Advanced Design, Fabrication, and Testing
October 1964
1964
October 1
Ceremonies in Washington marked the sixth anniversary of the National
Aeronautics and Space Administration (NASA). Administrator James E. Webb
reminded those present of NASA's unique contribution to America's
mission and destiny, then read a message from President Johnson:
"We must be first in space and in aeronautics," the President
said, "to maintain first place on earth. . . . Significant as our
success has been, it is but indicative of the far greater advances that
mankind can expect from our aeronautical and space efforts in the coming
years. We have reached a new threshold . . . which opens to us the
widest possibilities for the future." Two days later, in an address
in White Sulphur Springs, W. Va., Webb observed that "as the
national space program moves into its seventh year, the United States
has reached the half-way point in the broad-based accelerated program
for the present decade." America was halfway to the moon.
Astronautics and Aeronautics, 1964: Chronology on
Science, Technology, and Policy (NASA SP-4005, 1965), pp. 335,
338.
October 1-2
Representatives from Grumman Aircraft Engineering Corporation, North
American Aviation, Inc., and Massachusetts Institute of Technology's
(MIT) Instrumentation Laboratory, three of the Manned Spacecraft
Center's (MSC) principal contractors, met with radar and guidance and
navigation experts from Houston and Cape Kennedy. They formulated a
detailed plan for testing and checkout of the lunar excursion module
(LEM) rendezvous and landing radar systems both at the factory and at
the launch site.
MSC, "Minutes of Implementation Meeting #3, Apollo LEM G&D
Systems, September 29, 1965"; MSC, "ASPO Weekly Management
Report, October 1-8, 1964."
October 1-8
North American switched to a spring-activated pop-up antenna for the
command module (CM) high-frequency recovery radio.
"ASPO Weekly Management Report," October 1-8, 1964.
October 1-8
On the basis of new abort criteria (failure of one fuel cell), extended
operating periods, and additional data on fuel cell performance, Grumman
recommended a 20.4 kg (45-lb), 1,800 watt-hour auxiliary battery for the
LEM. MSC approved the recommendation and Grumman completed the redesign
of the electrical power distribution system and resizing of the battery
during late October and early November.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, September 20-October 17, 1964,"
p. 54; MSC, "ASPO Weekly Management Report, September 17-24,
1964"; "ASPO Weekly Management Report, September 24-October 1,
1964"; "ASPO Weekly Management Report, October 1-8,
1964"; "Monthly Progress Report No. 21," LPR-10-37, p.
26.
October 2
MSC submitted a Request for Proposals to General Electric Company (GE)
for two additional spacecraft acceptance checkout ground stations. Eight
million dollars was the estimated cost of the added equipment.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, September 20-October 17, 1964,"
p. 40.
October 2
MSC's Apollo Spacecraft Program Office (ASPO) approved a plan (put
forward by the MSC Advanced Spacecraft Technology Division to verify the
CM's radiation shielding. Checkout of the radiation instrumentation
would be made during manned earth orbital flights. The spacecraft would
then be subjected to a radiation environment during the first two
unmanned Saturn V flights. These missions, 501 and 502, with apogees of
about 18,520 km (10,000 nm), would verify the shielding. Gamma probe
verification, using spacecraft 008, would be performed in Houston during
1966. Only Block I CM's would be used in these ground and flight tests.
Radiation shielding would be unaffected by the change to Block II
status.
Memorandum, Joseph F. Shea, MSC, to Assistant Chief for Space
Environment, "Apollo Radiation Shielding Verification,"
October 5, 1964.
October 5-8
NASA conducted a formal review of the LEM mockup M-5 at the Grumman
factory. This inspection was intended to affirm that the M-5
configuration reflected all design requirements and to definitize the
LEM configuration. Members of the Mockup Review Board were Chairman Owen
E. Maynard, Chief, Systems Engineering Division, ASPO; R. W. Carbee, LEM
Subsystem Project Engineer, Grumman; Maxime A. Faget, Assistant Director
for Engineering and Development, MSC; Thomas J. Kelly, LEM Project
Engineer, Grumman; Christopher C. Kraft, Jr. (represented by Sigurd A.
Sjoberg), Assistant Director for Flight Operations, MSC; Owen G. Morris,
Chief, Reliability and Quality Assurance Division, ASPO; William F.
Rector III, LEM Project Officer, ASPO; and Donald K. Slayton, Assistant
Director for Flight Crew Operations, MSC.
The astronauts' review was held on October 5 and 6. It included
demonstrations of entering and getting out of the LEM, techniques for
climbing and descending the ladder, and crew mobility inside the
spacecraft. The general inspection was held on the 7th and the Review
Board met on the 8th. Those attending the review used request for change
(RFC) forms to propose spacecraft design alterations. Before submission
to the Board, these requests were discussed by contractor personnel and
NASA coordinators to assess their effect upon system design, interfaces,
weight, and reliability.
