Advanced Design, Fabrication, and Testing
May 1965
1965
May 1
North American and NASA officials conducted an engineering inspection on
boilerplate 23A at White Sands Missile Range, New Mexico. The board
approved four requests on minor structural changes; a fifth request,
involving tolerances on the boost protective cover, was slated for
further study.
Memorandum, Joe W. Dodson, MSC, to Distr., "Results of DEI on
BP-23A," May 4, 1965, with enclosures.
May 3
Systems Engineering Division did not concur in use of the chamber
technician's suit by test subjects in AFRM 008 tests. AFRM 008
represented the only integrated spacecraft test under a simulated
thermal- vacuum environment and was therefore considered a significant
step in man-rating the overall system. For that reason use of the flight
configuration Block I suit was a firm requirement for the AFRM 008
tests.
The same rationale would be applicable to the LEM and Block II vehicle
chamber tests. Only flight configured spacecraft hardware and
extravehicular mobility unit garments would be used by test subjects.
Memorandum, Owen E. Maynard, MSC, to Chief, Crew Systems Division,
"Utilization of a Flight Configured Block I Space Suit with AFRM
008," sgd. Robert W. Williams, May 3, 1965.
May 3
R. Wayne Young was appointed Chief of the LEM Contract Engineering
Branch, ASPO, to perform the functions of Project Officer for the LEM,
effective May 3. At the same time M. E. Dell was appointed Chief of the
G&N/ACE Contract Engineering Branch, ASPO, and would be responsible
for all functions of Project Officer for the guidance and navigation,
automatic checkout equipment-spacecraft, and Little Joe II systems for
the Apollo spacecraft, and for technical management of the General
Electric Support Contract.
Memorandum, J. Thomas Markley, MSC, to Distr., "Assignment of
Chief, LEM Contract Engineering Branch and Chief, G&N/ACE Contract
Engineering Branch, Apollo Spacecraft Program Office," May 4,
1965.
May 4
Technical personnel at MSC became concerned over an RCS oxidizer tank
failure that occurred in February 1965, during propellant exposure and
creep tests. The failure had previously been explained as stress
corrosion caused from a fingerprint on the tank shell before heat treat.
NASA requested that the test be repeated under tighter controlled
procedures.
TWX, C. L. Taylor, MSC, to NAA, Space and Information Division, Attn:
J. C. Cozad, May 4, 1965.
May 4
A Panel Review Board (PRB) meeting was held at Office of Manned Space
Flight (OMSF) in Washington and the MSC and MSFC Chairmen of the Flight
Mechanics Panel attended.
Prior to the formal meeting, discussions with T. Thompson and B. Kaskey
revealed that Bellcomm had recommended to Apollo Program Director Samuel
C. Phillips that the contingency mission for AS 204 be an unmanned
orbital flight and that no unmanned contingency mission be planned for
205. The reason for an unmanned contingency for 204 was to give MSFC an
additional opportunity to obtain orbital data from the S-IVB stage.
PRB was informed that lack of specific requirements concerning
contingency mission capability was hampering Flight Mechanics Panel in
completion of interface control documents and associated mission
development. Contingency capability was classified into two types: (1)
contingency capability to provide for failures during the flight
program or schedule adjustments of the hardware; and (2) in-flight
contingencies due to malfunction of the launch vehicle.
Memorandum, C. H. Perrine, MSC, to Chief, Systems Engineering Division,
"Trip Report on Panel Review Board Meeting at OMSF, May 4,
1965," May 7, 1965.
May 4
NASA Associate Administrator for Manned Space Flight George E. Mueller
concurred with a plan of MSC Director Robert R. Gilruth to implement a
three-station developmental Solar Particle Alert Network. Mueller said
he understood that Gilruth would "review the necessity for the
Guaymas station, and that you will examine having all data reduction
related to this network carried out under contract," and adding
that he felt the program would be enhanced if arrangement could be made
to involve one or more academic institutions in the analysis of
data.
Letter, Mueller to Gilruth, "Solar Particle Alert Network,"
May 4, 1965.
May 4
A preliminary flight readiness review was held in Houston on
boilerplate (BP) 22. Several participants voiced serious doubts about
the structural integrity of the boost protective cover, because of its
sizable cutouts (required for pressure measurements and its poor fit.
Structures and Mechanics Division representatives argued that the
article not be modified, however. They stressed that BP-23's cover,
which also fit poorly, endured greater dynamic pressures than were
anticipated for BP-22. Final inspection of the cover would be made at
WSMR. (See May 19, 1965.)
"ASPO Weekly Management Report, May 6-13, 1965."
May 4
Although North American was including real-time digital command
equipment in Block II CSMs (as NASA had directed), the firm recommended
that such equipment not be placed on Block I vehicles. North American
based their contention on two factors:
- the anticipated cost and schedule impacts; and
- command capability was not essential during earth orbital flights.
