Executive Summary
| Introduction |
On April 15, 1996, NASA signed a tripartite agreement with AlliedSignal
Technical Services (Allied) and Computer Sciences Corporation (CSC) to
provide support services for network and mission operations; systems,
engineering, and analysis; and operations and maintenance of radar
telecommunications. The agreement consolidated three existing support
service contracts
(1) into Allied contract NAS5-31000, the
Consolidated Network Missions Operations Support (CNMOS) contract. The
CNMOS contract is a cost-plus-award-fee contract with total negotiated
costs of about $1.8 billion. The former Mission Operations and Data Systems
Directorate (Code 500) at Goddard Space Flight Center led the consolidation
effort because two of the prior contracts supported Code 500 divisions.
NASA policy is to implement performance-based contracting (PBC), (2) wherever feasible, to produce contract savings. In October 1996, Allied and NASA negotiated $34.8 million in a contract cost reduction. The reduction represented the costs that were avoided by consolidating the three contracts. NASA agreed to share 20 percent of the negotiated savings with Allied, or about $7.2 million.
|
| Objectives |
The audit objectives were to determine whether:
|
| Results of Audit |
Allied has complied with reporting requirements of the cost savings sharing clause. Additionally, NASA adequately planned to provide services, through a contract extension, from October 1, 1997, until the award of the CSOC. However, the Allied cost reduction proposal for the period April 15, 1996, through September 30, 1997, overstates savings by about $9.0 million. As a result, Allied received $1.8 million more than entitled under the contract's cost savings sharing clause. |
| Recommendation |
The Agency should seek a recoupment of the overstated share of savings paid
to Allied.
|
| Management Response and Evaluation of the Response |
Nonconcur. Management stated that the audit calculations were inaccurate.
Further, the audit methodology used two separate time periods rather than
the single contract performance period. No overstated savings occurred, and
there is an inadequate basis for recoupment of savings.
In response to management's nonconcurrence, we reaffirm our position, taking into account new data Goddard Space Flight Center provided in its response that was not available during the audit. We revised the finding to reflect the new data presented, which did not change our position but did reduce the overstated savings by $.2 million, and we request additional comments on the final report.
|