The inspection categories were crew provisions; controls, displays, and
lighting; the stabilization and control system and the guidance and
navigation radar; electrical power; propulsion (ascent, descent,
reaction control system, and pyrotechnics ; power generation cryogenic
storage and fuel cell assemblies ; environmental control; communications
and instrumentation; structures and landing gear; scientific equipment;
and reliability and quality' control. A total of 148 RFCs were
submitted. Most were aimed at enhancing the spacecraft's operational
capability; considerable attention also was given to quality and
reliability and to ground checkout of various systems. No major
redesigns of the configuration were suggested.
As a result of this review, the Board recommended that Grumman take
immediate action on those RFC's which it had approved. Further, the LEM
contractor and MSC should promptly investigate those items which the
Board had assigned for further study. On the basis of the revised M-5
configuration, Grumman could proceed with LEM development and
qualification. This updated mockup would be the basis for tooling and
fabrication of the initial hardware as well.
MSC, "Lunar Excursion Module, Project Apollo, Board Report for NASA
Inspection and Review of M-5 Mockup Lunar Excursion Module, October 5-8,
1964," pp. 1-7, 10-27.
October 8
Radio Corporation of America's (RCA) Aerospace Systems Division received
a 9 million contract from Grumman for the LEM attitude translation
control assembly (ATCA). The ATCA, a device to maintain the spacecraft's
attitude, would fire the reaction control system motors in response to
signals from the primary guidance system.
Space Business Daily, October 9, 1964, p. 210.
October 8-15
On the basis of reentry simulations, North American recommended several
CM instrument changes. An additional reaction control system display was
needed, the company reported. Further, the flight attitude and the
stabilization and control system indicators must be modified to warn of
a system failure before it became catastrophic. The entry monitor system
for Block I spacecraft would have to be replaced and the sample g-meter
was not wholly satisfactory.
MSC, "ASPO Weekly Management Report, October 8-15, 1964."
October 8-15
Analysis by MSC of the performance of the environmental control system
radiators for Block I CM's placed their heat rejection capability at
4,000 Btus per hr, far below the anticipated mission load of 7,220.
Water boiled at the rate of 1.46 kg (3.22 lbs) per hr would be needed to
supplement the radiators. This, in turn, would limit the mission to 45
hours duration, at which time all of the spacecraft's water supplies
(both that in the water tanks at launch and that collected as a
byproduct from the fuel cells) would be exhausted.
As MSC saw it, potential solutions were to redesign the radiators
themselves, to increase the size of the tanks to hold another 194 kg
(428 lbs) of water, or to reduce the operating power level.
Memorandum, Owen E. Maynard, MSC, to Chief, Operations Planning
Division, "Limited mission duration capability for Block I Command
and Service Modules," October 21, 1964.
October 8-15
MSC established the configuration of the reaction control system engines
for both the service module (SM) and the LEM, and informed North
American and Grumman accordingly. The Center also directed North
American to propose a design for an electric heater that would provide
thermal control in lunar orbit and during contingency operations. The
design would be evaluated for use in Block I spacecraft as well.
MSC, "Minutes, Apollo/E and D Technical Management Meeting No. 8,
10/5 and 10/12, 1964," pp. 4-5; letters, W. F. Rector III, MSC to
GAEC, Attn: R. S. Mullaney, "Contract NAS 9-1100, Temperature
control for the RCS engines in the Service Module and LEM," October
19, 1964.
October 8-15
RCA reduced the weight of the LEM rendezvous radar from 39.9 to 31.98 kg
(88 to 70.5 lbs).
Memorandum, Robert C. Duncan and Ralph S. Sawyer, MSC, to Manager, ASPO,
"Apollo Radar Systems Design Review," September 16, 1964, with
enclosure: "Apollo Radar Design Review," undated.
October 8-15
North American representatives visited the Grumman plant to discuss
design features and to inspect the electroluminescent lighting on the
LEM. North American intended to adopt this same feature on Block II
CMs.
"ASPO Weekly Management Report, October 8-15, 1964."
October 9
NASA and Grumman representatives discussed a weight reduction program
for the LEM. Changes approved at the M-5 mockup review portended an
increase in LEM separation weight of from 68 to 453 kg (150 to 1,000
lbs). Both parties agreed to evaluate the alternatives of either
resizing the spacecraft or finding ways to lighten it about nine
percent, thus keeping the improved LEM within the present control
weight.
