Part 3 (B)
Developing Software Ground Rules
July 1964 through September 1964
1964 July
1964 August
1964 September
July 1
ASPO spelled out operational procedures for the space suit emergency
oxygen supply (EOS) units. [The primary function of the EOS was as a
backup during extravehicular operations, if the portable life support
system failed or if suit leakage was excessive. EOS could also be used
to back up the spacecraft environmental control system during short-term
emergencies such as crew transfer.] The two units, stowed in the CM,
would be worn during crew transfer to the LEM, then stored there. After
landing on the moon, the crewmen would wear the EOS during the entire
lunar stay. Putting on or taking off the units unassisted would not be
required. North American and Grumman were directed to provide suitable
stowage areas ih each spacecraft.
TWX, C. L. Taylor, MSC, to NAA, Attn: E. E. Sack, July 1, 1964; TWX, W.
F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, July 14, 1964;
memorandum, William C. Kincaide, MSC, to Chief, Crew Systems Div.,
"Apollo Emergency Oxygen Supply Subsystem (EOSS)," July 24,
1964.
July 2-9
MSC's Operations Planning Division (OPD) examined a 14-day lunar survey
mission (a manned Apollo Lunar Orbiter-type of photographic mission).
OPD found that the 578-kilowatt-hour capability of the CSM's electrical
power system was adequate, provided there were no cryogenic tank
failures. If such failures occurred, the maximum mission duration would
be 11.8 days (four days in lunar orbit).
MSC, "ASPO Weekly Management Report, July 2-9, 1964;"
interview, telephone, Richard H. Kohrs, Houston, March 11, 1970.
July 8
Donald K. Slayton, MSC Assistant Director for Flight Crew Operations,
announced specific assignments for the astronauts. Alan B. Shepard, Jr.,
was named Chief of the Astronaut Office, Slayton's former job. This
office was now divided into three branches, Apollo, Gemini, and
Operations and Training: L. Gordon Cooper, Jr., was head of the Apollo
branch, with James A. McDivitt, Charles Conrad, Jr., Frank Borman, and
Edward H. White II assisting him; in the Gemini branch, headed by Virgil
I. Grissom, were Walter M. Schirra, Jr., John W. Young, and Thomas P.
Stafford; the Operations and Training branch was headed by Neil A.
Armstrong, assisted by Elliot M. See, Jr., and James A. Lovell, Jr. (M.
Scott Carpenter, currently on duty with the U.S. Navy's Project Sealab,
was not given a specific MSC assignment.)
The 14 newest astronauts were given individual assignments within the
Operations and Training branch: Edwin E. Aldrin, Jr., mission planning
(including trajectory analysis and flight plans); William A. Anders,
environmental control systems and radiation and thermal protection;
Charles A. Bassett II, training and simulators; Alan L. Bean, recovery
systems; Eugene A. Cernan, spacecraft propulsion and the Agena; Roger B.
Chaffee, communications and the Deep Space Network; Michael Collins,
pressure suits and extravehicular experiments; R. Walter Cunningham,
electrical and sequential systems and monitoring of unmanned flight
experiments in other programs which might relate to MSC programs; Donn
F. Eisele, attitude and translation control systems; Theodore C.
Freeman, boosters; Richard F. Gordon, Jr., cockpit integration; Russell
L. Schweickart, future manned programs and inflight experiments in
Gemini and Apollo; David R. Scott, guidance and navigation; and Clifton
C. Williams, Jr., range operations and crew safety.
MSC News Release 64-125, July 9, 1964; MSC, Space News
Roundup, July 8, 1964, pp. 1, 3.
July 8
Apollo Program Director Samuel C. Phillips called a meeting at NASA
Headquarters to discuss disposing of the S-IVB stage and its instrument
unit (IU) during lunar missions. Certain restrictions were considered:
- the S-IVB/IU must not hit the spacecraft after separation;
- it was preferable that the S-IVB/IU not impact either the earth or
the moon, but in seeking to prevent this no changes would be made to the
space vehicle that might result in weight, cost, or schedule penalties;
and
- no special provision would be made for tracking the S-IVB/IU after
separation from the spacecraft.
"Minutes of Meeting to Review Disposition of the S-IVB/IU and
Related Support Requirements During the Post Injection Phase of Lunar
Missions," July 15, 1964.
July 8-9
MSC representatives attended the second Block I CSM mockup review at
North American. (See April 28- 30.) Although the crew area was decidedly
improved, further changes in the suit umbilicals and the restraint
system - and significant ones - still were required.
MSC, "ASPO Weekly Management Report, July 9-16, 1964."
July 9
ASPO directed Grumman to delete 200 watts, currently appearing on the
LEM's power allotment charts, for lighting during television
transmission of lunar earthshine scenes. The LEM television camera,
which was furnished by the government, would be able to televise all
lunar scenes during sunshine or earthshine periods.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, July 9,
1964.
July 16
A NASA-North American Technical Management meeting set the CM control
weight (based on an assumed 41,000-kilogram [90,000-pound]-payload
capability of the Saturn V) at 5,000 kilograms (11,000 pounds). MSC then
asked and North American agreed to design, test, and qualify the open
ring-sail main parachutes for a CM weighing 5,200 kilograms (11,500
pounds).
"Minutes of NASA-NAA Technical Management Meeting, July 14,
1964"; MSC, "ASPO Weekly Management Report, July 30-August 6,
1964."
July 16
Once the decision was made to use Gemini space suits during Apollo
earth-orbital flights, NASA took the next step. The space agency gave to
the David Clark Company, manufacturer of the Gemini suit, a program for
modifying and testing that suit for use in the Apollo program, and
designated it the "Aponi" suit. Formal contract awards were
scheduled for late in the year.
Memorandum, H. F. Battaglia, MSC, to Chief, MSC Crew Systems Div.,
"Trip report for visit to David Clark Company, Worcester,
Massachusetts concerning Aponi Space Suit Program," July 16,
1964.
July 16-17
Representatives of North American, RCA, and MSC's Instrumentation and
Electronic Systems Division held a meeting on the status of the CSM
television subsystem. A design review covering all electrical,
mechanical, and optical aspects of the configuration established that
the design was complete, subject only to changes growing out of
development and qualification tests.
MSC, "ASPO Weekly Management Report, July 16-23, 1964."
July 19-25
North American completed a CM-active docking simulation at its Columbus,
Ohio, facility to study propellant consumption, engine duty cycles, and
stabilization and control system characteristics and performance.
Preliminary results showed that sighting aids mounted on the LEM were
needed for a satisfactory docking. Furthermore, during transposition
docking the S-IVB's roll rate must be no greater than 0.1 degree. North
American would prepare a full-scale, three-dimensional study to evaluate
differences in lighting and would design sighting aids (to be tested at
Langley Research Center).
