PART 2 (D)
Design - Decision - Contract
July 1961 to September 1961
1961 July
1961 August
1961 September
July 6
At NASA Headquarters, the first meeting was held of the Manned Lunar
Landing Coordination Group, attended by NASA Associate Administrator
Robert C. Seamans, Jr., Ira H. Abbott, Don R. Ostrander, Charles H.
Roadman, William A. Fleming, DeMarquis D. Wyatt (part-time), and George
M. Low (in place of Abe Silverstein). This Headquarters Group, appointed
by Seamans, was to coordinate problems that jointly affected several
NASA Offices, during the interim period while the manned space flight
organization was being formed. Members of the steering group included
NASA program directors, with participation by Wernher von Braun of
Marshall Space Flight Center, Robert R. Gilruth of STG, and Wyatt and
Abraham Hyatt of NASA Headquarters, as required. Fleming acted as
Secretary of the Group. A list of decisions and actions required to
implement an accelerated lunar landing program was drawn up as a
tentative agenda for the next meeting:
- Begin Nova systems integration studies and develop the general
arrangement of second and third stages. The studies should include
spacecraft propulsion stages and spacecraft.
- Begin Saturn C-3 systems integration studies.
- Begin developing Nova and C-3 first-stage specifications in
preparation to letting contracts
- Continue Launch Operations Directorate-Air Force Missile Test Center
studies of Nova and C-3 launch sites at Atlantic Missile Range (AMR).
- Take steps to bring the contractor aboard as soon as possible for
Nova and C-3 launch facility and test stand designs.
- Accelerate F-1 engine funding to provide adequate production engines
for the Nova and C-3.
- Examine the Marshall Space Flight Center (MSFC) proposal for static
test facilities for large vehicle stages with a view toward beginning
detailed site examination.
- Accelerate funding of the J-2 engine to provide acceptance test
stands.
- Determine the necessity for a one-million-pound-thrust liquid-
hydrogen - liquid-oxygen engine.
- Begin design studies on spacecraft propulsion systems and develop
specifications. Define management responsibilities.
- Begin preparations for letting the contract for a spacecraft
operations facility at AMR.
- Determine the relationships and responsibilities of MSFC and STG on
guidance and control.
Memoranda, Low, Assistant Director for Manned Space Flight Programs, to
Director of Space Flight Programs, "Meeting of Manned Lunar Landing
Coordination Group," July 8, 1961; Ostrander, Director, Launch
Vehicle Programs, to Staff, "Manned Lunar Landing Program,"
July 10, 1961.
July 7
The NASA Administrator and the Secretary of Defense concluded an
agreement to study development of large launch vehicles for the national
space program. For this purpose, the DOD-NASA Large Launch Vehicle
Planning Group was created, reporting to the Associate Administrator of
NASA and to the Assistant Secretary of Defense (Deputy Director of
Defense Research and Engineering).
Memorandum, Associate Administrator to the Administrator, "Planning
of a DOD - NASA Program for Development of Large Launch Vehicles,"
July 7, 1961; letters, James E. Webb to Robert S. McNamara, July 7,
1961; McNamara to Webb, July 7, 1961.
July 12
Jet Propulsion Laboratory announced that construction was under way on
the first large space simulator in the United States capable of testing
full-scale spacecraft of the Ranger and Mariner classes. Three primary
space effects could be simulated: solar radiation, cold space heat sink,
and a high vacuum equivalent to about one part in a billion of the
atmospheric pressure at sea level.
Aeronautical and Astronautical Events of 1961, p. 32.
July 18-26
A NASA-Industry Apollo Technical Conference was held in Washington,
D.C., for representatives of about 300 potential Project Apollo
contractors. Scientists from NASA, the General Electric Company, The
Martin Company, and General Dynamics/Astronautics presented the results
of studies on Apollo requirements. Within the next four to six weeks
NASA was expected to draw up the final details and specifications for
the Apollo spacecraft.
Wall Street Journal, July 18, 1961; Aeronautical and
Astronautical Events of 1961, p. 33; "Apollo Spacecraft
Chronology," p. 10.