GAEC, "Monthly Progress Report No. 21," LPR-10-37, November
10, 1964, p. 6.
October 9
NASA approved Grumman's selection of Airite to supply the LEM helium
tanks, and the two firms started negotiations.
Ibid., pp. 7, 16.
October 11-November 10
Grumman completed contract negotiations with Arma Division, American
Bosch Arma Corporation, for the LEM caution and warning electronics
assembly.
Ibid., p. 22.
October 11-November 10
Grumman lighting experts evaluated self-luminous materials produced by
the Minnesota Mining and Manufacturing Company and found them feasible
for use in docking lighting.
Ibid., p. 4.
October 12
The U.S.S.R. launched the world's first multi-manned spacecraft,
Voskhod I, the first to carry a scientist and a physician
into space. The crew were Col. Vladimir Komarov, pilot; Konstantin
Feoktistov, scientist; and Boris Yegorov, physician. According to Tass,
orbital parameters of the spacecraft were 409 by 177 km (254 by 110 mi)
with a 90.1 minute period and a 65 degree plane. Purposes of this
flight, according to the Russian source, were to prove the operational
compatibility of the spacecraft and crew and to conduct scientific and
medical investigations during actual space flight. The mission featured
television pictures of the crew from space. The trio landed after 16
orbits of the earth, 24 hours and 17 min after they had left it. The
flight had a significant worldwide impact. In the United States, the
"space race" was again running under the green flag. NASA
Administrator James E. Webb, commenting on the spectacular, called it a
"significant space accomplishment." It was, he said, "a
clear indication that the Russians are continuing a large space program
for the achievement of national power and prestige."
Astronautics and Aeronautics, 1964, pp. 348, 350.
October 12
At a North American-Grumman interface meeting on September 23-24, two
possible relative role alignments for CSM-active docking were agreed
upon. The major item blocking final selection was the effect of the SM's
reaction control system engines upon the LEM antennas. ASPO requested
Grumman to investigate the problem, to analyze the design penalties of
the two-attitude docking mode, and to report any other factors that
would influence the final attitude selection.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, October 12,
1964.
October 12
MSC notified Grumman of several additional LEM guidance and navigation
ground rules that were applicable to the coasting phase of the mission.
During this portion of the flight, the LEM abort guidance system must be
capable of giving attitude information and of measuring velocity
changes. Navigational data required to take the LEM out of the coasting
phase and to put it on an intercept course with the CSM would be
provided by the CSM's rendezvous radar and its guidance and navigation
system, and through the Manned Space Flight Network back on earth.
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Additional Ground Rules for LEM Guidance anti
Navigation Operation and Monitoring," October 12, 1964.
October 13
North American and MIT Instrumentation Laboratory representatives met in
Houston to discuss electrical power requirements for the guidance and
control systems in Block II CMs. They had determined the additional
electrical power needed for the guidance and control system 24 volts was
available,
Jerold P. Gilmore, MIT/IL, "MIT GN&C-Saturn Interfaces,"
prepared for Implementation Meeting #8, "Apollo CSM Block II
Guidance & Control Systems," October 13, 1964.
October 14
Eagle-Picher Company completed qualification testing on the
25-amperehour reentry batteries for the CM. Shortly thereafter,
Eagle-Picher received authorization from North American to proceed with
design and development of the larger 40-ampere-hour batteries needed for
the later Block I and all Block II spacecraft.
MSC, "ASPO Weekly Management Report, October 15-22, 1964";
North American Aviation, Inc. [hereafter cited as NAA], "Apollo
Monthly Progress Report," SID-62-300-31, December 1, 1964, pp.
15-16; MSC, "Project Apollo Quarterly Status Report No. 10 for
Period Ending December 31, 1964," p. 12.
October 14
In a letter to Apollo Program Director General Samuel C. Phillips, ASPO
Manager Joseph F. Shea pointed out that Bellcomm, under contract to
NASA, had a subcontract with Space Technology Laboratories (STL) and
that MSC had a contract with STL covering the same basic areas as the
Bellcomm-STL subcontract. Shea told Phillips that STL was not allowed to
use the information on the MSC contract which had been obtained on the
Bellcomm contract, and requested that STL be permitted to use the
information on the MSC contract.
Letter, from Manager, ASPO, to NASA Headquarters, Attn: General
Phillips, "Space Technology Laboratories Contract with Bellcomm
Corporation," October 14, 1964.
October 14
In a letter to NASA Administrator James E. Webb, AC Spark Plug reported
that the first Apollo guidance system completed acceptance testing and
was shipped at 11:30 p.m. and arrived at Downey, California, early the
following day. AC reported that in more than 2,000 hours of operation
they had found the system to be "remarkably reliable, accurate and
simple to operate."