MSC, "Weekly Activity Report for the Office of the Associate
Administrator, Manned Space Flight, July 19- 25, 1964," p. 4;
"Apollo Monthly Progress Report," SID 62-300-28,
July 20-21
At Grumman, representatives from MSC's Structures and Mechanics and
Systems Engineering Divisions reviewed the design criteria for the LEM's
landing gear. The group agreed to study landing stability in various
landing conditions. This investigation, and results of MSC Guidance and
Control Division's landing simulations, would permit a realistic
evaluation of the 406.4-centimeter (160-inch) cantilever gear. (See
October 2, 1963.)
MSC, "ASPO Weekly Management Report, July 23-30, 1964."
July 21
MSC approved a configuration that Hamilton Standard had recommended for
the power supply for the liquid-cooled portable life support system.
This configuration embodied an 11-cell secondary battery and separate
conversion devices for each electrical load. The total battery capacity
required was 108.8 watt-hours.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, July 21,
1964.
July 21
Grumman held a portable life support system (PLSS) accessibility test in
test mockup 1 for the MSC Crew Systems Division. Subjects were able to
put the PLSS on and take it off, unassisted, with the suits pressurized
and unpressurized.
MSC, "ASPO Weekly Management Report, July 23-30, 1964."
July 21
MSC approved Grumman's subcontract with Allison Division of General
Motors Corporation for the LEM descent engine tanks. The amount of the
cost-plus-incentive-fee contract was $5.48 million.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, July 19-August 22, 1964," p.
41.
July 21
NASA announced that its Office of Space Science and Applications was
inviting scientists to participate in a scientific experiment program
for manned and unmanned spacecraft. American and foreign scientists from
universities, industry, and government were being asked to submit
proposals. The earliest Apollo missions that could support this program
were anticipated to be the fourth and fifth flights. About 0.06 cubic
meter (two cubic feet) of space would be available for instruments and
equipment weighing not more than 36 kilograms (80 pounds), but it was
expected that additional space and weight would be available in the
S-IVB stage during early flights.
NASA News Release 64-177, "NASA Invites World Scientists to Propose
Space Experiments," July 21, 1964.
July 23-30
As currently conceived, the LEM's waste management system was designed
for direct transfer from the space suit assembly and immediate dumping.
If a storage system for the urine were not designed into the LEM, ASPO
reported, the spacecraft could be lightened by more than 23 kilograms
(50 pounds). MSC, "ASPO Weekly Management Report, July 23-30,
1964."
July 23-30
At its Reno, Nev., facility, Rocketdyne conducted the first checkout
firing (five seconds) of their LEM descent engine at a simulated
altitude of 39,600 meters (130,000 feet). A heavyweight, 20.3-millimeter
(0.8- inch) thick nozzle extension skirt was used. During the following
week, firings of the engine included one of 110 seconds.
MSC, "ASPO Weekly Management Report, July 23-30, 1964";
"ASPO Weekly Management Report, July 30-August 6, 1964."
July 23-30
Dalmo Victor Company was selected to supply the LEM S-band steerable
antenna system to RCA, subcontractor for the LEM communication system.
MSC, "ASPO Weekly Management Report, July 23-30, 1964."
July 24
After comparing capabilities of the space suit assembly with and without
the emergency oxygen supply (EOS), the MSC Apollo Portable Life Support
Systems Office recommended that the EOS system be retained for crew
safety considerations. (See July 1.)
Memorandum, William C. Kinkaide, MSC, to Crew Systems Division,
"Apollo Emergency Oxygen Supply Subsystem (EOSS)," July 24,
1964.
July 24
MSC authorized North American to provide a boost protective cover that
would completely enclose the conical portion of the CM during launch. As
an integral part of the launch escape system (LES), the cover would be
jettisoned after atmospheric exit or during an atmospheric abort. Also
the cover would satisfy the requirement for clean windows on the CM
after LES separation and would protect the CM's thermal coating and
docking mechanism from the launch environment. (See January 15-23 and
March 19-26.)
Letter, H. P. Yschek, MSC, to NAA, Space and Information Systems Div.,
"Contract Change Authorization No. 235," July 24, 1964.
July 27
ASPO notified Grumman that spacecraft attitude criteria had been changed
to relax thermal design requirements. The former constraints ("worst
case orientation") had imposed severe penalties on the design of
subsystems and components. The new criteria relieved thermal design
problems, but Grumman must ensure that these standards were compatible
with other constraints and that they provided adequate operational
flexibility.
Letter, W. F, Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Apollo spacecraft thermal design
mission," July 27, 1964.
July 28
MSC awarded a $335,791 contract to Lockheed-California Company for
transient heat transfer and thermodynamic analyses of the service
propulsion system (SPS). Phase I, an analytical study, and Phase II,
testing a one-third-scale model of the SPS, were scheduled for
completion in January and May. Tests would be run in the Hughes Aircraft
Company altitude chamber in a thermal vacuum and under simulated solar
radiation.
MSC, "ASPO Weekly Management Report, August 13-20, 1964."
July 28
Ranger VII was launched from Cape Kennedy. The
365.6-kilogram (806pound) spacecraft, carrying six television cameras to
take close-up pictures of the moon, was boosted into an earth-parking
orbit by an Atlas-Agena launch vehicle. The Agena engines then refired
to place the spacecraft on a translunar trajectory. On July 31,
Ranger VII crashlanded on the moon at 10.7 degrees S, 20.7
degrees W, in the Sea of Clouds. The spacecraft sent back 4,316
pictures, beginning at an altitude of about 800 kilometers (500 miles)
and ending at impact.
During the next several weeks, MSC's Space Environment Division, ASPO,
Grumman, and Bellcomm studied these photographs in great detail. On
October 30, ASPO Manager Joseph F. Shea informed Samuel C. Phillips,
Deputy Director of the OMSF Apollo Program, that the Ranger
VII data had eliminated most of the major uncertainties about the
lunar surface that could be resolved by photographic techniques.
The New York Times, July 29, 1964; memorandum, John M.
Eggleston, MSC, to Shea, "Preliminary analysis of Ranger 7
photographs," August 13, 1964; memorandum, Shea, to NASA
Headquarters, Attn: Phillips, "Apollo Mapping and Survey
System," October 30, 1964.
July 30
MSC awarded a cost-plus-fixed-fee contract estimated at $365,000 to the
Astronautics Division of LTV for Apollo space suit evaluation and
thermal development and qualification testing of Gemini space suits in
the company's space environment simulator.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, July 19-August 22, 1964," p.
64; memorandum, Robert E. Smylie, MSC, to Chief, Systems Test Branch,
"Technical Monitorship of the LTV Space Environment Simulator
Contract," August 26, 1964.
July 30
NASA approved Grumman's proposal to use the spacecraft's VHF radios as
an "intercom" between the docked LEM and the CM. Early
planning had involved the use of a hardline/umbilical arrangement.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, July 30,
1964.