July 20
The Large Launch Vehicle Planning Group, established on July 7, 1961,
began its formal existence with seven DOD and seven NASA members and
alternates. The members of the Group included : Nicholas E.Golovin,
Director of the Group, Technical Assistant to the Associate
Administrator of NASA; Lawrence L. Kavanau, Deputy Director of the
Group, Special Assistant (Space) in the Office of the Director of
Defense Research and Engineering; Warren Amster and Edward J. Barlow,
Aerospace Corporation; Aleck C. Bond, STG; Lt. Col. David L. Garter and
Col. Otto J. Glasser, Air Force Systems Command; Col. Matthew R.
Collins, Jr., U.S. Army, Office of Chief of Ordnance; Eldon W. Hall,
Harvey Hall, and Milton W. Rosen, NASA Office of Launch Vehicle
Programs; Wilson B. Schramm and Francis L. Williams, Marshall Space
Flight Center; Rear Adm. Levering Smith, U.S. Navy, Special Projects
Office ; Capt. Lewis J. Stecher, Jr., U.S. Navy, Office of the Chief of
Naval Operations; H. J. Weigand, Headquarters, U.S. Air Force; Kurt R.
Stehling, NASA Office of Program Planning and Evaluation; and William W.
Wolman, NASA Office of Programs.
The Group, frequently called the Golovin Committee, was to concern
itself only with large launch vehicle systems, including propulsion
elements, guidance and control, and instrumentation. It was to suggest
launch vehicle configurations and operational procedures, taking into
consideration not only the manned lunar landing program but other
anticipated needs of DOD and NASA. Report of DOD-NASA Large Launch
Vehicle Planning Group, Vol. 1, 1961.
July 21
Liberty Bell 7, manned by Astronaut Virgil I. Grissom, was
launched successfully from the Atlantic Missile Range. The Mercury
capsule, boosted by a Redstone rocket, reached a peak altitude of 118.26
miles and a speed of 5,168 miles per hour. After a flight of 15 minutes
and 37 seconds, the landing was made 302 miles downrange from the launch
site. The spacecraft was lost during recovery operations, but Astronaut
Grissom was rescued and was reported in excellent condition.
Swenson et al., This New Ocean, pp. 370-377,
640-641.
July 24
Changes in Saturn launch vehicle configurations were announced :
- C-1:
- Stages S-I (1.5 million pounds of thrust) and S-IV
- C-2:
- Stages S-I, S-II, and S-IV
- C-3:
- Stages S-IB (3 million pounds of thrust), S-II, and S-IV.
Senate Staff Report, Manned Space Flight Program, p. 200.
July 24
NASA issued a letter contract to the Astro-Electronic Division of Radio
Corporation of America to develop and fabricate the high-resolution
television system (including associated communication and electronic
equipment) for the Ranger program.
Sixth Semiannual Report of the National Aeronautics and Space
Administration, July 1, 1961, through December 31, 1961 (1962),
p. 66.
July 28
NASA invited 12 companies to submit prime contractor proposals for the
Apollo spacecraft by October 9: The Boeing Airplane Company, Chance
Vought Corporation, Douglas Aircraft Company, General Dynamics/Convair,
the General Electric Company, Goodyear Aircraft Corporation, Grumman
Aircraft Engineering Corporation, Lockheed Aircraft Corporation,
McDonnell Aircraft Corporation, The Martin Company, North American
Aviation, Inc., and Republic Aviation Corporation.
In the Statement of Work sent to each prospective bidder, three phases
of the Apollo program were described:
- Phase A:
- Manned low-altitude earth orbital flights of up to two weeks'
duration and unmanned reentry flights from superorbital velocities. The
spacecraft designed for these missions should be capable of development
for the lunar landing and return. The objectives of Phase A were to
qualify the spacecraft systems and features for the lunar landing
mission within the constraints of the earth orbital environment, to
qualify the heat protection and other systems for the lunar mission
through reentry tests from superorbital velocities, to study the
physiological and psychological reactions and capabilities of human
beings under extended periods in the space environment, to develop
flight and ground operational techniques and equipment for space flights
of extended duration, and to conduct experimental investigations to
acquire information for the lunar mission. The Saturn C-1 would be used
for Phase A missions.