Letter, to NASA Administrator Webb, from B. P. Blasingame, Manager,
Milwaukee Operations, October 19, 1964.
October 15
A number of outstanding points were resolved at a joint MSC-Grumman
meeting on LEM communications. Most significant, the VHF key mode was
deleted, and it was decided that, during rendezvous, voice links must
have priority over all other VHF transmissions. Further, the echo
feature of the current configuration (i.e., voice sent to the LEM by the
ground operational support system, then relayed back via the S-band
link) was undesirable.
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Minutes of Lunar Excursion Module
Communications Subsystem Review October 15 and 16, 1964," October
29, 1964, with enclosure: subject minutes, pp. 2-3.
October 15
MSC's Systems Engineering Division reported on the consequences of
eliminating the command and service module (CSM) rendezvous radar:
- Coasting period:
- During this phase of the mission, the rendezvous radar on the CSM
would be used to track the LEM and the rendezvous radar on the LEM would
be used to track the CSM. With the use of Mission Control through the
Manned Space Flight Network (MSFN), three sources of information could
be used as a vote for guidance system monitoring. Without the CSM
rendezvous radar, the monitoring task would become more difficult;
however, this was not to imply that it was impossible. The conclusion
was that CSM rendezvous radar was highly desirable, but not absolutely
necessary.
- Lunar descent and ascent:
- During powered flight, the CSM would be tracking the LEM. This was
desirable because if the LEM guidance computer (LGC) failed, it was very
doubtful that the astronauts could manually acquire radar lock-on with
the CSM. Also, if the LEM rendezvous radar failed, CSM lock-on would be
highly desirable. There were several alternative solutions to this
problem. First of all, Mission Control through the MSFN could relieve
the problem. If this did not satisfy all requirements, it was possible
for the LEM rendezvous radar to track the CSM during powered descent and
ascent. If the LGC then failed, the tracking acquisition would no longer
be a problem. In summary, there did appear to be other ways of
fulfilling the functions of the CSM rendezvous radar during the powered
phases.
- Lunar surface:
- While the LEM was on the lunar surface, it would be tracked with the
CSM rendezvous radar in order to update launch conditions. This could be
accomplished by the LEM tracking the CSM and the MSFN.
- Rendezvous:
- This was the most critical phase for the use of the rendezvous radar
on the CSM. If the LEM primary guidance system should fail (i.e., the
LGC, inertial measurement unit [IMU], and LEM rendezvous radar),
navigation information for long-range midcourse corrections would be
provided by the rendezvous radar on the CSM. The MSFN, however, could
supply this information. The terminal rendezvous maneuver would become a
problem if the LEM rendezvous radar failed and there was not a
rendezvous radar on the CSM. It had not been established that the MSFN
could supply the required terminal rendezvous information. If MSFN
could, a restricted mission profile would have to be employed. There
were other methods of supplying terminal rendezvous information such as
optical tracking. The scanning telescope or sextant on the CSM could be
used with the IMU and Apollo guidance computer on the CSM to derive
navigation information, meaning that the LEM would require flashing
lights. There was a delta-V penalty associated with using angle-only
information in place of range range rate and angle information, its
importance depending on the accuracy of the angle data and the
range/range rate data.
Memorandum, Aaron Cohen, MSC, to Chief, Operations Planning Div.,
"CSM Rendezvous Radar," October 15, 1964.
October 15
The Guidance and Control Implementation Sub-Panel of the MSC-MSFC Flight
Mechanics Panel defined the guidance and control interfaces for Block I
and II missions. In Block II missions the CSM's guidance system would
guide the three stages of the Saturn V vehicle; it would control the S-
IVB (third stage) and the CSM while in earth orbit; and it would perform
the injection into a lunar trajectory. In all of this, the CSM guidance
backed up the Saturn ST-124 platform. Actual sequencing was performed by
the Saturn V computer.
Memorandum, Aaron Cohen, MSC, to Chief, Flight Technology Branch,
"Flight Mechanics Panel's Activities," October 15, 1964.
October 15
Remote operation of the CSM's rendezvous radar transponder and its
stabilization and control system (SCS) was not necessary, ASPO told
North American. Should the CSM pilot be incapacitated, it was assumed
that he could perform several tasks before becoming totally disabled,
including turning on the transponder and the SCS. No maneuvers by the
CSM would be required during this period. However, the vehicle would
have to be stabilized during LEM ascent, rendezvous, and docking.
Letter, C. L. Taylor, MSC, to NAA, Attn: E. E. Sack, "Contract NAS
9-150, Operations Groundrule and Disabled CSM Astronaut," October
15, 1964.