Letter, E. E. Sack, NAA, to NASA MSC, Attn: J. B. Alldredge,
"Contract NAS 9-150, Contract Change Proposal SID-150-370,
Revision 1, Preliminary; Real Time Radio Command Requirements on Block
I and Block II CSM's," May 4, 1965, with enclosure.
May 4
MSC directed North American to provide spacecraft 012, 014, 017, and
020 with a system to monitor combustion instability in the service
propulsion engine. (On April 8, officials of ASPO, Propulsion and Power
Division, and the Flight Operations Directorate had agreed on the
desirability of such a system.) Should vibrations become excessive, the
device would automatically shut down the engine. Manual controls would
enable the astronauts to lock out the automatic system and to restart
the engine.
Letter, J. B. Alldredge, MSC, to NAA, Space and Information Systems
Division, "Contract Change Authorization No. 347," May 4,
1965; memorandum, Christopher C. Kraft, Jr., MSC, to Manager, ASPO,
"Flight Combustion Stability Monitor (FCSM)," May 13,
1965.
May 5
In response to a query, Apollo Program Director Samuel C. Phillips told
NASA Associate Administrator for Manned Space Flight George E. Mueller
that plans to use VHF communications between the CSM, LEM, and
extravehicular astronauts and to use X-band radar for the CSM/LEM
tracking were reviewed. Bellcomm reexamined the merits of using the
Unified S-Band (USB) type which would be installed in the CSM and LEM
for communication with and tracking by the earth.
It was found that no appreciable weight saving or weight penalty would
result from an all USB system in the Apollo spacecraft. Also, it was
determined there would be no significant advantage or disadvantage in
using the system. It was noted, however, that implementation of an all
S-band system at that stage of development of the design of the CSM,
LEM, and astronaut equipment would incur an obvious cost and schedule
penalty.
Memorandum, Phillips to Mueller, "Use of Only Unified S-Band
Communication Equipment in Apollo Spacecraft," May 5, 1965.
May 6
After lengthy investigations of cost and schedule impacts, MSC directed
North American to incorporate airlocks on CMs 008 and 014, 101 through
112, and 2H-1 and 2TV-1. The device would enable astronauts to conduct
experiments in space without having to leave their vehicle. Initially,
the standard hatches and those with airlocks were to be interchangeable
on Block II spacecraft. During October, however, this concept was
changed: the standard outer hatch would be structured to permit
incorporation of an airlock through the use of a conversion kit
(included as part of the airlock assembly); and when an airlock was
installed, an interchangeable inner hatch would replace the standard
one.
TWX, Samuel C. Phillips, NASA, to MSC, Attn: J. F. Shea, January 4,
1965; letters, J. B. Alldredge, MSC, to NAA, Space and Information
Systems Division (S&ID), "Contract Change Authorization No.
348," May 6, 1965; Alldredge, MSC, to NAA, S&ID,
"Contract Change Authorization No. 348, Revision 1," July 27,
1965; James Stroup, MSC, to NAA, S&ID, "Contract Change
Authorization No. 348, Revision 2," August 4, 1965; Alldredge,
MSC, to NAA, S&ID, "Contract Change Authorization No.
441," October 11, 1965.
May 6
ASPO overruled a recommendation by the Flight Operations Directorate
for an up-data link in the LEM. Although an automated means of
inserting data into the spacecraft's computer was deemed "highly
desirable," there were prohibitive consequences:
- Weight - 7.25 kg (16 lbs) in the ascent stage
- Cost - $1.7 million
- Schedule delay - five months
This last effect ASPO termed "flatly unacceptable."
Memorandum, William A. Lee, MSC, to Assistant Director for Flight
Operations, "LEM Up-Data Link," May 6, 1965.
May 6
As a result of the Critical Design Review at North American during the
previous month, Crew Systems Division (CSD) directed Hamilton Standard
to fabricate an Apollo space suit with a pressure-sealing zipper. CSD
would compare this concept with the current gusset design, which leaked
excessively and hindered donning the suit.
TWX, Richard S. Johnston, MSC, to R. E. Breeding, Hamilton Standard
Division, May 6, 1965; MSC, "ASPO Weekly Management Report, June
3-10, 1965."
May 6
The Apollo earth landing system (ELS) was tested in a drop of
boilerplate (BP) 19 at El Centro, Calif. The drop removed constraints
on the ELS for BP-22 (see May 19 ; also, it was a
"prequalification" trial of the main parachutes before the
start of the full qualification test program (see June 3).
"Apollo Monthly Progress Report," SID 62-300-37, p. 3.
May 6-13
Both General Electric and Radio Corporation of America studied the
feasibility of using the spacecraft- LEM-adapter to dissipate heat from
the radioisotope generator during initial phases of the mission. The
generator would raise the temperature of the adapter about 30 degrees;
radiation back to the spacecraft was not considered serious.