- Phase B:
- Circumlunar, lunar orbital, and parabolic reentry test flights
employing the Saturn C-3 launch vehicle for furthering the development
of the spacecraft and operational techniques and for lunar
reconnaissance.
- Phase C:
- Manned lunar landing and return missions using either the Nova class
or Saturn C-3 launch vehicles and using rendezvous techniques for the
purpose of lunar observation and exploration.
The contractor was to design and manufacture the command module, service
module, and spacecraft adapter with associated ground support equipment,
excluding the navigation and guidance system, research and development
instrumentation, and scientific instrumentation; to design and
manufacture the "test" spacecraft for use with Saturn C-1
research and development launch vehicles; to integrate the spacecraft
modules and to integrate these modules with their ground support
equipment and ensure compatibility of spacecraft with launch vehicle and
with the ground operational support system; and to design and
manufacture spacecraft mockups.
The contractor was to prepare the spacecraft for flight, man the systems
monitoring positions in the ground operational support system, and
support the operation of the overall space vehicle.
STG had prepared the Statement of Work, using both contractor and in-
house studies. Included in the Statement of Work was a description of
the major command and service module systems.
- Guidance and control system
- Navigation and guidance subsystem components:
- Stable platform
- Space sextant
- Radar altimeter
- Secondary inertial elements
- Computer
- Periscope
- Sun trackers
- Associated electronics
- Displays and controls
- Cabling
Stabilization and control subsystem to provide:
- Flight-path control during the thrusting period of atmospheric abort
and stability augmentation after launch escape system separation
- Orientation, attitude control, and reentry stabilization and control
during extra-atmospheric abort
- Stabilization of the spacecraft plus the final stage of the launch
vehicle while in a parking orbit
- Stabilization and control during translunar and transearth midcourse
flight
- Rendezvous and docking with the space laboratory module
- Attitude control for accomplishing landings and takeoffs from the moon
and for entering and departing from lunar orbits
- Control requirements for reentry guidance
- Stabilization and control of the command module flight direction in
the landing configuration, as well as the landing system suspension
members
- Vernier propulsion system
- The system would be included in the service module to provide
longitudinal velocity control not supplied by the reaction control
system, mission propulsion system, or lunar landing module; and to
furnish effective thrust-vector control during operation of the mission
propulsion system. It would be pressure-fed, using storable hypergolic
bipropellants.
- Mission propulsion system
- Representing the major portion of propulsion for translunar abort,
lunar orbit injection and rejection, and velocity increment for lunar
launch, the system would comprise a number of identical solid-propellant
rocket motors and would be included in the service module.
- Reaction control system
- The system would provide attitude control, stabilization, ullage for
the vernier propulsion system, and minor velocity corrections. For both
the command and service modules, the system would be pulse-modulated,
pressure-fed, and would use storable hypergolic fuel identical with that
in the vernier propulsion system. The fuel tanks would be the positive
expulsion type.
- Launch escape system
- During failure or imminent failure of the launch vehicle during all
atmospheric mission phases, the system would separate the command module
from the launch vehicle. The basic propulsion system would be a
solid-fuel rocket motor with "step" or regressive burning
characteristics.
- Earth landing system
- The system would consist of a ribbon drogue parachute and a cluster
of three simultaneously deployed landing parachutes, sized so that
satisfactory operation of any two of the three would satisfy the
vertical velocity requirement. The command module would hang in a canted
position from the parachute risers and be oriented through roll control
to favor impact attenuation.
- Structural system
- In addition to fundamental load-carrying structures, the command and
service modules would carry meteoroid protection, radiation protection
inherent in the structure, and passive heat protection systems.
- Crew systems
- Included were:
- Three couches, the center one stowable
- Support and restraint systems at each duty station
- Shock mitigation devices for individual crew support and restraint
systems
- Pressure suits for each crewman
- Sleeping area
- Sanitation area
- Environmental control system
- To provide a shirtsleeve environment in the command module, the
system would consist of:
- Cabin atmosphere - an oxygen-nitrogen mixture stabilized at 7.0 psia
- Removal of carbon dioxide by lithium hydroxide
- Removal of noxious gases by activated charcoal and a catalytic burner
- Heat-exchanger water-separation system for control of temperature and
humidity
- Potable water from the fuel cells
- Controls for pressure, humidity, and temperature
- Electrical power system
- The system would be composed of nonregenerative hydrogen-oxygen
Bacon- type fuel-cell batteries carried, with their fuel supply, in the
service module; silver-zinc primary batteries required during reentry
and postlanding carried, with their associated fuel, distribution, and
control equipment, in the command module.