October 15-22
The Air Force Eastern Test Command concurred in the elimination of
propellant dispersal systems for the SM and the LEM. Costs, schedules,
and spacecraft designs, NASA felt, would all benefit from this action.
ASPO thus notified the appropriate module contractors.
MSC, "ASPO Weekly Management Report, October 15-22, 1964."
October 15-22
Because they were unable to find a satisfactory means of plating the
magnesium castings for the CM data storage equipment (to fulfil the one
percent salt spray requirement), Collins Radio Company and the Leach
Corporation were forced to use aluminum as an alternative. This change
would increase the weight of the structure by about 2.3 kg (5 lbs) and,
perhaps even more significant, could produce flutter when the recorder
was subjected to vibration tests. These potential problems would be
pursued when a finished aluminum casting was available.
Ibid.
October 15-22
Grumman completed the fuel cell assembly thermal study and was preparing
a specific directive to Pratt and Whitney Aircraft Company which would
incorporate changes recommended by the study. These changes would
include the cooling of electrical components with hydrogen and the
shifting of other components (water shutoff valves, and oxygen purge
valve) so that they would operate at their higher design temperatures.
Ibid.
October 15-22
Representatives from the MSC Astronaut Office, and ASPO's Systems
Engineering, Crew Systems, and Mission Planning divisions made several
significant decisions on crew transfer and space suit procedures:
- Crew transfer, both pressurized and unpressurized, would be
accomplished using the environmental control system umbilicals. The CM
and LEM umbilicals would be designed accordingly. Crew Systems would
request the necessary engineering changes.
- The requirement for "quick-don" capability for the space
suit would be reevaluated by Systems Engineering people. If the
probability of a rapid decompression of the spacecraft during
"noncritical" mission phases was negligible,
"quick-don" capability might be eliminated. This would ease
several design constraints on the suit.
- The question of a crossover valve in the CM, for ventilation during
open-faceplate operation, was postponed pending the decompression study
and ventilation tests at Hamilton Standard.
Ibid.
October 16
In a letter on August 25, 1964, the LEM Project Office had requested
Grumman to define the means by which CSM stabilization and rendezvous
radar transponder operation could be provided remotely in the event the
CSM crewman was disabled.
In another letter on October 16, the Project Office notified Grumman
that no requirement existed for remote operation of either the
rendezvous radar transponder or the stabilization and control system.
The letter added, however, that the possibility of an incapacitated CSM
astronaut must be considered and that for design purposes Grumman should
assume that the astronaut would perform certain functions prior to
becoming completely disabled. These functions could include turning on
the transponder and the SCS. No CSM maneuvers would be required during
the period in which the CSM astronaut was disabled but the CSM must
remain stabilized during LEM ascent coast and rendezvous and docking
phases.
Letter, W. F. Rector III to GAEC, "Contract NAS 9-1100, Operations
Groundrule for Disabled CSM Astronaut," October 16, 1964.
October 16-November 15
Three Pratt and Whitney fuel cells were operated in a simulated space
vacuum at North American for 19, 20, and 21 hours. This was the first
time three cells were operated as an electrical power generating
subsystem.
"Apollo Monthly Progress Report," SID-62-300-31, p. 1.
October 16-November 15
North American and Honeywell reviewed the Block II CSM entry monitor
subsystem's compatibility with the stabilization and control system. The
proposed configuration, they found, combined maximum reliability with
minimum size and weight and would provide adequate mission
performance.
Ibid., p. 13.
October 17
MSC and International Business Machines Corporation (IBM) negotiated a
$1,500,000 fixed-price contract for the Apollo guidance and navigation
system backup computer.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, October 18-November 30, 1964,"
p. 39; MSC, "ASPO Weekly Management Report, October 15-22,
1964."
October 19
MSC ordered Grumman to halt work on the LEM test article (LTA) 10. The
LTA-10's descent stage would be replaced with one cannibalized from LEM
test mockup 5.
"Monthly Progress Report No. 21," LPR-10-37, pp. 12, 18.
October 19
On October 19, a supplemental agreement in the amount of $115,000,000
was issued to North American, bringing the total funded amount of the
CSM contract to $1,136,890,000.
MSC, "Consolidated Activity Report for the Office of the Associate
Administrator, Manned Space Flight, October 18-November 30, 1964,"
p. 39.
October 22
In response to inquiries from General Samuel C. Phillips, Apollo Program
Deputy Director, ASPO Manager Joseph F. Shea declared that, for Apollo,
no lunar mapping or survey capability was necessary. Shea reported that
the Ranger, Surveyor, and Lunar Orbiter programs should give ample
information about the moon's surface. For scientific purposes, he said,
a simpler photographic system could be included without requiring any
significant design changes in the spacecraft.