MSC, "ASPO Weekly Management Report, May 6-13, 1965."
May 6-13
Structures and Mechanics Division engineers determined that the
spacecraft-LEM-adapter would not survive a service propulsion system
abort immediately after jettisoning of the launch escape tower. North
American planned to strengthen the upper hinges and fasteners and to
resize the shock attenuators on spacecraft 009.
Ibid.
May 7
Launch escape system (LES) installation for CSM 009 was completed,
marking the first LES completion. "Apollo Monthly Progress
Report," SID 62-300-37, p. 1.
May 9
The U.S.S.R. launched a 1,476-kg (3,254-lb) scientific probe, called
Luna V, on a trajectory to the moon. Western observers,
among them England's Sir Bernard Lovell, speculated that the craft's
mission was a soft landing. If that was indeed its goal, the attempt
failed: Luna V crashed and all transmissions ceased. It
was generally thought that the vehicle's retrorockets had
malfunctioned.
Astronautics and Aeronautics, 1965, p. 222; Space
Business Daily, May 11, 1965, pp. 49-50; M. K. Tikhonravov, B.
V. Raushenbakh, G. A. Skuridin, and O. L. Vaysberg, Ten Years of Space
Research in the USSR, NASA Technical Translation F-11, 500 of:
"Desyat' let issledovaniya kosmosa v SSSR";
Kosmicheskiye Issledovaniya, Vol. 5, No. 5, pp. 643-679, 1967,
p. 17.
May 10
ASPO reviewed Grumman's recommendation for a combination of
supercritical and gaseous modes for storing oxygen in the LEM's
environmental control system (ECS). MSC engineers determined that such
an approach would save only about 14.96 kg (33 lbs) over a high-
pressure, all-gaseous design. Mission objectives demanded only four
repressurizations of the LEM's cabin. On the basis of this criterion,
the weight differential was placed at less than nine pounds.
As a result of this analysis, MSC directed Grumman to design the LEM ECS
with an all-gaseous oxygen storage system. (See June 11.)
Letter, W. F. Rector III, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Lunar Excursion Module - ECS Oxygen Storage
Configuration," May 10, 1965, with enclosures.
May 10
Public Health Service (PHS) officials revealed that the Surgeon General
had discussed the PHS/NASA relationships on back-contamination problems
with the NASA Administrator. During this discussion, the Surgeon General
proposed:
- expansion of the space biology and contamination contract program in
the PHS;
- assignment by the PHS of a liaison officer to NASA; and
- development by NASA of an interagency advisory committee on both
outbound and inbound contamination problems with PHS participation.
The Administrator and Surgeon General were reported to have agreed that
negotiations at staff level were appropriate. As a result, NASA was
drafting a proposal to go from the Administrator to the Surgeon General
embodying not only the three items listed but also proposing a NASA
organizational structure capable of implementing the objectives of the
two agencies.
Memorandum, O. E. Reynolds, Director Bioscience Programs, NASA
Headquarters, to Associate Administrator for Space Science and
Applications, "Status of the Public Health Service - National
Aeronautics and Space Administration negotiations on back
contamination," May 10, 1965.
May 10
ASPO Assistant Manager William A. Lee heard a proposal to modify the
LEM radar programs to reduce FY 1966 costs by $7 million. It was his
understanding that the proposal would be presented to the Configuration
Control Board. Lee said he at first thought the change would be
"tolerable," but later felt it was a poor idea.
The major points of the proposal were:
- Delete landing radars from LEMs 1 and 2: the landing radar was not
essential to earth-orbital missions of these two vehicles. In fact, ASPO
had planned to drop it on LEM-2 (AS-207) to save weight. Nevertheless
the proposal was a violation of the "all-up" concept, and, if
adopted, would set a precedent for further deletions.
- Delete the rendezvous radar on LEM 1.
- Use "qualifiable" but not qualified rendezvous radars on
LEMs 2 and 3.
- Install the rendezvous radars for LEMs 2, 3, and 4 at KSC rather
than at Grumman.
Lee opined that the violations of program ground rules inherent in
these changes would establish a dangerous precedent and cut back
existing margins too early in the program. It would also, he said,
"open the door to a series of 'one-of-a-type' LEMs tailored to
their specific development missions. . . . It is too early in the LEM
program to consider compromising these requirements, and to do so for
budgetary reasons almost certainly will prove to be false
economy."
Memorandum, William A. Lee, MSC, to Manager, ASPO, "Proposed
reduction in LEM radar expenditures," May 11, 1965.
May 11
Crew Systems Division let a contract to the Zaret Foundation to study
effects of radiation on the lens of the human eye. The foundation would
develop instruments that, by examining changes in the organ, would
determine the precise dose that it had absorbed. Radiation could produce
cataracts. Up to this time, however, the amount of radiation that could
be absorbed safely was not known, nor could the initial damage be
detected. It was generally thought that this damage was cumulative and
that it was irreparable. For the crew's safety, the amount of radiation
that the eye could sustain had to be known. And, of course, some
technique for measuring dosages was essential. (See July 2.)