July 30-August 6
Technicians in MSC's Operations Planning Division (OPD) studied oxygen
storage capacities in the two spacecraft to determine whether those
supplies exceeded by 50 percent the levels of consumption anticipated
during a normal mission (as required by OMSF specifications). On the
basis of current design consumption, they found that mission
requirements were exceeded by only 45 and 25 percent for the CSM and
LEM, respectively. OPD therefore recommended that OMSF's specifications
be revised, because oxygen for the fuel cells as well as for breathing
was contained in the same tanks. Rather than the 50 percent reserve, OPD
said, Headquarters should instead require the oxygen supplies in both
spacecraft to be the maximum amount that would be used for environmental
control and for generating power during a lunar mission. And, to allow
for safe aborts, some alternate or redundant oxygen storage would be
provided in each spacecraft.
MSC, "ASPO Weekly Management Report, July 30-August 6, 1964."
During the Month
Members of the National Academy of Sciences' Committee on Lunar
Exploration, meeting in Houston, expressed fear about contamination of
the lunar surface before Apollo astronauts could secure samples for
analysis. Contaminants might come, they noted, from at least two
possible sources:
- air released when the LEM was depressurized, and
- leakage from the space suits.
Elliott S. Harris, head of MSC's Microbiology, Biochemistry, and Hygiene
Section, who was present at the meeting, informed Crew Systems Division
of the scientists' concern and relayed their recommendations on ways of
preventing or controlling such contamination (such as bacteria filters).
Memorandum, Elliott S. Harris, MSC, to Chief, Crew Systems Division,
"Lunar contamination," July 31, 1964.
During the Month
At Hamilton Standard and at MSC, testing continued on early versions of
the Hamilton Standard liquid-cooled garment as well as an in-house model
developed by the Crew Systems Division. (See February 1 and May 8.)
While sweating was not yet completely eliminated, these tests
nonetheless confirmed the efficacy of using liquid- rather than
gas-cooled garments.
MSC, Space News Roundup, June 24, 1964, p. 7; MSC News Release 64-121,
July 8, 1964; MSC, "Consolidated Activity Report for the Office of
the Associate Administrator, Manned Space Flight, May 17- June 20,
1964," p. 53; memorandum, Gilbert M. Freedman and Francis J. DeVos,
MSC, to Apollo Portable Life Support Systems Office, "Trip
Report-Contract NAS 9-723," July 8, 1964; MSC, "ASPO Weekly-
Management Report, July 2-9, 1964"; "ASPO Weekly Management
Report, July 16-23, 1964."
At its new Magic Mountain, Calif., facility, the Marquardt Corporation
began development firings on the LEM reaction control system. By using
successively more advanced components, the testing program would
gradually build toward a complete prototype. Early in September, MSC's
Propulsion and Power Division (PPD) reported that Marquardt had
suspended testing temporarily because of problems with monitoring
equipment (which, the Division grumbled, could have been checked out
before the testing started). Two weeks later, PPD reported that
contamination of the thrust chamber had forced Marquardt to halt these
developmental firings again. Finally, by mid-October, problems with
manufacturing and acceptance checking of the thrust chambers at the
company's manufacturing plant portended a twenty-week slippage in
delivery of the chambers to the Magic Mountain site.
MSC, "ASPO Weekly Management Report, July 30-August 6, 1964";
"ASPO Weekly Management Report, August 27-September 3, 1964";
"ASPO Weekly Management Report, September 10-17, 1964";
"ASPO Weekly Management Report, October 8-15, 1964."
August 4
ASPO tentatively approved Grumman's recommendation to use
electroluminescent lighting for controls and display panels inside the
LEM's cabin (with backup floodlighting). "Definitive
acceptance," of course, was "dependent upon resolution of
actual production hardware capabilities." This action followed a
July 16 presentation of the electroluminescent concept by Grumman and a
review by MSC representatives (among whom were two astronauts, Richard
F. Gordon, Jr., and Charles Conrad, Jr.). [Electroluminescence involved
the use of a crystalline phosphor to give off light. Advantages of the
concept, which was wholly new to manned spacecraft, were that it used
less power and gave off less heat than conventional incandescent bulbs;
and, even more significant in the eyes of the astronauts, it was much
more even and had an "afterglow" of less than one second.]
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Lighting Mockup Review," with enclosure:
"Abstract of Proceedings, LEM Crew Integration Meeting, GAEC,
Bethpage, L. I., New York, Subject: LEM Interior Lighting Review,"
July 17, 1964.
August 4
At a meeting at MSC on July 23, MIT outlined aids and radar display
requirements, as well as landing site selection procedures, for lunar
landing. This included the recticular patterns on the LEM window that
designated where the vehicle was coming down and which enabled the pilot
to make touchdown corrections. There was a good deal of concern that, at
some time during the final letdown phase, dust might obscure the
astronauts' vision and make the radar data unreliable. To overcome this,
MSC ordered Grumman to use inertially derived data to monitor automatic
touchdown or as a basis for switching to manual control of the descent.
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S, Mullaney,
"Contract NAS 9-1100, NASA Coordination Meeting L8A, Implementation
of Decisions," August 4, 1964, with enclosure: "Minutes of
NASA Coordination Meeting L8A, July 23, 1964."
August 6
ASPO Deputy Manager Robert O. Piland issued a memorandum concerning the
Block II SM, as he put it, "to clear up any confusion which may
have existed" - and obviously there was some. (See April 16.) On
the basis of revised velocity budget requirements, and as a
weight-saving scheme, Piland said, the service propulsion tanks in the
Block II SM were being shortened. But he emphasized that the length of
the spacecraft per se "will not be reduced," and would
thus remain the same as the Block I vehicle.
Memorandum, Piland, MSC, to Addressees, "Block II Service Module
Length," August 6, 1964.
August 6-13
To investigate problems that might be encountered during the LEM's
"blast off"from the moon, Grumman conducted "fire in the
hole" tests using a 1/10th-scale model of the spacecraft. (See
February and March 11, 1963.) These tests showed that the initial shock
of the ascent engine's ignition could increase the pressure in the
engine nozzle by 2 newtons per square centimeter (3 psi), and that this
pressure could vary from one side of the nozzle to the other by as much
as 0.53 newtons per square centimeter (0.75 psi). This pressure
differential would change the thrust vector and cause an overturning
moment on the vehicle. Grumman planned additional testing before actual
full-scale firings began at WSMR.
MSC, "ASPO Weekly Management Report, August 6-13, 1964."
August 7
At North American, engineers from MSC's Crew Systems Division (CSD)
reviewed the revised CM couch restraint system. (See May.) CSD still
considered the restraint harness unacceptable for use with the
pressurized suit. Also the harness attachment gave inadequate restraint
when the couch angles were changed and would have to be relocated. North
American was asked to install a mirror in the CM to help the astronauts
in securing the restraint harness.
Ibid.
August 7
ASPO's LEM Project Office authorized Grumman to proceed with its
subcontractor effort for attitude indicators for the LEM. Until MSC
concluded defining the LEM's guidance equipment (anticipated early in
November), Grumman should pursue the analog concept (i.e., visual
display instruments). (MSC was in the midst of "tradeoff"
studies on digital versus analog indicators.) ASPO thus sought to ensure
that the manufacturer did not delay procurement of the devices.
Letter, W. F, Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, LEM Attitude Indicator and Gimbal Angle
Sequence Transformation Assembly (GASTA)," August 7, 1964.