TWX, Shea, MSC, to NASA Headquarters, Attn: Phillips, October 22, 1964;
letter, J. A. Hornbeck, Bellcomm, to S. C. Phillips, NASA, November 5,
1964.
October 22-29
Heavy black deposits were discovered on the environmental control system
(ECS) cold plates when they were removed from boilerplate 14. Several
pinholes were found in the cold plate surfaces, and the aluminum lines
were severely pitted. This was, as ASPO admitted, a matter of
"extreme concern" to the ECS design people at North American,
because the equipment had been charged with coolant for only three
weeks. This evidence of excessive corrosion reemphasized the drawbacks
of using ethylene glycol as a coolant.
MSC, "ASPO Weekly Management Report, October 22-29, 1964."
October 2-29
ASPO notified Grumman and North American that it had canceled
requirements for Apollo part task trainers.
Ibid.
October 22-29
MSC's Crew Systems Division investigated environmental control system
(ECS) implications of using Gemini suits in Block I missions. The
results indicated that the ECS was capable of maintaining nominal cabin
temperature and carbon dioxide partial pressure levels; however, this
mode of operation always had an adverse effect on cabin dewpoint
temperature and water condensation rate.
Ibid.
October 23
ASPO deleted the requirement for LEM checkout during the translunar
phase of the mission. Thus the length of time that the CM must be
capable of maintaining pressure in the LEM (for normal leakage in the
docked configuration) was reduced from 10 hours to three.
Ibid.
October 23
Jet Propulsion Laboratory proposed a meeting on October 29 between
representatives of NASA Headquarters, Bellcomm, MSC, MIT, and JPL to
present the requirements and status of projects underway as they related
to the landing aid problem. The Surveyor Block II study effort was
concentrating on determining needs of obtaining data on the lunar
surface and environment for Apollo.
JPL proposed the following agenda items:
- LEM requirements and specifications on a Surveyor deployed
transponder.
- MSC planned active and passive landing aids study program.
- Landing aids capabilities under consideration by the Surveyor study:
- Active RE device.
- Passive RF device - corner reflector or other.
- Visual markers - visible during terminal phase and landing only;
visible during terminal phase and landing as well as from lunar orbit;
or visible during terminal phase and landing from lunar orbit as well as
photographically from the unmanned Lunar Orbiter.
- Landing aids lifetime and checkout problems.
- LEM-Surveyor mission interface problems.
MSC personnel would present a summary of results to date on the first
two items and JPL personnel would present similar results on items three
and four.
TWX from JPL to NASA Hq., MSC, Bellcomm, Inc., and MIT,
"Surveyor Employed Landing Aids for Apollo," signed Lou
Divone, October 23, 1964.
October 26
The trajectory summary of the Design Reference Mission (DRM) prepared by
the Apollo Mission Planning Task Force was sent to Grumman by the LEM
Project Office with a note that the operational sequence-of-events would
be forwarded in November.
It was acknowledged that a single mission could not serve to
"completely define all the spacecraft functional requirements"
but "such a mission has considerable value as a standard for
various purposes on the Apollo Program."
Specifically, the DRM would be used for weight reporting, electrical
power reporting, reliability modeling, engineering simulation, crew task
analyses, mission-related Interface Control Documents, and trade-off
studies.
Letter, MSC, W. F. Rector III, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Transmittal of the Apollo Lunar Landing
Design Reference Mission Trajectory," October 26, 1964.
October 27
ASPO requested Grumman to list all single-point failures that would
cause loss of the crew during a lunar orbit rendezvous mission. Grumman
was to consider only the equipment that it was responsible for.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, October 27,
1964.
October 27
NASA announced the appointment of Major General Samuel C. Phillips as
Director of the Apollo Program. Phillips thus assumed part of the duties
of George E. Mueller, Associate Administrator of Manned Space Flight,
who had been serving as Apollo Director as well. Phillips had been
Deputy Director since January 15.
NASA News Release 64-267, "General Phillips Appointed Director of
Apollo Program," October 27, 1964.
October 27
MSC ordered North American to halt procurement of a CM simulator.
Instead, the company was to begin a simulator program using the two
existing evaluator-type CMs in conjunction with the digital-analog
computer facility. These evaluators would be used to verify the guidance
and navigation and stabilization and control system software, and to
analyze crew tasks and failure effects.
Letter, H. P. Yschek, MSC, to NAA, Space and Information Systems Div.,
"Contract Change Authorization No. 263," October 27, 1964.