- Communication and instrumentation system
- Communication subsystems:
- Deep-space communication
- Telemetry
- VHF transmitter and receiver
- Intercommunication system
- Near-field transceiver
- Television
- C-band transponder
- Altimeter and rendezvous radar
- Minitrack beacon
- HF/VHF recovery subsystem
- Antennas
Instrumentation subsystem:
- Sensors
- Data disposition (telemetry and onboard recorders)
- Subsystem calibration
- Auxiliary instrumentation (clock, cameras, telescope)
- Scientific equipment
- The equipment was unspecified but would be fitted into ten cubic
feet and weigh 250 pounds.
In addition to the description of the major command and service module
systems, the Statement of Work outlined the general concepts of the
lunar landing module and space laboratory module.
- Lunar landing module
- The basic systems comprised :
Lunar touchdown system to arrest impact, support the spacecraft during
its period on the moon, and provide a launching base
Guidance and control, provided by the command and service modules
Main propulsion system, for translunar velocity control and the gross
velocity decrement required for lunar landing, using liquid-hydrogen -
liquid-oxygen propellant
Terminal propulsion system, to provide propulsion and attitude reaction
control to perform the terminal descent maneuver, including hovering and
translation
Structural system, to meet the same requirements as specified for the
command and service modules
- Space laboratory module
- The module would be used in earth orbital flights for special
experiments. It would provide its own power supply, environmental
control system, etc., without demand on the command and service module
systems and could support two of the three Apollo crewmen except for
their food and water.
NASA, Project Apollo Spacecraft Development Statement of Work, Phase
A (STG, July 28, 1961), pp. 1-1 to 1-3, A-2 to A-21; New York
Times, July 29, 1961.
July 28
NASA Associate Administrator Robert C. Seamans, Jr., appointed members
to the Source Evaluation Board to evaluate contractors' proposals for
the Apollo spacecraft. Walter C. Williams of STG served as Chairman, and
members included Robert O. Piland, Wesley L. Hjornevik, Maxime A. Faget,
James A. Chamberlin, Charles W. Mathews, and Dave W. Lang, all of STG;
George M. Low, Brooks C. Preacher, and James T. Koppenhaver (nonvoting
member) from NASA Headquarters; and Oswald H. Lange from Marshall Space
Flight Center. On November 2, Faget became the Chairman, Kenneth S.
Kleinknecht was added as a member, and Williams was relieved from his
assignment.
Memoranda, Robert R. Gilruth to Member, Source Evaluation Board,
"Instructions for Members of the Source Evaluation Board for
Evaluation of Proposals for Project Apollo Spacecraft, RFP No.
9-150," September 1, 1961; Seamans to STG, "Redesignation of
Source Evaluation Board Members," November 2, 1961.
July 31
Phase I of a joint NASA-DOD report on facilities and resources required
at launch sites to support the manned lunar landing program was
submitted to Associate Administrator Robert C. Seamans, Jr., by Kurt H.
Debus, Director, Launch Operations Directorate, and Maj. Gen. Leighton
I. Davis, Commander of the Air Force Missile Test Center. The report,
requested by Seamans on June 23, was based on the use of Nova- class
launch vehicles for the manned lunar landing in a direct ascent mode,
with the Saturn C-3 in supporting missions. Eight launch sites were
considered: Cape Canaveral (on-shore); Cape Canaveral (off- shore);
Mayaguana Island (Atlantic Missile Range downrange); Cumberland Island,
Ga.; Brownsville, Tex.; White Sands Missile Range, N. Mex.; Christmas
Island, Pacific Ocean; and South Point, Hawaii. On the basis of minimum
cost and use of existing national resources, and taking into
consideration the stringent time schedule, White Sands Missile Range and
Cape Canaveral (on-shore) were favored. White Sands presented serious
limitations on launch azimuths because of first-stage impact hazards on
populated areas.