August 7
At its Potrero, Calif., test facility, Lockheed Propulsion Company began
qualification testing on the pitch control motors for the launch escape
system. Early in September, when the program ended, about two dozen
motors had been successfully fired for full duration. Test and
reliability results showed that the motors met procurement
specifications and had an average specific impulse three percent higher
than required.
Lockheed Propulsion Company, "Qualification Test Report, Apollo
Pitch Control Motor," 588-M-50, December 8, 1964, pp. 1-2, 2-1,
2-2, 2-11.
August 9-15
The modified ring-sail parachutes for the CM's earth landing system
demonstrated their potential when Northrop Ventura conducted its first
clustered drop using that type of chute.
MSC, "Weekly Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 9-15, 1964," p. 2.
August 11
During late July and early August, MSC and its two spacecraft
contractors worked out the dimensions of sample containers and other
scientific equipment that would be stowed aboard the spacecraft during
lunar missions: 48 by 20 by 29 centimeters (19 by 8 by 11.5 inches). MSC
asked Grumman for cost and weight estimates for the containers.
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Results of Meeting on Scientific Equipment
Stowage Space," August 11, 1964, with enclosure: "Results of
Meeting on Scientific Equipment Stowage Space, July 23, 1964."
August 12
In designing batteries for the LEM electrical power system, ASPO ordered
Grumman to assume that, if a fuel cell failed, the mission would be
aborted.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, August 12,
1964.
August 13-20
The U. S. Navy's Air Crew Equipment Laboratory agreed to conduct a
series of tests on the water-cooled undergarment. Part I would determine
the garment's suitability for the postlanding phase of the mission; Part
II would investigate the CM range of temperature that could be tolerated
wearing the garment, with and without a space suit.
MSC, "ASPO Weekly Management Report, August 13-20, 1964."
August 13-20
To save money on the Hamilton Standard contract in Fiscal Year 1965,
MSC's Crew Systems Division (CSD) would take over preliminary
development of the meteoroid protective garment. Since there was still
too little knowledge about the need for meteoroid protection, CSD
believed that a concentrated contractor effort was
"unwarranted" at that time. (See November 17-December 21,
1963.)
Ibid.
August 13-September 3
MSC Crew Systems Division engineers evaluated the feasibility of
transferring water from the CM to the LEM in lunar orbit. They found
that hardware modifications would be needed - either lower water tank
pressures in the LEM during transfer or a pump added to the water
management system in the CM. Six weeks later, Grumman submitted a report
confirming that continuous use of CM water from transposition to
separation was more desirable than transferring water to the LEM.
MSC, "ASPO Weekly Management Report, August 13-20, 1964";
"ASPO Weekly Management Report, August 27-September 3, 1964";
"ASPO Weekly Management Report, October 1-8, 1964."
August 14
At Baylor University's College of Medicine, investigators presented some
results of a joint MSC-Baylor study of human tolerance to low frequency
noise (up to 12 cycles per second [cps]). [The study was undertaken
because, as launch vehicles for manned spacecraft become larger - i.e.,
Saturn V and Apollo - they produce higher noise levels, but lower noise
frequencies. The possibility of harmful effects upon the crew had to be
known.] Audiometry indicated some temporary physiological effect: after
three minutes of exposure at levels of about 140 decibels (dB), about
half of the twenty test subjects suffered some temporary impairment of
their hearing. No serious vestibular effects were encountered during
noise levels below 12 cps with a maximum of 144 db; heart and
respiration rates of the subjects indicated no severe stresses. Based
upon these findings, crew exposure to these noise levels (both -
frequency and intensity) was considered acceptable.
MSC, "ASPO Weekly Management Report, August 13-20, 1964;"
Burrell O. French et al., Effects of Low Frequency Pressure
Fluctuations on Human Subjects, NASA TN D-3323, March 1966, pp.
1-2, 7-9.
August 16-September 15
Studies at North American and at MSC disclosed that, during aborts above
9,100 meters (30,000 feet), simultaneous separation of the CM apex cover
and the launch escape system (with boost protective cover attached)
probably would damage the parachutes or escape hatch. One method of
eliminating this hazard was to jettison the apex cover 0.4 second after
ignition of the tower jettison motor and firing of the separation bolts.
Also being studied were means of sequencing the firing of the jettison
motor, the separation bolts, and the heatshield thrusters.
"Apollo Monthly Progress Report," SID 62-300-29, p. 3; MSC,
"Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19, 1964,"
p. 63.
August 16-September 15
North American recommended an uprighting system for the CM composed of
three 0.566-cubic-meter (20- cubic-foot) airbags and an inflation system
with an electric pump. Using the bags and flooding the aft compartment
would maintain a single-point flotation attitude for both Block I and
Block II CMs. MSC Structures and Mechanics Division tests of a 1/5-scale
model indicated that all three bags were needed to upright the CM. North
American contended that any two bags would usually be sufficient, with
the third bag providing a redundant capability. The contractor would
conduct further tests with inflatable bags (rather than the rigid foam
spheres used previously), while MSC would evaluate the use of an
extendable boom with two flotation bags.
"Apollo Monthly Progress Report," SID 62-300-29, p. 8; MSC,
"Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19, 1964,"
pp. 45-46.
August 18
From Wallops Island, Va., NASA launched another in its series of Scout
reentry tests to evaluate the thermal performance of various ablative
materials. The material (Avcoat 5026-39, which was being considered for
use in the CM's heatshield - see June 10, 1963) was fabricated and
bonded in much the same manner as on the actual heatshield. The multi-
staged rocket's trajectory propelled the payload into a reentry path
that simulated heating loads and shear forces of lunar returns. Though
not coming through completely unscathed, the material nonetheless
survived.
Data on heating, telemetered from the vehicle, established design limits
for the ablative material and, thus, were applied to the design of the
CM's thermal protection.
James L. Raper (ed.), Results of a Flight Test of the Apollo
Heat-Shield Material at 28,000 Feet Per Second, NASA TM X-1182,
February 1966, pp. 1, 5, 11-12, 23; MSC, "ASPO Weekly Management
Report, September 3-10, 1964"; NASA News Release 64-202,
"Re-entry Heating Experiment to be Flown by Scout," August 11,
1964.
August 18
Thiokol Chemical Corporation began qualification testing on the tower
jettison motor. The third motor to be fired in the series, on September
9, experienced a failure of the spot welding on the interstage
structure. The motor, now freed, broke apart in the test bay. Analysis
of the failure and repairs to the test stand followed, but Thiokol
reported that testing could not be resumed until about mid-November -
"at the earliest." This foreshadowed a probable delay of about
two months in the qualification program.
Thiokol Chemical Corporation, Elkton Div., "Apollo Tower Jettison
Program, Monthly Progress Report No. 26," A-226, October 14, 1964,
pp. ii, 2-12, 32-34; "Apollo Monthly Progress Report," SID
62-300-29, p. 16.