"ASPO Weekly Management Report, June 3-10, 1965."
May 11
MSC instructed Grumman to negotiate award of a contract to supply
batteries for the ascent and descent stages of the LEM with
Eagle-Picher Company. Grumman had solicited and received proposals from
Eagle-Picher and Yardney Electric Corporation. The bids, including
fees, were: Eagle-Picher, $1,945,222; and Yardney, $1,101,673. Grumman
evaluated the bids; made presentations to MSC personnel; and proposed
on May 6 that they negotiate with Eagle-Picher for ascent and descent
batteries; and with Yardney for development of a lighter ascent battery
at a cost of approximately $600,000. MSC instructed Grumman not to
place the proposed development contract with Yardney, stating that such
work could be more appropriately done by MSC work with Yardney or other
battery vendors.
Memorandum of Conference, Apollo Program Management Office, "LEM
Battery Procurement, MSC Comments on GAEC Recommendation for Contractor
Selection," sgd. J. B. Trout, May 11, 1965.
May 12
Developmental testing began on a new landing device for the CM, one
using rockets (mounted on the heatshield) that would be ignited
immediately before impact. The current method for ensuring the integrity
of the spacecraft during a landing in rough water involved strengthening
of the aft structure. The new concept, should it prove practicable,
would offer a twofold advantage: first, it would lighten the CM
considerably; second, it would provide an improved emergency landing
capability.
MSC, Space News Roundup, May 28, 1965, p. 8.
May 12
MSFC informed MSC that the thrust of the H-1 engine was being uprated to
1,000 kilonewtons (205,000 lbs), thus increasing the Saturn IB's payload
capability.
Letter, Frederick E. Vreuls, MSFC, to O. E. Maynard, MSC,
"Uprating the H-1 Engine in the Saturn IB Vehicle," May 12,
1965.
May 12-June 24
Representatives from North American, Grumman, Hamilton Standard, and MSC
discussed the problem of stowing the portable life support systems
(PLSS).
The space suit for the lunar landing mission was the only operational equipment designed to go all the way to the lunar surface and return to earth. Above is a photo of a subject in that suit as designed at that time, with the portable life support system strapped on.
Current specifications called for two PLSSs under the crew couch in the
CM at launch, one of which would be brought back to earth. This location
presented some serious problems, however. (See April 29-May 6.)
MSC officials laid down several ground rules for the discussions:
- The capability for extravehicular transfer must be maintained.
- During translunar flight, the capability must exist for general
extravehicular activity from the CM.
- And upon landing, the PLSS must not interfere with the sweep of the
crew couch.
The participants explored a number of stowage options (and the
complications involved), even exploring the possibilities of staging and
of using a Gemini Extravehicular Life Support System. As a result of
these talks, Hamilton Standard began studying the feasibility of
repackaging the PLSS to fit underneath the side hatch of the CM and to
determine whether the reshaped system would be compatible with both
spacecraft.
During the next few weeks, MSC concluded that, at earth launch, one PLSS
would be stowed in each spacecraft. With the help of Hamilton Standard
engineers, North American and Grumman designers worked out a stowage
volume acceptable to all concerned. Hamilton Standard agreed to
repackage the PLSS accordingly. MSC ordered North American to provide
for stowage of one PLSS beneath the side hatch of the CM, again
stressing that the system must not interfere with the crew couch during
landing impact; also, the Center directed Grumman to plan for PLSS
stowage in the LEM and to study ingress and egress with the reshaped
backpack. (Studies by the Crew Systems Division had already indicated
that, from the standpoints of compatibility and mobility, the new shape
probably would be acceptable.)
TWX, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, May 17, 1965;
memorandum, Charles R. Haines, MSC, to Owen E. Maynard,
"PLSS," May 25, 1965; memorandum, Haines, to Record,
"PLSS stowage study," May 25, 1965; "ASPO Weekly
Management Report, May 27-June 3, 1965"; MSC, "ASPO Weekly
Management Report, June 10-17, 1965"; memorandum, R. Wayne Young,
MSC, to James L. Neal, "PLSS stowage in the LEM," June 21,
1965; letter, J. B. Alldredge, MSC, to NAA, Space and Information
Systems Division, Attn: J. C. Cozad, "Contract NAS 9-150, Portable
Life Support System (PLSS) Stowage in the Command Module," June
24, 1965.
May 13
Samuel C. Phillips, Apollo Program Director, issued the mission
directive for Apollo-Saturn 201. The mission would flight-test the
Saturn IB and the Apollo CSM.
NASA OMSF, "Apollo Program Flight Mission Directive for
Apollo-Saturn 201 Mission," Program Directive M-D MA 2240.061, May
13, 1965.