October 27
Because of the redesign of the portable life support system that would
be required, MSC directed Grumman and North American to drop the
"buddy system" concept for the spacecraft environmental
control system (ECS) umbilicals. The two LEM crewmen would transfer from
the CM while attached to that module's umbilicals. Hookup with the LEM
umbilicals, and ventilation from the LEM ECS, would be achieved before
disconnecting the first set of lifelines. MSC requested North American
to cooperate with Grumman and Hamilton Standard on the design of the
fetal end of the umbilicals. Also, the two spacecraft contractors were
directed jointly to determine umbilical lengths and LEM ECS control
locations required for such transfer.
TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, October 27,
1964; TWX, C. L. Taylor, MSC, to NAA, Attn: E. E. Sack, October 27,
1964; TWX, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney, October
29, 1964; MSC, "ASPO Weekly Management Report, October 29-November
5, 1964."
October 28
Testing of the first flight-weight 15-cell stack of the LEM fuel cell
assembly began. Although the voltage was three percent below design, the
unit had a 980-watt capability. Earlier, the unit completed 150 hours of
operation, and single cell life had reached 662 hours.
MSC, "ASPO Weekly Management Report, October 29-November 5,
1964."
October 28
ASPO's Operations Planning Division defined the current Apollo mission
programming as envisioned by MSC. The overall Apollo flight program was
described in terms of its major phases: Little Joe II flights (unmanned
Little Joe II development and launch escape vehicle development); Saturn
IB flights (unmanned Saturn IB and Block I CSM development, Block I CSM
earth orbital operations, unmanned LEM development, and manned Block II
CSM/LEM earth orbital operations); and Saturn V flights (unmanned Saturn
V and Block II CSM development, manned Block II CSM/LEM earth orbital
operations, and manned lunar missions).
Memorandum, William A. Lee, MSC, to Distr., "Apollo Spacecraft
Flight Development Mission Program," October 28, 1964.
October 28
At Langley Research Center, representatives from Langley, MSC, Ames
Research Center, Avco Corporation, and North American met to discuss
their independent conclusions of the data gathered from the Scout test
of the Apollo heatshield material and to determine whether a second test
was advisable. Langley's report revealed that: the heatshield materials
performed as predicted within the flight condition appropriate to
Apollo; the excessive recession rates occurred during flight conditions
which were more severe than those considered for the design of the
heatshield or expected during Apollo reentries.
Each group represented had a different interpretation of the reasons for
the excessively high surface recession. The conclusion was that a second
flight of the heatshield materials on the Scout would not particularly
improve the understanding of the material's performance because of the
limited variation in reentry trajectory and flight conditions obtainable
with the Scout vehicle.
Memorandum, Owen E. Maynard, MSC, to Mgr., ASPO, "Significance of
Langley Working Paper on Scout Test of Apollo Heat Shield
Material," December 11, 1964.
October 29
North American conferred with representatives from Shell Chemical
Company, Narmco, Epoxylite, and Ablestick on the problems of bonding the
secondary structure to the CM. They agreed on improved methods of curing
and clamping to strengthen the bond and prevent peeling.
MSC, "ASPO Weekly Management Report, October 29-November 5,
1964"; "ASPO Weekly Management Report, November 5-12,
1964."
October 29-November 5
North American conducted the first operational deployment of the launch
escape system canards. No problems were encountered with the wiring or
the mechanism. Two more operational tests remained to complete the
minimum airworthiness test program, a constraint on boilerplate 23.
MSC, "ASPO Weekly Management Report, October 29-November 5,
1964."
October 29-November 5
After studying the merits of three flush-mounted versus two scimitar VHF
antennas for the Block II CSM, the MSC Instrumentation and Electronics
Systems Division recommended the flush-mounted type.
Ibid.
October 29-November 5
MSC directed North American to halt development of a portable light
assembly for the CM. It was not required, the Center said, because the
spaceship's primary lighting system included extendable floodlights.
Small lights on the fingertips of the space suit and a flashlight in the
survival kit were also available if needed.
Ibid.
October 29-November 5
The MSC Meteoroid Technology Branch inspected a hard shell meteoroid
garment built by the Center's Crew Systems Division. It was only a crude
prototype, yet it in no way hampered mobility of the pressurized suit.
The Meteoroid Technology people were satisfied that, should a hard
garment be necessary for protection of the Apollo extravehicular
mobility unit, this concept was adequate. The garment might present
stowage problems, however, and investigations were underway to determine
the minimum area in the LEM that would be required.
Ibid.
October 29-November 5
An MSC Crew Systems Division (CSD) medical representative attended a
meeting on U.S. Atomic Energy Commission (AEC) participation in those
NASA Office of Manned Space Flight (OMSF) and MSC radiobiology pro grams
aimed at delineating the effects of high doses of whole-body radiation
on man. The meeting was attended by NASA's Dr. W. R. Lovelace, Director,
Office of Space Medicine; Dr. Dunham, Medical Director of the AEC; Dr.