August 19
Homer E. Newell, head of NASA's Office of Space Science and
Applications, informed MSC Director Robert R. Gilruth that, as NASA had
requested (see April 16), the Space Science Board of the National
Academy of Sciences had defined the academic requirements for
scientist-astronauts for the Apollo program. These requirements demanded
graduate studies to the doctorate level, or equivalent.
Letter, Newell, NASA, to Gilruth, MSC, August 19, 1964.
August 20-27
MSC's Crew Systems Division (CSD) appraised crew tolerance to SM abort
accelerations for Block I spacecraft. Normal mission limits of + 0.5 g,
with total base durations of 50 seconds, were judged tolerable. Under
these conditions, CSD estimated that dizziness or visual disturbance
would occur in less than 10 percent of the cases. CSD set emergency
limits as + 18 g, with base durations not exceeding 40 seconds.
MSC, "ASPO Weekly Management Report, August 20-27, 1964."
August 21
ASPO gave Grumman formal approval to proceed with their concept of a
mission programmer for the LEM. The concept, which the contractor bad
presented in June, involved using the guidance computer as the main
sequencing element, with the tape reader as a backup sequencer.
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, LEM Mission Programmer," August 21,
1964; MSC, "ASPO Weekly Management Report, August 20-27,
1964."
August 23-29
A redesigned thrust chamber (called the "phase C") for the LEM
ascent engine was tested in the altitude chamber at Arnold Engineering
Development Center. [The "phase C" chamber differed from the
"phase B" in that a compression-molded ablative throat section
was used.] Firing runs of 60, 380, and five seconds produced only
negligible throat erosion. Preliminary data indicated a 2.0-second
specific impulse increase over the "phase B" chamber.
MSC, "Weekly Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-29, 1964."p. 3.
August 23-September 19
MSC proposed a device affixed to the interior of the spacecraft, called
a body-mounted attitude gyro (BMAG), as a backup to the inertial
platform in the CM. Should the platform fail during reentry, the pilot
could take control of the spacecraft and, using this secondary attitude
indicator, fly a safe trajectory. Analog computer analysis indicated the
BMAG's feasibility, provided the spacecraft did not maintain a constant
roll rate during reentry.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19, 1964,"
p. 49.
August 23-September 19
MSC-completed negotiations with General Electric Corporation (GE) Apollo
Support Department for 10 ground stations for spacecraft checkout. (See
March 25.) The figure finally agreed upon, $62,244,657 with a $4.1
million fee, was over $20 million less than GE's March quotation.
Ibid., p. 41.
August 23-September 19
MSC's Technical Services Division (TSD) built a prototype lightweight
Apollo couch and test fixture and delivered them to the Crew Systems
Division. TSD had designed this couch assembly, as a single unit, to
replace previously planned individual couches in the CM, which would
save 15.9 kilograms (35 pounds). During subsequent qualification
testing, however, the couch did not stand up structurally, and was
abandoned. But the concept itself was later useful to North American in
the design of their couch arrangement.
Ibid., p. 35; interview, telephone, Ralph Drexel, Houston,
March 12, 1970.
August 24-28
At North American, the service propulsion engine was gimbaled during hot
firing tests, the first time that the engine had been gimbaled under
these conditions. Gimbal operation was satisfactory.
MSC, "ASPO Weekly Management Report, September 3-10, 1964;"
"Apollo Monthly Progress Report," SID 62-300-29, pp. 14-15.
August 24-29
MSC's Crew Systems Division (CSD) conducted mobility tests on lunar-like
surfaces near Bend, Oreg. Three types of terrain were used: loose
basaltic rubble, low-density pumice with crusty surface and low bearing
load, and loose sand. Several CSD engineers and Astronaut Walter
Cunningham wore pressurized Apollo prototype space suits and simulated
portable life support systems. Climbing steep slopes covered by loose
material proved difficult unless aided by ropes. Not surprisingly, how
fast they could walk depended upon the terrain. Simple geophysical tasks
at the level of the astronaut's feet were easily accomplished, but those
requiring good visibility and dexterity were almost impossible and were
better accomplished at a working level of between one and four feet
above the ground. The only problems with the space suit were fogging of
the visor, inadequate ventilation, and stiffness in the hips and ankles
of the suits.
MSC, "ASPO Weekly Management Report, August 27-September 3,
1964"; "ASPO Weekly Management Report, September 3-10,
1964"; MSC, "Consolidated Activity Report for the Office of
the Associate Administrator, Manned Space Flight, August 23-September
19, 1964," p. 65; memorandum, Willis B. Foster, NASA, to Assoc.
Adm., Manned Space Flight, "Apollo Field Simulations,"
September 8, 1964; MSC, Space News Roundup, September 2,
1964, p. 1.
August 25
At a Contractor Coordination Meeting on June 9-10, the point had been
made that there existed a single- point failure that would preclude the
crew's safe return - a disabled crewman in the CM during LEM operations.
MSC demanded unequivocally that, even under these circumstances, the two
crewmen in the LEM must be able to complete the mission. Therefore, the
CSM must be designed for such a contingency; and to limit hardware
impact, this must be done by using onboard equipment as much as
possible.
Accordingly William F. Rector III, the LEM Project Officer in ASPO,
advised Grumman of two operational requirements:
- The radar transponder in the CSM must be turned on before the LEM's
ascent from the moon and must be pointed toward the LEM during ascent
and rendezvous.
- The CSM's attitude had to be stabilized during this phase of the
mission.
The two prime contractors, Rector said, should decide on some means of
controlling remotely the CSM's transponder and its stabilization and
control system. The contractors should, however, use the simplest and
most reliable arrangement. To initiate these two functions, the CSM
would receive commands from the ground. Finally, Rector informed Grumman
of a new ground rule on CSM communications: continuous communications,
both telemetry and voice, must be maintained whenever the spacecraft was
in view of the earth.
Letter, Rector, MSC, to GAEC, Attn: R. S. Mullaney, "Contract NAS
9-1100, Operations Groundrule for Disabled CSM Astronaut," August
25, 1964.
August 25
Apollo operational radiation protection was divided into two categories:
personal dosimeters (attached to the space suit) and a portable, hand-
held, radiation survey meter. Grumman was directed to provide a readily
accessible stowage location aboard the LEM for the meter, which would
weigh about 0.5 kilogram (one pound) and measure approximately 51 x 51 x
191 millimeters (2 x 2 x 7.5 inches).
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Space Allocation for LEM Radiation
Instrumentation," August 25, 1964.
August 25
MSC's Crew Systems Division (CSD) concluded that, in terms of weight and
complexity, the "buddy system" concept for supporting two
crewmen on a single portable life support system (see July 28-August 3,
1963) was undesirable. An additional emergency oxygen system seemed more
practical. The suit assembly already provided at least five minutes of
emergency life support; this extra system would afford another five, at
a cost of only 1.4 kilograms (three pounds). Consequently CSD redefined
the rescue requirement to mean simply "the capability for the
crewman remaining in the spacecraft to egress . . . and attend or
retrieve the crewman in distress."
Memorandum, Richard S. Johnston, MSC, to Asst. Chief, Systems
Engineering Div., "Portable Life Support System emergency
operation," August 26, 1964.