May 13
AC Spark Plug officials presented to MSC their evaluation of bidders to
design an optical rendezvous sensor for the LEM. Because three different
approaches were planned, AC gained Guidance and Control Division's
approval to let three subcontracts. The firms chosen were Perkin-Elmer,
Hughes Aircraft, and the Itek Corporation.
MSC, "ASPO Weekly Management Report, May 20-27, 1965."
May 13-20
Crew Systems Division (CSD) representatives contracted with Northrop
Space Laboratories to study physiological effects of tailward g forces.
(CSD believed these forces might be "very hazardous."
Consequently, the lowest impact limits for Apollo missions were in that
direction.) Northrop would study bradycardia (slow heart rate) in
animals induced by such acceleration, and would apply these findings to
humans. CSD hoped thereby to determine whether current limits were
"ultraconservative."
MSC, "ASPO Weekly Management Report, June 3-10, 1965."
May 13-20
To broaden communications capabilities during near-earth phases of a
mission, the S-band omnidirectional antennas on all Block II CMs were
moved to the toroidal (doughnut-shaped) section of the forward
heatshield.
MSC, "ASPO Weekly Management Report, May 27-June 3, 1965."
May 16-June 15
North American released a preliminary report, "Apollo Reliability
Modeling Documentation," in response to an action item assigned to
MSC by the President's Scientific Advisory Committee (PSAC) Space
Technology Panel at an Apollo program reliability briefing for the
panel in January. The expected crew safety reliability was assessed at
0.973 with a confidence level of 60 percent. Functional logic diagrams
indicated the amount of redundancy in each CSM function. North American
noted that a direct comparison should not be made between mission
AS-506 lunar orbit rendezvous (LOR) crew safety reliability and the
preliminary crew safety number 0.976 for spacecraft 012. The LOR
assessment, while preliminary, was developed in greater depth than the
assessment for the PSAC briefing. However, a real increase in
reliability was indicated from spacecraft 012 to the LOR mission
because the reliability values were about equal, and the complexity and
number of required functions in the LOR were far greater.
NAA, "Apollo Monthly Progress Report," SID 62-300-38, July 1,
1965, p. 13.
May 16-June 15
North American conducted the third in a series of water impact tests on
boilerplate 1 to measure pressures on forward portions of the
spacecraft. Data from the series supported those from tests with one-
tenth scale models of the CM. The manufacturer reported, therefore, that
it planned no further full-scale testing.
Ibid., p. 3.
May 17
MSC informed Grumman it believed it would be beneficial to the LEM
development program for MSC to participate in the manned environmental
control system tests to be conducted in Grumman's Internal Environment
Simulator. The following individuals were suggested to participate:
Astronaut William A. Anders or an alternate to act as a test crewman for
one or more manned runs; D. Owen Goons or an alternate to act as a
medical monitor for the aforementioned astronaut; and John W. O'Neill or
an alternate to monitor voice communications during the test and record
astronaut comments.
Letter, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, MSC participation in Grumman manned
environmental control system (ECS) tests," May 17, 1965.
May 18-20
Representatives from Motorola, RCA, Grumman, and MSC held the first
design review on the S-band transponder for the LEM. Several areas were
pointed out in which the equipment was deficient. Motorola was
incorporating improved circuitry to ensure that the transponder met
specifications.
Letter, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, Rendezvous Radar Transponder Assembly
Design," May 28, 1965; TWX, Young to Mullaney, "Communication
Subsystem Input Voltage Levels," June 1, 1965; TWX, Young to
Mullaney, "LEM S-Band Transponder," June 1, 1965.
May 19
Apollo mission A-003, a planned high-altitude abort test, was flown at
WSMR. About 25 seconds after launch, and at an altitude of about three
miles, the Little Joe II booster disintegrated as a result of violent -
and unprogrammed - roll. The launch escape system (LES) functioned
perfectly, however, and lifted the spacecraft (boilerplate 22) clear of
the vehicle. ASPO Manager Joseph F. Shea, while acknowledging that
A-003's "prime objectives . . . were not met," rightly
observed that the LES nonetheless "proved its mettle in an actual
emergency," (See mission objectives in Appendix 5.)
NASA News Release 54-145, "NASA to Test Apollo Escape System at
High Altitude," May 9, 1965; memorandum, George E. Mueller, NASA,
to Administrator, "Apollo Spacecraft Flight Abort Test, Mission
A-003, Post Launch Report No. 1," May 24, 1965, with enclosure;
MSC, Space News Roundup, May 28, 1965; TWX, NASA, MSC/
WSO, to addressees, "Apollo Mission A-003 one hour report,"
sgd. J. F. Shea, May 19, 1965; General Dynamics, Convair Division,
Little Joe II Test Launch Vehicle, NASA Project Apollo: Final
Report, GDC-66-042 (May 1966), Vol. I, p. 1-18.