NASA-DOD, Phase I Report: Joint Report on Facilities and Resources
Required at Launch Site to Support NASA Manned Lunar Landing,
July 31, 1961.
During the Month
Langley Research Center simulated spacecraft flights at speeds of 8,200
to 8,700 feet per second in approaching the moon's surface. With
instruments preset to miss the moon's surface by 40 to 80 miles, pilots
with control of thrust and torques about all three axes of the craft
learned to establish orbits 10 to 90 miles above the surface, using a
graph of vehicle rate of descent and circumferential velocity, an
altimeter, and vehicle attitude and rate meters, as reported by Manuel
J. Queijo and Donald R. Riley of Langley.
Aeronautical and Astronautical Events of 1961, p. 36.
During the Month
James A. Chamberlin and James T. Rose of STG proposed adapting the
improved Mercury spacecraft to a 35,000-pound payload, including a
5,000-pound "lunar lander." This payload would be launched by
a Saturn C-3 in the lunar orbit rendezvous mode. The proposal was in
direct competition with the Apollo proposals that favored direct landing
on the moon and involved a 150,000-pound payload launched by a
Nova-class vehicle with approximately 12 million pounds of thrust.
Interviews with Chamberlin, Houston, Tex., June 9, 1966; Rose, St.
Louis, Mo., April 13, 1966.
During the Month
Ralph Ragan of the MIT Instrumentation Laboratory, former director of
the Polaris guidance and navigation program, in cooperation with Milton
B. Trageser of the Laboratory and with Robert O. Piland, Robert C.
Seamans, Jr., and Robert G. Chilton, all of NASA, had completed a study
of what had been done on the Polaris program in concept and design of a
guidance and navigation system and the documentation necessary for
putting such a system into production on an extremely tight schedule.
Using this study, the group worked out a rough schedule for a similar
program on Apollo.
Interview with Ralph Ragan, Instrumentation Laboratory, MIT, April 27,
1966.
July-September
The MIT Instrumentation Laboratory and NASA completed the work
statements for the Laboratory's program on the Apollo guidance and
navigation system and the request for quotation for industrial support
was prepared.
Interview with Ralph Ragan, Instrumentation Laboratory, MIT, April 27,
1966.
NASA Headquarters announced that it was making a worldwide study of
possible launching sites for lunar spacecraft. The size, power, noise,
and possible hazards of Saturn or Nova rockets would require greater
isolation for public safety than currently available at NASA launch
sites.
Washington Post, August 3, 1961.
August 6
The Soviet Union successfully launched Vostok II into orbit
with Gherman S. Titov as pilot. The spacecraft, which weighed 10,430
pounds, carried life-support equipment, radio and television for
monitoring the condition of the cosmonaut, tape recorder, telemetry
system, biological experiments, and automatic and manual control
equipment. After 17.5 orbits, the spacecraft reentered on August 7 and
landed safely. Titov made a separate parachute landing in an ejector
couch.
New York Times, August 7 and 8, 1961; Instruments and
Spacecraft, p. 194.
August 7
STG appointed members to the Technical Subcommittee and to the Technical
Assessment Panels for evaluation of industry proposals for the
development of the Apollo spacecraft.
Memoranda, Wesley L. Hjornevik for Walter C. Williams to Member,
Technical Subcommittee, "Instruction for Members of the Technical
Subcommittee for the Evaluation of Contractors' Proposals for Project
Apollo Spacecraft RFP-9-150," August 7, 1961; Hjornevik for
Williams to Member, Technical Assessment Panel, "Instruction for
Members of the Technical Assessment Panels for the Evaluation of
Contractors Proposals for Project Apollo Spacecraft RFP-9-150,"
August 7, 1961.
August 9
NASA selected the Instrumentation Laboratory of MIT to develop the
guidance and navigation system for the Apollo spacecraft. This first
major Apollo contract had a long lead-time, was basic to the overall
Apollo mission, and would be directed by STG.