August 30
North American reported that qualification testing had been completed on
the launch escape motor. In all, 20 motors had been successfully static
fired. (See June 19.)
MSC, "Project Apollo Quarterly Status Report No. 9 for Period
Ending September 30, 1964," p. 17; MSC, "ASPO Weekly
Management Report, September 3-10, 1964."
August 30-September 5
MSC decided to use total mission elapsed time, instead of Greenwich mean
time, as the time reference for mission operations. (See February 27,
1963.) North American and Grumman were directed to provide a common
format for this display.
MSC, "Weekly Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 30-September 5, 1964,"
p. 3.
August 31
Robert E. Smylie, of MSC's Crew Systems Division (CSD), advised that, as
a consequence of MSC's canceling the requirement for inflight
maintenance, there were no longer any provisions for tools or for a tool
belt inside the spacecraft. Smylie reported that CSD was developing a
belt for carrying tools and small equipment needed on the lunar surface,
which would be stowed along with the scientific equipment in the LEM's
descent stage.
Memorandum, Smylie, MSC, to Systems Engineering Div., Attn: Lee N.
McMillion, "Extravehicular equipment belt," August 31, 1964.
August 31
Studies of future Gemini and Apollo missions showed that at least four
flight directors would be needed. MSC Director Robert R. Gilruth named
Christopher C. Kraft, Jr., John D. Hodge, Eugene F. Kranz, and Glynn S.
Lunney to these positions. The flight directors would manage all flight
operations from launch to recovery. Their responsibilities would include
making operational decisions on spacecraft performance, implementing
flight plans, and ensuring the safety of the astronauts.
MSC Announcement 64-120, "Designation of Flight Directors,"
August 31, 1964; MSC News Release 64-150, September 4, 1964.
During the Month
During zero g tests at Wright-Patterson Air Force Base, subjects wearing
pressurized Gemini space suits got into the Apollo crew couch and
attached the restraint harness. They entered through a Block II CM
tunnel 73.6 centimeters (29 inches) in diameter. One subject made the
transfer with a portable life support system (PLSS) strapped on his back
and another with the PLSS carried in his hands. One subject also went
through the tunnel with an 24.7-meter (81-foot) umbilical hose attached
to his suit. These tests demonstrated the feasibility of moving the
couch to the earth landing position without readjusting the restraint
harness; also they pointed up the need for improving the lap belt.
MSC, "ASPO Weekly Management Report, September 3-10, 1964."
MSC Crew Systems Division reported that the present water capacity of
the LEM (181 kilograms; 400 pounds) was sufficient for either a 35-hour
lunar stay with a nine-hour orbital contingency or for a 44-hour lunar
stay with no reserve. No excessive weight growths were needed to
accomplish this mission flexibility.
Memorandum, Richard S. Johnston, MSC, to Asst. Chief, Systems
Engineering Div., "LEM ECS Water Provisioning," September 1,
1964; MSC, "Consolidated Activity Report for the Office of the
Associate Administrator, Manned Space Flight, August 23-September 19,
1964," p. 19.
September 1
NASA and North American signed an amendment to the prime contractor's
Apollo contract, extending that agreement to February 15, 1966. The
amendment called for production of five additional CSM's (flight
articles), three more boilerplate spacecraft, another full-scale mockup,
and nine adapters which house the LEM. (See August 14, 1963.) The $496
million amendment increased the estimated value of North American's
contract (including cost and fee) to over $1.436 billion. Also, the
amendment forecast, beyond that February 1966 date, production of 20
more spacecraft.
Oakley, Historical Summary, S&ID Apollo Program, p. 25;
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19, 1964,"
p. 40; NASA Note to Editors, "Correction on Release No: 64-277
Friday, Sept. 4, 1964," September 11, 1964.
September 2-9
The alternate mode of escape tower jettison called for firing the launch
escape motors. Analyzing the structural integrity of a tower thus
jettisoned, MSC Structures and Mechanics Division calculated that it
would hold together for 3.5 seconds at least. By that time, it would be
610 meters (2,000 feet) away from the flight path of the spacecraft and
launch vehicle. This second method for shedding the tower would be
tested on the forthcoming AS-102 mission. (See September 18.)
MSC, "ASPO Weekly Management Report, September 3-10, 1964."
September 3
MSC awarded a $2,296,249 contract to Westinghouse Electric Corporation
for the LEM television camera. The first test model was scheduled for
delivery to Houston in March 1965.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19, 1964,"
pp. 42, 58.
September 3
MSC issued a definitive contract to Kollsman Instrument Corporation for
the LEM optical subsystem. A statement of work had gone into effect on
March 10 and had been implemented by technical directives from MIT to
Kollsman. The definitive contract covered work until December 31. After
that date, Kollsman would become a subcontractor to AC Spark Plug.
Ibid., p. 40; Kollsman Instrument Corporation, "LEM
[Optics] Program Quarterly Technical Progress Report No. 1,"
September 30, 1964, pp. Kv, K1-1, K2-1.
September 3
To evaluate lunar surface light, Astronauts Edwin E. Aldrin, Jr., Elliot
M. See, Jr., and David R. Scott (accompanied by engineer pilots) began
simulated landing approaches over lava flats in southern Idaho. They
wore dark glasses that had been modified to permit rapid change to
progressively darker (or lighter) filters. Diving in T-33 aircraft from
4,600 meters (15,000 feet), they leveled off at 900 meters (3,000 feet).
See, who had also participated in helicopter exercises earlier in
California, believed that the reflected earth-shine would be
insufficient to allow a LEM pilot to avoid deep surface cracks or large
boulders. He also thought that earthshine would limit the crew's
visibility to only a short distance. Aldrin, however, felt that this was
a pessimistic view. He suggested that the LEM might be equipped with
landing lights or flares.
The Houston Post, September 3, 1964; Jim Maloney, The
Houston Post, September 12, 1964; interview, telephone, Dean F.
Grimm, MSC, January 27, 1970.
September 3-10
Grumman and the Link Division signed a definitive
cost-plus-incentive-fee contract (valued at $7,083,022) for two LEM
simulators.
MSC, "ASPO Weekly Management Report, September 3-10, 1964;"
"ASPO Weekly Management Report, September 10-17, 1964."
September 3-10
North American gave Minneapolis-Honeywell an official go-ahead to begin
design work on the Block II CSM stabilization and control system.
MSC, "ASPO Weekly Management Report, September 3-10, 1964."
September 4
Representatives of Geonautics, Inc., reported on the status of their
study of selenodetic experiments for early lunar surface missions. (See
June 9.) Results to date indicated that lunar survey measurements could
rely heavily on photographic data acquired on the lunar surface.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19,
1964,"p. 65.
September 8-11
The resident Apollo office at Grumman reported that Pratt and Whitney
had achieved reliable 100-hour operation of the LEM fuel cell through
the use of new filling methods. This "apparently" had solved
the problem of potassium hydroxide deposits stopping up the cell, the
cause of early plugging failures (i.e., after only 10 hours of
operation). Some cells, in fact, had run between 200 and 400 hours
before failing, the office reported. On the other hand, carbonate
plugging was still a problem.