May 20-27
Engineers from General Electric and MSC's Crew Systems and Systems
Engineering Divisions determined that transferring water from the CSM to
the LEM involved a 5.4-kg (12-lb) increase in the latter's separation
weight. Grumman had placed the penalty at only l.8 kg (4 lbs). Because
the LEM's weight was so critical, the water transfer scheme was
canceled.
TWX, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney, June 3, 1965.
May 20-27
To determine lunar touchdown velocity uncertainties, MIT studied
radar-aided powered descent. From MIT's findings, Guidance and Control
Division concluded that one or two sensors should provide velocity
updates to the guidance system throughout the descent maneuver.
MSC, "ASPO Weekly Management Report, June 10-17, 1965."
May 21
Marquardt Corporation completed preliminary flight rating tests on the
reaction control engine for the SM.
"Apollo Monthly Progress Report," SID 62-300-38, p. 10.
May 22
NASA launched another reentry heating experiment, Project Fire II, from
Cape Kennedy, Fla. An Atlas D booster propelled the instrumented probe,
called a "flying thermometer," into a ballistic trajectory
over 805 km (500 mi) high. After 26 minutes of flight, when the
spacecraft began its descent, a solid-fueled Antares rocket accelerated
its fall.
The probe entered the atmosphere at a speed of 40,877 km (25,400 mph)
and generated temperatures of about 11,206K (20,000 degrees F). Data on
heating were transmitted to ground stations throughout the descent.
Thirty-two minutes after the launch - and but six minutes after the
Antares was fired - the device impacted in the Atlantic about 8,256 km
(5,130 mi) southeast of the Cape.
NASA News Release 65-131, "NASA Schedules Project Fire Launch in
May," April 28, 1965; NASA News Release 65-179, "NASA Reports
Project Fire Performed Well," May 27, 1965.
May 23
The Life Sciences Committee of the National Academy of Sciences' Space
Science Board recommended to NASA that American astronauts returning
from the moon and planets be kept in quarantine for at least three
weeks to prevent possible contamination of the earth by
extraterrestrial organisms, Howard Simons reported in the Washington
Post. A report entitled "Potential Hazards of Back Contamination
from the Planets" presented quarantine and other recommendations:
the need to avoid decontamination of returning equipment until it had
been subjected to biological study; the possible need for the
astronauts to shed their outer garments on the moon and Mars before
returning home; the need to conduct immediate research on any samples
of extraterrestrial life brought to earth; and trial runs to acquaint
astronauts with methods for minimizing chance of contamination.
Astronautics and Aeronautics, 1965, p. 246.
May 21-24
The Resident ASPO at Grumman approved three vendor selections by the
LEM manufacturer:
- Mechanical Products, Inc. - circuit breakers. (MSC concurred in the
use of hermetically sealed breakers.)
- Hartman Electric Co. - relays (also hermetically sealed).
- Electronic Products Division of Hughes Aircraft Co. - rectangular
connectors.
MSC, "ASPO Weekly Management Report, May 20-27, 1965";
memorandum, Ralph S. Sawyer, MSC, to Chief, Systems Engineering
Division, "Common usage of Circuit Breakers," May 18,
1965.
May 24
MSC concurred in Grumman's selection of the RF tracking mode for the
LEM's steerable antenna.
Letter, R. Wayne Young, MSC, to GAEC, Attn: R. S. Mullaney,
"Contract NAS 9-1100, LEM high gain steerable antenna RF
tracker," May 24, 1965.
May 24
At Wright-Patterson AFB, North American engineers conducted zero-g
tests of crew transfer using mockup 27 A. The two subjects, astronauts
Donn F. Eisele and Richard F. Gordon, had difficulty manipulating the
forward hatches and the drogue assembly. North American reported that
handles might be required on those pieces of hardware.
"Apollo Monthly Progress Report," SID 62-300-38, p. 5;
memorandum, Donald K. Slayton, MSC, to Manager, ASPO, "CM/LEM
Tunnel Hatches and Docking Hardware Zero Gravity Removal and
Installation Test," June 18, 1965.
May 24
Donald K. Slayton, Assistant Director for Flight Crew Operations,
described a potential hazard involved in crew procedures inside the LEM.
Two sets of umbilicals linked the Block II space suit to the
environmental control system (ECS) and to the portable life support
system (PLSS). Though slight, the possibility existed that when a hose
was disconnected, the valve inside the suit might not seat. In that
event, gas would escape from the suit. Should this occur while the LEM
was depressurized, the astronaut's life would be in jeopardy.
Consequently, Slayton cautioned, it would be unwise to disconnect
umbilicals while in a vacuum. This in turn imposed several mission
constraints:
- PLSSs could not be recharged while the LEM was unpressurized.
- If the astronauts were planning to leave the spacecraft, they had to
switch to the PLSSs and disconnect the ECS hoses before depressurizing
their vehicle.
