metal roof system over the existing
flat roof, the modification of the building entrances and parking, and
improvements to the storm drainage system. Building 4732 is 51 years old,
poorly insulated, and has severe moisture penetration problems. The proposed
rehabilitation will preserve the integrity of the facility, provide an energy
efficient and low maintenance building envelope, and upgrade handicapped
accessibility to current standards.
2. Rehabilitate Laboratory Building (4623)........................ 900,000
This project provides for the rehabilitation of Building 4623. Exterior work
includes the installation of insulation, face brick, insulated glass windows,
and a new sloped standing-seam metal roof system. Parking will be upgraded
to asphaltic concrete and surrounding areas will be graded to improve drainage.
Interior work includes the replacement of the heating, ventilation, and air
conditioning system; the restoration of the electrical distribution system;
and the renovation and reconfiguration of the interior walls, ceilings,
restrooms, interior lighting, and emergency exit signs. Building 4623 is
a 700 square meter laboratory facility. It is 34 years old and maintenance
intensive. The proposed rehabilitation will preserve the integrity of the
facility, provide an energy efficient and low maintenance building envelope,
upgrade the facility to current Life Safety and Handicapped Accessibility
standards, reduce operations and maintenance costs, and greatly improve
the functionality of the facility.
3. Modifications to Electrical Power System (4755)................ 610,000
This project provides for modifications to the electrical power system in the
Multi-Purpose High Bay Facility. Work to be performed includes the installation
of a new 4,160/480 V transformer, a 1,000 kVA emergency power generator with
associated switch gear, power panels, and a 90 square meter enclosure. The
project also provides for the modification and upgrade of the existing electrical
switch gear and power panels. The proposed upgrades are required to support the
Environmental Control and Life Support System testing being conducted in support
of the Space Station program.
4. Upgrade of Utility Control System Data Channel
and Control Capability......................................... 900,000
This project provides for modifications to the MSFC Utility Control System (UCS)
to upgrade and modernize its data channel and control capability. Work includes
addition of computer capability to the individual building-field interface device
terminals, and expanding the existing system from 10,000 to 100,000 data and control
points. Data processing hardware and software will be upgrade as required. The
UCS controls most of the heating, ventilation, and air conditioning systems, as
well as critical alarm functions at MSFC. Despite the shortcomings of the existing
UCS, it is heavily utilized for energy management and plant maintenance. This
project will improve the system's speed, capability, and reliability.
5. Modifications to North Low Bay of Productivity
Enhancement Facility (4707)..................................... 270,000
This project provides for the conversion of the north low bay area of the Productivity
Enhancement Facility, Building 4707, from office to laboratory space. Scope includes
the installation of a heating, ventilation, and air conditioning system capable of
providing make-up air to support chemical fume hoods, and with positive air pressure
and replaceable HEPA filters for control of particulate contamination. The
laboratories will be equipped with stainless steel laboratory furniture, hoods,
lay-up tables, potable water, sinks/drains, and special utilities, as needed.
Laboratory space is required to house activities in support of environmental
replacement technologies, general adhesive bonding technology, and thermal analysis
and mechanical tests functions. These activities require special environmental
control to achieve material characterization and processing properties.
J. Michoud Assembly Facility (MAF).................................$1,350,000
1. Rehabilitate Fire Water Piping System......................... $500,000
This project provides for the rehabilitation of the fire protection piping system
serving Buildings 101, 102, and 103. Scope includes replacement of approximately
1,500 meters of outer perimeter mains and system components, post indicator valves,
automatic sprinkler risers, and sectional control valves. The existing fire
protection system is 1940Õs vintage. The mains and sprinkler risers are severely
corroded, leak extensively, and are below the minimum thickness required by code.
Valves are faulty and do not hold or close properly.
2. Rehabilitate North Chilled Water Overhead Piping (103)......... $850,000
This project provides for the restoration and upgrade of approximately 1,400 meters
of overhead chilled water return and supply piping in the External Tank Main
Manufacturing Building. The new piping will be routed differently than the
existing piping to improve accessibility and maintainability. Work to be done
also includes the replacement of existing valves, or the addition of new valves,
as required. The chilled water piping system was originally installed in the 1940s
and is very deteriorated. Pipe wall thickness has decreased by 50 percent in some
areas due to severe corrosion, and current configuration does not provide sufficient
valves to adequately isolate problem areas during outages. Lack of easy access to
piping makes piecemeal repairs difficult and costly.
K. Stennis Space Center (SSC).......................................$2,400,000
1. Modification of Central Heat Plant Facility (B3204)...............900,000
This project provides for modification of the Central Heat Plant (B3204) to provide
for the relocation of the center Fire Department and emergency response services.