Memorandum, William W. Petynia to Associate Director, STG, "Visit
to MIT Instrumentation laboratory on September 12-13, 1961, regarding
Apollo Navigation and Guidance Contract," September 21, 1961.
August 14
STG requested that a program be undertaken by the U.S. Navy Air Crew
Equipment Laboratory, Philadelphia, Penna., to validate the atmospheric
composition requirement for the Apollo spacecraft. On November 7, the
original experimental design was altered by the Manned Spacecraft Center
(MSC). The new objectives were:
- Establish the required preoxygenation time for a rapid decompression
(80 seconds) from sea level to 35,000 feet.
- Discover the time needed for equilibrium (partial denitrogenation)
at the proposed cabin atmosphere for protection in case of rapid
decompression to 35,000 feet.
- Investigate the potential hazard associated with an early mission
decompression - i.e., before the equilibrium time was reached, preceded
by the determined preoxygenation period.
- Conduct any additional tests suggested by the results of the
foregoing experiments.
Letter, Robert R. Gilruth, Director, MSC, to Director, Air Crew
Equipment Laboratory, November 7, 1961.
August 14-15
STG held a pre-proposal briefing at Langley Field, Va., to answer
bidders' questions pertaining to the Request for Proposal for the
development of the Apollo spacecraft.
"Apollo Spacecraft Chronology," p. 11.
August 16
STG appointed members to the Business Subcommittee and to the Business
Assessment Panels for evaluation of industry proposals for the
development of the Apollo spacecraft.
Memoranda, Walter C. Williams to Member, Business Subcommittee,
"Instructions for Members of the Business Subcommittee for
Evaluation of Proposals for Project Apollo Spacecraft, RFP No.
9-150," August 16, 1961; Williams to Member, Business Assessment
Panels, "Instructions for Members of the Business Assessment Panels
for Evaluation of Proposals for the Project Apollo Spacecraft, RFP No.
9-150," undated.
August 23
Ranger I, a test version of the spacecraft which would attempt an
unmanned crash landing on the moon, was launched from the Atlantic
Missile Range by an Atlas-Agena B booster. The 675-pound spacecraft did
not attain the scheduled extremely elongated orbit because of the
misfiring of the Agena B rocket. Although the spacecraft systems were
tested successfully, only part of the eight project experiments could be
carried out. Ranger I reentered on August 29 after 111 orbits.
New York Times, August 24, 1961; Aeronautical and
Astronautical Events of 1961, pp. 41, 42, 84.
August 23
The Large Launch Vehicle Planning Group (Golovin Committee) notified the
Marshal! Space Flight Center (MSFC), Langley Research Center, and the
Jet Propulsion Laboratory (JPL) that the Group was planning to undertake
a comparative evaluation of three types of rendezvous operations and
direct flight for manned lunar landing. Rendezvous methods were earth
orbit, lunar orbit, and lunar surface. MSFC was requested to study earth
orbit rendezvous, Langley to study lunar orbit rendezvous, and JPL to
study lunar surface rendezvous. The NASA Office of Launch Vehicle
Programs would provide similar information on direct ascent. Emphasis
was to be placed on developmental problems, exclusive of vehicle design
which would be handled separately.
In each case, environmental conditions peculiar to the particular mode
of rendezvous, and their effects on equipment design, were to be
considered so that the problems characteristic of the different
rendezvous modes could be separated and compared as quantitatively as
possible. Examples of problem areas were automatic versus manual
operation, mission profile, and lunar surface conditions. All rendezvous
modes would assume that the reentry capsule(s) should be capable of
supporting three men and weigh within the range specified by STG (about
8,500 pounds).
The preliminary results of the study were to be ready in 30 days.
TWX from Harvey Hall, NASA Coordinator, NASA-DOD Large Launch Vehicle
Planning Group, to MSFC, Langley Research Center, and JPL, August 23,
1961.
August 24
Expanded facilities in the Cape Canaveral area would be the site for the
launch of manned lunar flights and other missions requiring the use of
Saturn and Nova vehicles, NASA announced. The site of the new
facilities, north and west of the Air Force Missile Test Center, had
been chosen after months of NASA-DOD surveys of proposed launch areas.
Washington Post, August 25, 1961.