Grahn, head of the Argonne National Laboratory, Biology Division; Dr.
Gould Andrews, Chief, Oak Ridge Institute for Nuclear Studies, Medicine
Division; and OMSF and NASA Office of Advanced Research and Technology.
CSD requested that the AEC whole-body radiation analysis be extended to
include all future cases throughout the country and that the low dose
rates being planned for a number of clinical conditions particularly be
included. The ultimate objective was a computer, for MSC use, which
would accept sequential radiation flux and type information and predict
the occurrence of subsequent acute or chronic radiation illness or
death. The program was agreed by everyone to be highly desirable. Dr.
Dunham said that the AEC would not undertake it unless he had reasonable
assurance of long-term support from NASA. A letter giving such assurance
was being prepared for Dr. George E. Mueller's signature.
Ibid.
October 29-November 5
MSC conducted a week-long salt spray test on the CM television camera's
magnesium housing. This was necessitated by similar tests on the Leach
data storage structure, which had disclosed the inadequacy of that
equipment's nickel plating. The television camera, with its protective
coating (AMS 2478, Dow 17 treatment), withstood the ordeal quite well.
MSC therefore decided that the magnesium housing was acceptable.
Ibid.; "ASPO Weekly Management Report, November 5-12,
1964."
October 29-November 5
Grumman reported to MSC the results of development tests on the welding
of the LEM cabin's thin-gauge aluminum alloy. The stress and corrosion
resistance of the metal, Grumman found, was not lessened by environments
of pure oxygen, varying temperatures, and high humidity.
MSC, "ASPO Weekly Management Report, October 29-November 5,
1964."
October 30
North American conducted the first drop test of boilerplate 28 at
Downey, Calif. The test simulated the worst conditions that were
anticipated in a three-parachute descent and water landing. The second
drop, it was expected, would likewise simulate a landing on two
parachutes. In the week preceding the drop, the MSC Structures and
Mechanics Division had sounded a note of caution. The aft heatshield,
they said, "might not respond to the impact loading as static
loading." In this event, they predicted, pressures imposed on the
heatshield would "greatly exceed" design allowables.
The drop appeared normal, but the spacecraft sank less than four minutes
after hitting the water. Inspection of the vehicle immediately afterward
disclosed that the heatshield had broken open on impact and that the
welds of the stainless-steel honeycomb core had failed. The cabin
interior also sustained considerable damage, especially the aft bulkhead
and the cabin floor, which were forced upward and struck the crew couch.
Three instrumented manikins were seated in the crew positions. The two
outboard "crewmen" sustained 25 g's each at impact. The dummy
in the second couch, however, suffered stresses of 50 g's, a condition
that might euphemistically be called "unacceptable." MSC and
North American personnel were investigating further.
MSC, "ASPO Weekly Management Report, October 22-29, 1964";
"ASPO Weekly Management Report, October 29-November 5, 1964";
"ASPO Weekly Management Report, November 5-12, 1964";
"Apollo Monthly Progress Report," SID-62-300-31, pp. 3-4.
October 31
Astronaut Theodore C. Freeman died in an aircraft accident at Ellington
Air Force Base, near Houston. Freeman, an Air Force captain and a member
of NASA's third group of spacemen, was preparing to land his T-38
training jet when it struck a goose and lost power. He ejected from his
aircraft, but did not have sufficient altitude for his parachute to
open. Freeman thus became the first American astronaut to lose his life
in the quest for the moon.
Astronautics and Aeronautics, 1964, pp. 370, 388; The
Houston Chronicle, November 1, 1964; The Houston
Post, November 17, 1964.
During the Quarter
MSC spelled out additional details of the LEM environmental control
system (ECS) umbilical arrangements. The hoses were to be permanently
bonded to the ECS; a crossover valve, to permit flow reversal, was
mandatory; and a bypass relief would be added, if necessary, to prevent
fan surge. Grumman was to coordinate with North American to ensure that
all umbilicals were long enough for crew transfer and to determine the
optimum location for the spacecraft's ECS switches.
MSC, "ASPO Weekly Management Report, October 29-November 5,
1964"; memorandum, Robert E. Smylie, MSC, to Chief, Program Control
Div., "Apollo Spacecraft Program Quarterly Status Report No.
10," January 19, 1965, with enclosures; memorandum, W. F. Rector
III, MSC, to Contracting Officer, LEM, "Contract NAS 9-1100, LEM
Environmental Control System (ECS), Suit Supply Connector and Flow
Control," November 3, 1964.