Executive Summary
| Introduction |
Office of Management and Budget Circular A-127, "Financial Management
Systems," requires Federal agencies to maintain a single, integrated
financial management system. To fully comply with the circular, NASA
established the Integrated Financial Management Project (IFMP), which will
also facilitate compliance with other statutory and regulatory requirements
including the Federal Financial Management Improvement Act of 1996. See
Appendix B for the applicable requirements.
On September 18, 1997, NASA awarded a fixed-price contract, valued at $186 million, to KPMG Peat Marwick (KPMG) to provide commercial-off-the-shelf (COTS) software for, and to implement NASA-wide, the IFMP. The contract required that the IFMP be implemented at all NASA Centers by July 1, 1999. On February 26, 1998, KPMG notified NASA that it would not meet key elements of the contract delivery schedule. NASA issued a contract modification that recognized a revised delivery schedule and allowed additional costs of up to $7.1 million for an extended delivery schedule. On December 1, 1998, KPMG made an incomplete delivery of the IFMP system to the IFMP Integrated Test Facility (IITF) - the first major milestone under the revised delivery schedule. The incomplete delivery of IFMP required further contract modification, and NASA was unable to determine the extent to which the incomplete delivery would impact the revised delivery schedule.
|
| Objectives |
The overall objective was to evaluate contractor performance on the IFMP.
Specifically, we determined whether:
|
| Results of Audit |
From its inception, the IFMP contract experienced significant performance
problems. In 18 months since the contract award, the project has experienced
a delivery schedule slip of 11 months with additional schedule slippage
pending, and the COTS software that KPMG promised to be available at
contract award is still incomplete. The delay in implementing IFMP will
prevent NASA from meeting Federal financial management system requirements
and will result in material costs to the agency. Additionally, the IFMP as
delivered, may not fulfill Federal financial management system requirements
in areas such as agency reports, standard general ledger, receipts
management, and payment management and will require additional testing by
NASA to ensure that those requirements are met.
Since contract award, NASA has taken steps to ensure the success of IFMP. The Agency has implemented a contractor surveillance plan to better monitor KPMG's performance on IFMP. NASA has also prepared a contingency plan to better prepare itself in the case of further problems with contractor performance.
|
| Recommendations |
The IFMP Director should:
|
| Management's Response |
Management concurred with the recommendations and has taken actions to
correct identified weaknesses. The complete text of the response is in
Appendix F.
|
| Evaluation of Management's Response |
Management's corrective actions planned or completed are responsive to the
recommendations.
|