August 29
NASA announced that planned Ranger launchings would be increased from
five to nine. These additional spacecraft would be equipped with six
high-resolution television cameras. They would be programmed to begin
operating at about 800 miles above the lunar surface and continue until
moments before the spacecraft crash-landed. The final pictures would
record features no more than eight inches across. About 1,600
photographs were expected from each spacecraft, which would no longer
carry previously planned instrumented capsules. The objective of these
spacecraft now was to provide information on the lunar surface in
support of the manned lunar landing mission.
Sixth NASA Semiannual Report, p. 67.
August 31
C. Stark Draper, Director of the MIT Instrumentation Laboratory, at a
meeting with NASA Administrator James E. Webb, Deputy Administrator Hugh
L. Dryden, and Associate Administrator Robert C. Seamans, Jr., at NASA
Headquarters proposed that at least one of the Apollo astronauts should
be a scientifically trained individual since it would be easier to train
a scientist to perform a pilot's function than vice versa. (In a letter
to Seamans on November 7, Draper further proposed that he be that
individual.)
Ralph Ragan and David G. Hoag, personal notes of meeting, August 31,
1961 ; letter, Draper to Seamans, November 7, l961.
During the Month
The Ad Hoc Task Group for Study of Manned Lunar Landing by Rendezvous
Techniques, Donald H. Heaton, Chairman, reported its conclusions:
rendezvous offered the earliest possibility for a successful lunar
landing, the proposed Saturn C-4 configuration should offer a higher
probability of an earlier successful manned lunar landing than the C-3,
the rendezvous technique recommended involved rendezvous and docking in
earth orbit of a propulsion unit and a manned spacecraft, the cost of
the total program through first lunar landing by rendezvous was
significantly less than by direct ascent.
Summary report of Ad Hoc Task Group Study, "Earth Orbital
Rendezvous for an Early Manned Lunar Landing," Part I, August
1961.
During the Month
John C. Houbolt of Langley Research Center made a presentation to STG on
rendezvous and the lunar orbit rendezvous plan. At this time James A.
Chamberlin of STG requested copies of all of Houbolt's material because
of the pertinence of this work to the Mercury Mark II program and other
programs then under consideration.
Bird, "Short History of the Development of the Lunar Orbit Rendezvous
Plan at the Langley Research Center," p. 3.
During the Month
The deep-space tracking station at Hartebeesthoek, South Africa, was
completed. Dedication took place on September 8. NASA thus gained the
capacity for continuous line-of-sight communication with lunar and
interplanetary probes despite the earth's rotation. The other deep-space
tracking stations were at Goldstone, Calif., and Woomera, Australia.
Sixth NASA Semiannual Report, p. 76; Aeronautical and
Astronautical Events of 1961, p. 45.
During the Month
The Jet Propulsion Laboratory selected the Blaw Knox Company of
Pittsburgh, Penna., for second-phase feasibility and design studies of
an antenna in the 200-to 250-foot diameter class. The first of these
antennas, which were to be used in acquiring data from advanced lunar
and planetary exploration programs, would be operational at Goldstone,
Calif., by early 1965.
Sixth NASA Semiannual Report, p. 76.
NASA announced that the government-owned Michoud Ordnance Plant near New
Orleans, La., would be the site for fabrication and assembly of the
Saturn C-3 first stage as well as larger vehicles.
St. Louis Post-Dispatch, September 7, 1961.
September 11
NASA selected NAA to develop the second stage (S-II) for the advanced
Saturn launch vehicle. The cost, including development of at least ten
vehicles, would total about $140 million. The S-II configuration
provided for four J-2 liquid-oxygen - liquid-hydrogen engines, each
delivering 200,000 pounds of thrust.
Wall Street Journal, September 12, 1961.
September 12-13
Representatives of STG and NASA Headquarters visited the Instrumentation
Laboratory of MIT to discuss the contract awarded to the Laboratory on
August 9 and progress in the design and development of the Apollo
spacecraft navigation and guidance system. They mutually decided that a
draft of the final contract should be completed for review at
Instrumentation Laboratory by October 2 and the contract resolved by
October 9. Revisions were to be made in the Statement of Work to define
more clearly details of the contract. Milton B. Trageser of the
Laboratory, in the first month's technical progress report, gave a brief
description of the first approach to the navigation and guidance
equipment and the arrangement of the equipment within the spacecraft. He
also presented the phases of the lunar flight and the navigation and
guidance functions or tasks to be performed. Other matters discussed
were a space sextant and making visual observations of landmarks through
cloud cover.