MSC, "ASPO Weekly Management Report, September 10-17, 1964."
September 9
Robert E. Smylie, of MSC's Crew Systems Division, asked the Crew
Performance Section of the Center's Space Medicine Branch to test the
capability of men in space suits to roll over in 1/6 g. In a previous
test, using a mockup portable life support system (PLSS), a subject
lying on his back had been unable to turn over. Two different PLSS
configurations and two kinds of thermal garments would be tested with
the Apollo suit. Also an emergency oxygen system mockup would be
attached to the helmet.
Memorandum, Smylie, MSC, to Chief, Space Medicine Branch, "Testing
of Apollo SSA roll-over capability in 1/6 g," September 9, 1964.
September 9
NASA directed North American to add the electronics equipment needed to
enable the crew to gimbal the service propulsion engine by using the
rotational hand controller.
Letter, H. P. Yschek, MSC, to NAA, Space and Information Systems Div.,
"Contract Change Authorization No. 250," September 9, 1964.
September 11
MSC issued a definitive contract to AC Spark Plug for LEM guidance and
navigation equipment. (See October 18, 1963, and June 12.) Estimated
cost and fee of the contract was $2.316 million.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, August 23-September 19, 1964,"
p. 40.
September 14
MSC issued three amendments (worth $6,134,113) to Grumman's LEM
contract. These amendments provided funds for data acquisition equipment
that MSC formerly was to have furnished; for static test stands at WSMR;
and for additional systems engineering studies by Grumman.
Ibid.
September 14
ASPO issued ground rules for Grumman and MIT to use when defining the
LEM guidance and control system. MSC's concerns related to provision for
lunar landing aborts and recognition of guidance and control equipment
failures. An example of rules during an abort stated that the system
should be able to provide information for the astronauts to fire the
engines and gain orbital flight on the first effort after initiating an
abort. If the first attempt failed, procedures had to specify how the
crew could use the system to achieve orbit and then rendezvous and dock
with the CM. The second matter concerned investigations to assure that
failures in the guidance and control system could be detected and to
define what responses the crew must make to those failures.
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Ground Rules for LEM Guidance and Navigation
Operation and Monitoring," September 14, 1964.
September 14
North American completed modifications to CM boilerplate (BP) 6, which
had been used in Apollo mission PA-1 (see November 7, 1963). The
spacecraft, now designated BP-6A, was then delivered to Northrop Ventura
for use as a parachute test vehicle.
"Apollo Monthly Progress Report," SID 62-300-29, p. 1.
September 14
The first attitude-controlled Little Joe II (see May 1963) was shipped
to WSMR. This vehicle would be used for Mission A-002, scheduled for
December 1964.
Little Joe II Test Launch Vehicle, NASA Project Apollo, Final
Report, p. 1-6,
September 15
William A. Lee of ASPO outlined minimum communications requirements for
"near-lunar" operations. Those of a general nature included
two-way voice communication between spacecraft and ground at any time
when a line-of-sight existed with the tracking network. Also there
should be provisions so that the crew could maneuver the spacecraft to
control antenna position when needing to acquire or reacquire the
communication link with the ground.
Requirements for specific phases of the mission - the trip from earth to
moon, lunar orbit, and the flight to earth - were also covered:
- Translunar: must be able to transmit, track, and receive telemetry
data, television, voice simultaneously at least 50 percent of the time
(half-hour on and half-hour off) and, on occasions, as much as two hours
at a time.
- Lunar Orbit:
- continuous voice except when behind the moon and out of sight
with the ground network;
- continuous voice between the LEM and the spacecraft at all times
when the LEM was flying - descending or ascending.
- Transearth: the same as translunar.
Memorandum, Lee, MSC, to Addressees, "CSM Lunar Mission
Communications Requirements," September 15, 1964.
September 16
The Air Force released Launch Complex 16 of its Eastern Test Range to
NASA for use as a service propulsion system test facility and static
firing stand.
"Apollo Quarterly Status Report No. 9," p. 47.
September 17
The first production CM environmental control system was installed in
boilerplate 14, and pressurization tests on the water-glycol system were
begun. Contamination checks, servicing, and checkout were completed near
the end of the month.
MSC, "ASPO Weekly Management Report, September 10-17, 1964";
"ASPO Weekly Management Report, September 24-October 1, 1964";
"Apollo Quarterly Status Report No. 9," p. 47.
September 17-24
MSC's Instrumentation and Electronic Systems Division (IESD) advised
ASPO that it would probably recommend a second steerable S-band high
gain antenna on the CSM. IESD based this assertion upon the operational
requirements for communications, the need for reliability, and
constraints imposed by the spacecraft's attitude. The division was
giving Lockheed Electronics Company the job of analyzing the problems of
acquisition and tracking with the high gain antennas on both spacecraft,
and thus made the dual-antenna concept for the CSM a part of that study.
Also included in Lockheed's study were: an RF (radio frequency) tracking
system, comparing it with the current infrared concept; and an inertial
reference system for acquisition.
MSC, "ASPO Weekly Management Report, September 17-24, 1964."
September 18
Apollo Mission A-102, the second flight of an Apollo spacecraft with a
Saturn I (SA-7) launch vehicle, was launched from Complex 37B of the
Eastern Test Range at 11:22:43 a.m., e.s.t. [The first such flight was
Mission A-101, with boilerplate (BP) 13, launched on May 28.] A-102 used
BP-15, essentially the same configuration as BP-13 except that one of
the SM's simulated reaction control system quadrant assemblies was
instrumented to measure launch temperatures and vibrations. The mission
was intended to demonstrate
- spacecraft launch vehicle compatibility,
- launch and exit parameters to verify design, and
- the alternate mode of escape-tower jettison (i.e., using the launch
escape and pitch control motors).
The launch azimuth was again 105 degrees. The S-1 stage shut down at
T+147.4 seconds, only 0.7 second later than planned. The S-1 and S-IV
stages separated at T+148.2 seconds, and the S-IV stage ignited 1.7
seconds after that. The launch escape tower was jettisoned at T+160.2
seconds. S-IV cutoff took place at T+621.1 seconds, burning l.3 seconds
longer than anticipated. The spacecraft and S-IV were inserted into
orbit at 631.1 seconds (2.0 seconds late), at a velocity of 7,810.05
meters (25,623.54 feet) per second. The spacecraft weight at insertion
was 7,815.9 kilograms (17,231 pounds). Orbital parameters were 212.66
and 226.50 kilometers (114.85 and 122.37 nautical miles), and the period
88.64 minutes.
All spacecraft test objectives were met. Satisfactory engineering data
verified the launch and exit design criteria. The launch escape and
pitch control motors moved the launch escape system safely out of the
path of the spacecraft. The Manned Space Flight Network obtained
telemetry data into the fifth orbit, at which time the transponders
stopped working, but several stations continued to track the vehicle
until it reentered over the Indian Ocean on its 59th journey around the
earth. As with BP-13, no recovery of the spacecraft was planned.