- Because the cooling circuit in the PLSS operated only in a vacuum,
the crew must depressurize the LEM shortly after switching to their
PLSSs.
Memorandum, Slayton, MSC, to Chief, Systems Engineering Division,
"Apollo suit procedures inside the LEM," May 24, 1965.
May 25
Pegasus "finds" a meteoroid.
NASA launched Pegasus II, a meteoroid detection satellite,
from Cape Kennedy. (See February 16, 1965.) The Saturn I launch vehicle
(SA-8) placed the spacecraft, protected by a boilerplate CSM (BP-26),
into a 740-by-509-km (460-by-316-mi) orbit. Once in orbit, the dummy
CSM was jettisoned. Pegasus II, still attached to the
second stage of the launch vehicle, then deployed its 29-m (96-ft)
winglike panels. Within several hours, the device began registering
meteoroid hits.
NASA News Release 65-151, "NASA to Launch Second Pegasus Meteoroid
Satellite," May 17, 1965; NAA, "Project Apollo Spacecraft
Test Program Weekly Activity Report (Period 24 May 1965 through 30 May
1965)," pp. 1-2; MSFC Historical Office, History of the
George C. Marshall Space Flight Center from January 1 through December
31, 1965 (MHM-11), Vol. I, p. 53.
May 25
MSC directed North American to install Block II-type, flush-mounted
omni-directional S-band antennas on CMs 017 and 020. These antennas
would survive reentry and thus would afford telemetry transmissions
throughout the flight. On June 25, the Center ordered that they be
installed in the toroidal (doughnut shaped) section of the aft
heatshield.
Letters, James Stroup, MSC, to NAA, Space and Information Systems
Division (S&ID), "Contract Change Authorization No. 357,"
May 25, 1965; J. B. Alldredge, MSC, to NAA, S&ID, "Contract
Change Authorization No. 357, Revision 1," June 25, 1965.
May 25
ASPO pointed out to the Systems Engineering Division that planning of
the manned Apollo missions had been constrained to maximize the Manned
Space Flight Network support available for guidance and navigation
(G&N) functions. While this was a desirable technique to maximize
mission success probabilities, it led to a tendency to neglect onboard
G&N capabilities.
"It is ASPO policy that, wherever feasible, both onboard and ground
systems will be exercised fully during manned developmental missions.
Spacecraft maneuvers should be computed both on the ground and in the
flight vehicle, and the results of these computations recorded and
compared. . . . It is requested that Apollo mission planning conform to
this policy and that any tendency to omit full exercise of the onboard
G&N capability be corrected."
Memorandum, William A. Lee, MSC, to Chief, Systems Engineering
Division, "Utilization of onboard G&N capability during Apollo
Manned Development Missions," May 25, 1965.
May 25
MSC completed contract negotiations with Westinghouse Electric Company
on gear for the LEM's television camera (cables and connectors, stowage
containers, and camera mockups). Because of technical requirements, the
idea of using the same cable in both spacecraft was abandoned.
MSC, "ASPO Weekly Management Report, May 27-June 3, 1965."
May 26
To aid reacquisition and tracking of the high-gain antenna, MSC directed
North American to study the feasibility of an inertial reference system
on Block II spacecraft, one that would use rate signals from the CSM's
stabilization and control system. Without this system, the astronauts
would have to perform anywhere from 250 to 500 antenna reacquisitions
during a single lunar mission. And during sleeping periods, when the CM
pilot was alone in the vehicle, it was mandatory that the antenna
automatically reacquire the earth.
Letters, James Stroup, MSC, to NAA, Space and Information Systems
Division (S&ID), "Contract Change Authorization No. 358,"
May 26, 1965; J. B. Alldredge, MSC, to NAA, S&ID, "Contract
Change Authorization No. 358, Revision 1," July 23, 1965.
May 26
ASPO requested the Apollo Program Director to revise the LEM control
weight at translunar injection as follows:
- Ascent stage - 2,193kg (4,835lbs)
- Descent stage - 2,166kg (4,775lbs)
- Total LEM (fueled) - 14,515kg (32,000lbs)
The increase would be made possible by reductions of service propulsion
system propellant requirements associated with the revised delta-V
budget. ASPO pointed out that existing CSM and adapter control weight
propellant requirements allowed a maximum LEM injected weight of 14,877
kg (32,800 lbs) with no increase in the launch vehicle payload
requirement.
Letter, Joseph F. Shea, MSC, to NASA Headquarters, Attn: Director
Apollo Program, "Revised LEM Control Weights," May 26,
1965.