Memorandum, William W. Petynia to Associate Director, STG, September 21,
1961.
September 13
Mercury-Atlas 4, carrying an astronaut simulator, was
launched from the Atlantic Missile Range in the first earth orbital test
of the Mercury spacecraft. After one orbit, the spacecraft reentered and
was recovered safely. With minor deviations, the flight was highly
successful.
Grimwood, Project Mercury: A Chronology, pp. 148-149.
September 14
In a memorandum to the Large Launch Vehicle Planning Group (LLVPG)
staff, Harvey Hall of NASA described the studies being done by the
Centers on rendezvous modes for accomplishing a manned lunar landing.
These studies had been requested from Langley Research Center, Marshall
Space Flight Center, and the Jet Propulsion Laboratory on August 23. STG
was preparing separate documentation on the lunar orbit rendezvous mode.
An LLVPG team to undertake a comparative evaluation of rendezvous and
direct ascent techniques had been set up. Members of the team included
Hall and Norman Rafel of NASA and H. Braham and L. M. Weeks of Aerospace
Corporation.
The evaluation would consider:
- Effect of total flight time on specifications and reliability of
equipment and on personnel.
- Effect of vehicle system reliability in each case, including the
number of engine starts and restarts.
- Dependence on data, data-rate, and distance from ground station for
control of assembly and refueling operations
- Launch and injection windows
- Effect of differences in the total weight propelled to earth escape
velocity
- Relative merits of lunar gravity and of a lunar base in general
versus an orbital station for rendezvous and assembly purposes.
Reliability estimates on vehicles would be based on LLVPG data;
estimates on equipment would rely on experience with similar types in
known applications.
Memorandum, Hall to Large Launch Vehicle Planning Group Staff,
"Comparison of Mission Alternatives (Rendezvous versus Direct
Flight)," September 14, 1961.
September 17
NASA invited 36 companies to bid on a contract to produce the first
stage of the advanced Saturn launch vehicle. Representatives of
interested companies would attend a pre-proposal conference in New
Orleans, La., on September 26. Bids were to be submitted by October 16
and NASA would then select the contractor, probably in November.
Wall Street Journal, September 18, 1961.
September 19
NASA announced that a site near Houston, Tex., had been selected for the
manned space flight research center which would design, develop,
evaluate, and test Apollo spacecraft in addition to training the
astronauts for lunar flights and other space missions. The laboratory
would be the command center for the manned lunar landing mission and
subsequent space flight missions. Selection had followed a nationwide
study by NASA of prospective sites.
Washington Post, September 20, 1961.
September 24
A major reorganization of NASA Headquarters was announced by
Administrator James E. Webb. Four new program offices were to be formed,
effective November 1: the Office of Advanced Research and Technology,
Ira H. Abbott, Director; the Office of Space Sciences, Homer E. Newell,
Director; the Office of Manned Space Flight, D. Brainerd Holmes,
Director; and the Office of Applications, directorship vacant. Holmes'
appointment had been announced on September 20. He had been General
Manager of the Major Defense Systems Division of the Radio Corporation
of America. The new Directors would report to Robert C. Seamans, Jr.,
NASA's Associate Administrator.
At the same time, Robert R. Gilruth was named Director of the Manned
Spacecraft Center to be located in Houston, Tex. The Directors of NASA's
nine field centers would, like the newly appointed program Directors,
report to Seamans.
Washington Post, September 24, 1961; Washington Daily
News, September 21, 1961.
During the Month
Richard H. Battin published MIT Instrumentation Laboratory Report R-341,
"A Statistical Optimizing Navigation Procedure for Space Flight,"
describing the concepts by which Apollo navigation equipment could make
accurate computations of position and velocity with an onboard computer
of reasonable size.
Battin, Astronautical Guidance (1964).