The work includes removal of three abandoned hot water generators and associated
piping, tanks, pumps, and chemical feed stations. The existing 650 square meters
will be modified to accommodate fire department apparatus; monitoring and alarm
equipment; dormitory, classroom, and office space; parking bays for pumpers and
emergency response vehicles; and host drying apparatus. Work also includes asphalt
paving for training drills and adequate parking for facility personnel. The project
places critical fire protection services in close proximity to the key operations
the fire department is required to support.
2. Rehabilitate Administration and Engineering Building (B1100).......900,000
This project provides for rehabilitation of the air handler units in the
Administration and Engineering Building. Work includes replacement of air
handlers, repair of return air fans, and replacement of noise attenuators
with straight duct sections and associated asbestos removal. The existing
units have exceeded their useful life with components over 30 years old which
have deteriorated beyond repair.
3. Modify Utility Control System, Various Locations...................600,000
This project provides for modifications to the Utility Control System (UCS). The
work includes replacement of the pneumatic controls and refurbishment of the air
handling units for buildings 1000, 2040, and 3110. The existing UCS and HVAC
systems are more than 20 years old and many parts are no longer available for
the system. This project will provide for an efficient, reliable, and maintainable
energy management system.
L. Wallops Flight Facility (WFF).......................................$890,000
1. Rehabilitation of Aircraft Hangar (N-159)......................... 390,000
This project provides for the modification of the exterior building siding and
roof top structures of this aircraft hanger. The work includes the removal of
existing protected metal siding and windows; the installation of new protected
steel siding, secondary support steel framing, batt insulation, metal liner panel,
flashing and trim, guttering, downspouts, and splashblocks. The existing metal
siding on this 35 year old hangar has outlived its life expectancy. It is damaged
in places and the protective coating is cracked and peeling off. The windows in
the hangar area leak and serve no useful purpose. The new metal panel system will
provide a strong protective covering for the hangar and upper mechanical rooms,
insulation to eliminate heat loss, and a more pleasing appearance to such a sizable
structure.
2. Modification of Rocket Assembly Building Z-41..................... 500,000
This modification consists of the removal of steel, repair of the roof, and the
installation of fire protection and grounding system; the installation of two
9,000 kilogram bridge cranes in the high bay area; the upgrade of overhead
lighting and electrical power panels; the replacement of overhead and personnel
doors; the painting of interior/exterior finishes; the rehabilitation of the
restroom; and associated work. Building Z-41 is a high bay vertical assembly
building strategically located to provide support to the launch facilities on
Wallops Island. The building is 25 years old and is in need of rehabilitation
due to age, deterioration, and exposure to the Island environment.
M. Various Locations.....................................................$2,710,000
1. Rehabilitate and Modify Feedcone for 70-Meter Antenna,
Goldstone, California..................................................710,000
This project will provide for a new Feedcone shell to house microwave equipment,
transmitter, waveguide switches, and maser. A Dichroic mirror and retraction
mechanism will be fabricated and tested. This project is required to expand
the capability of the 70-meter antenna to provide both X-band uplink and downlink
support to flight projects.
2. Modify Power Distribution System, Goldstone, California................600,000
The project will convert the existing 2400 V radial distribution system to a loop
system. The loop system will be fed from two existing 2400 V breakers so that if
one of the breakers fails or is out for maintenance, the other breaker is capable
of serving the connected load without any interruption. The project includes the
installation of additional 2400 V cables, ducts and trenches to complete the loop
system, a new substation at DSS-15 antenna, and the modification of the power plant
programmable controller to adapt it to the new configuration. This will improve
maintainability, redundancy, and will allow isolation and testing of the 20 year
old system.
3. Modify 34-Meter Antenna (DSS-28), Goldstone, California................500,000
This project will implement site and structural changes to the antenna facility
which include fencing around the antenna apron, seismic bracing for electronic
equipment, and cable trays. Also, electrical modifications will be made to the
pedestal, a fire detection and a safety surveillance system will be installed,
and a prefabricated metal building for a motor generator set will be constructed.
Redundant air conditioning will be installed at DSS-27 and DSS-28. Operational
requirements for DSS-28 require these modifications to meet safety requirements
and back-up cooling capacity for critical electronic equipment.
4. Modification to Launch Area #4, Poker Flats Research Range............900,000
This project provides for the modification to Launch Area #4 located at Poker Flats,
Alaska. It includes sitework; elevation of rails on a concrete base; installation
of a insulated mobile shelter with rollup doors; a 16.2 square meters terminal
building; and the installation of power and lighting. The purpose of the
modification is to provide safety and protection for personnel and flight components
from severe weather conditions during the final staging and checkout of sounding
rockets on the launcher.
N. Miscellaneous Projects Not in Excess of $250,000.......................$480,000
Total..........................................................$35,000,000
FUTURE ESTIMATED CONSTRUCTION FUNDING REQUIRED:
Approximately $40-50 million per year will be required for continuing rehabilitation
and modification needs.
CF-3.3