MSC,"Postlaunch Report for Apollo Mission A-102 (BP-15),"
MSC-R-A-64-3 (October 10, 1964), pp. 1-1, 2-1, 3-4, 3-5, 3-6, 5-1, 6-1,
7-15.
September 18
ASPO asked Grumman to investigate automatic switching mechanisms for LEM
VHF and S-band omnidirectional antennas. If such devices were used in
manned flights, the crew would need to pay only minimum attention to
antenna selection; on unmanned flights, it would improve communication
operations and range. TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S.
Mullaney, September 18, 1964.
September 20-26
"Fire-in-the-hole" tests of the LEM's ascent engine (see
February 1963) were completed at Arnold Engineering Development Center
after 18 successful runs. Visual inspection showed no damage to the
thrust chamber. Grumman confidently reported to MSC that these tests
indicated that "the ascent engine can handle the shock" of
ignition with its exhaust nozzle enclosed by the descent stage of the
vehicle.
MSC, "Weekly Activity Report for the Office of the Associate
Administrator, Manned Space Flight, September 20-26, 1964," p. 3;
MSC, "ASPO Weekly Management Report,
September 17-24, 1964;" GAEC, "Monthly Progress Report No.
20," LPR-10-36, October 10, 1964, p. 20.
September 20-30
Joseph F. Shea directed that the LEM's television camera built by
Westinghouse (see September 3) also be used in the Block II CM. (RCA was
the contractor for the Block I's camera.) Engineers from North American
and MSC met with Westinghouse representatives to work out the design
details (such as mounting, since Westinghouse's camera was larger - and
more versatile - than was RCA's).
"Apollo Quarterly Status Report No. 9," p. 2; MSC,
"Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, September 20-October 17, 1964,"
p.52; MSC, "ASPO Weekly Management Report, October 1-8, 1964";
interview, telephone, Milton G. Kingsley, Houston, March 13, 1970.
September 20-26
Rocketdyne conducted its first firing of the prototype LEM descent
engine using a new dome manifold injector, called the "Block
II" engine (in comparison to the previously tested circumferential
manifold type). Rocketdyne reported, in Grumman's words, "no
noticeable change in the combustion chamber pattern thrust chamber
erosion."
MSC, "Weekly Activity Report for the Office of the Associate
Administrator, Manned Space Flight, September 20-26, 1964,"p. 3;
"Monthly Progress Report No. 20," LPR-1036, p. 20; interview,
telephone, C. Harold Lambert, Jr., Houston, March 19, 1970.
September 21
NASA approved Grumman's subcontract with RCA for the LEM attitude and
translation control assembly. (See May 1.) The cost-plus-incentive-fee
subcontract was valued at $9,038,875.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, September 20-October 17, 1964,"
p. 39.
September 21-24
North American, MIT, and NASA jointly conducted a series of tests at
Wright-Patterson Air Force Base. The tests, in which four astronauts
participated, evaluated suit mobility, manipulation of controls, and
adjustment of couch and restraints.
NAA, "Apollo Monthly Progress Report," SID 62-300-30, November
1, 1964, pp. 7-8.
September 22
The first SM propulsion engine firing in the F-2 text fixture at WSMR
was unsuccessful. Although analysis was incomplete, improper functioning
of the engine's main propellant valve might have delayed full combustion
until eight seconds after fire signal. In a second test on October I,
the engine was fired for 10 seconds. The engine performed satisfactorily
this time, even though oxidizer inlet pressure was below normal.
MSC, "ASPO Weekly Management Report, September 17-24, 1964";
"Apollo Monthly Progress Report," SID 62-300-30, pp. 16,
32.
September 24-27
North American and MSC officials negotiated the specifications for the
overall Block I CSM system, including special needs for some spacecraft
to provide for specific mission objectives. The documents subsequently
were incorporated into the North American contract. (See Volume I, July
28 and November 7, 1962; April 28-30, 1964.)
"Apollo Monthly Progress Report," SID 62-300-30, p. 27.
September 25
NASA approved a $14,185,848 contract with North American for spare parts
(for Apollo spacecraft and ground support equipment) to expedite
repairing of the CSM at WSMR and Cape Kennedy. Spares would include
complete electronic packages, hydraulic and mechanical components,
reaction control engines, and equipment needed to service the
spacecraft.
MSC News Release 64-159, September 25, 1964.
September 25
MSC Director Robert R. Gilruth approved a Structures and Mechanics
Division proposal for three- dimensional dynamic testing of the Apollo
docking system in a thermal-vacuum environment. Tests were scheduled for
late 1965 in the Center's Space Environment Simulation Laboratory.
MSC, "ASPO Weekly Management Report, September 24-October 1,
1964"; "Apollo Quarterly Status Report No. 9," p. 8.
September 28
MSC's Crew Systems Division (CSD) advised against increasing the
capacity of the portable life support system. CSD contended that the
current design was capable of performing a variety of lunar missions (at
the maximum design metabolic load of 1,600 BTUs per hour) and that the
minimum 30 minutes of contingency time was sufficient.
Memorandum, Richard S. Johnston, MSC, to Systems Engineering Division,
"Contingent operation of the Portable Life Support System,"
September 28, 1964.
September 29
Richard S. Johnston, Chief of Crew Systems Division, provided Hamilton
Standard with some new guidelines and operating procedures formulated by
MSC concerning crew transfer from CM to LEM. One major item related to
suit umbilicals. A former requirement for end-to-end interchangeability
(called the "buddy system") was deleted (see September 19-25,
1963), as was the requirement for quick disconnects at the environmental
control system (ECS) outlet. Under MSC's new rules, the crew would
transfer with the two cabins unpressurized. Both CM and LEM umbilicals
had to be long enough to enable the astronauts to reach the LEM's ECS
controls.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, September 29,
1964; TWX, Richard S. Johnston, MSC, to Hamilton Standard, Attn: R.
Breeding, October 8, 1964.
September 30
NASA conducted a formal inspection and review of the Block II CSM
mockup. [The design resulted from a number of meetings earlier in the
year (see April 16 and June 11), a three-month program definition study,
and additional investigations requested by NASA.]
North American presented mockups of the CM interior, upper deck, lower
equipment bay, and the SM with two bays exposed. Actual hardware was
simulated. The couches from the Block I review in April were used, with
revised harnesses. The Block I inner and outer hatches were displayed,
while the CM exterior showed only changes from Block I.
North American explained that this mockup had been designed to depict
only volume, space allocations, and arrangements of the CSM. New systems
required for Block II were defined only as to maximum size. A detailed
mockup, showing actual hardware configuration, of the Block II CSM
interior and exterior would be available in February and April,
respectively.
Letter, H. P. Yschek, MSC, to NAA, Space and Information Systems Div.,
"Contract Change Authorization No. 254," October 1, 1964; MSC,
"Command and Service Modules: Project Apollo, Board Report for NASA
Inspection and Review of Block II Mockup, September 29-October 1,
1964," pp. 1-4.