May 26
William A. Lee, ASPO Assistant Manager, asked Systems Engineering
Division to study the feasibility of an abbreviated mission, especially
during the initial Apollo flights. Because of the uncertainties involved
in landing, Lee emphasized, the first LEMs should have the greatest
possible reserves. This could be accomplished, he suggested, by
shortening stay time; removing surplus batteries and consumables; and
reducing the scientific equipment. Theoretically, this would enable the
LEM pilot to hover over the landing site for an additional minute; also,
it would increase the velocity budgets both of the LEM's ascent stage
and of the CSM. He asked that the spacecraft's specifications be changed
to fly a shorter mission:
- Stay time - 10 hours
- Exploration time - six man-hours
- Scientific payload - 32 kg (70 lbs)
- Lunar samples returned - 36 kg (80 lbs)
Lee said that this modification would produce a spacecraft that could be
adapted to short and long missions.
Memorandum, William A. Lee, MSC, to Chief, Systems Engineering
Division, "Spacecraft capability for short-duration lunar landing
missions," May 26, 1965.
May 27
Because correspondence from Grumman and the Resident ASPO there hinted
at deleting some equipment from the first LEM, MSC reaffirmed that LEM-1
would be an "all-up" spacecraft, as specified in the SA-206A
mission requirements.
MSC Internal Note No. 65-PL-1 (Revision A), "Project Apollo
Mission Requirements for Apollo Spacecraft Development Mission 206A
(LEM 1)," May 11, 1965; TWX, R. Wayne Young, MSC, to GAEC, Attn:
R. S. Mullaney, "Mission Requirements for Apollo Spacecraft
Development Mission 206A (LEM I) MSC Internal Note No. 65-PL-I (Rev. A)
dated May 11, 1965," June 2, 1965.
May 27-June 3
MSC's Crew Systems Division (CSD) received from Hamilton Standard
Division a liquid cooling garment which had been modified to include a
comfort liner. Preliminary tests by the contractor showed a substantial
increase in comfort with only a small decrement to cooling capacity. CSD
scheduled tests to validate the performance.
MSC, "ASPO Weekly Management Report, May 27-June 3, 1965."
May 28
ASPO approved the use of common communications equipment in Block I and
II space suits. The hardware would be procured from North American
(under their contract with Pacific Plantronics), then furnished to the
suit contractors (David Clark and Hamilton Standard).
TWX, James Stroup, MSC, to NAA, Space and Information Systems Division,
Attn: J. C. Cozad, June 7, 1965.
May 30-June 5
ASPO Manager Joseph F. Shea reported the accomplishment of a number of
important items:
- Boilerplate 23A command module and launch escape system were moved
to the launch pad at WSMR and stacked; integrated ground support
equipment checkout was in progress.
- North American was directed to stop all work on systems installation
on CSM 006. Test objectives would be reassigned to boilerplate 14 and
CSM 008.
- The first deliverable LEM attitude and translation control assembly
had passed acceptance test at RCA and was delivered to Grumman.
- The Design Engineering Inspection on LEM descent propulsion test rig
PD-1 was completed and the rig shipped to WSMR/PSDF. The LEM ascent
propulsion rig HA-4 was shipped to AEDC for ascent engine environmental
tests.
- The LEM Technical Specification and the LEM Master End Item
Specification were incorporated into the Grumman contract on June 1,
1965. "Weekly Activity Report, May 30-June 5," sgd. Joseph F.
Shea.
During the Month
Thiokol Chemical Company completed qualification testing on the tower
jettison motor. An ignition delay on February 22 had necessitated a
redesign of the igniter cartridge. Subsequently, Thiokol developed a
modified pyrogen seal, which the firm tested during late August and
early September.
"Apollo Monthly Progress Report," SID 62-300-38, pp. 2, 8,
11.
During the Month
Using one-third scale models, Grumman tested the LEM's antenna field at
the extremes of the frequency range. Data evaluation showed that the
range was adequate; errors were well within expected values.
"Monthly Progress Report No. 28," LPR-10-44, p. 16.
During the Month
Using improved restraint hardware, Grumman resumed tests simulating the
shock of landing on the moon. Investigators reported better lateral
stability - and they no longer bounced off the floor. Astronaut Donn F.
Eisele, who took part, judged the system superior to those used in
earlier trials.
Ibid., p. 14.
During the Month
Bell Aerosystems Company successfully cycled a LEM ascent engine
propellant valve 500 times (double the specification requirement).
Also, the company conducted a full-duration altitude firing with an
ablative nozzle extension to verify heating characteristics.
Ibid., p. 1.
During the Month
MSC postponed the formal LEM program review (wherein spacecraft
requirements would be redefined and Grumman's contract converted to an
incentive type). The Center directed the company to submit firm
proposals for all contract change authorizations (CCA), which were
promised by July 11. Grumman was preparing a revised estimate of total
program cost. In the meantime, both parties were negotiating on all
outstanding CCAs.
Also, Grumman described its continuing cost reduction effort. To keep
expenditures within limits "suggested" by MSC, the firm was
preparing detailed budgets both for itself and its subcontractors. The
company had made a number of changes to strengthen its administrative
structure and, with Houston's support, was reviewing possible schedule
changes with an eye toward eliminating some test vehicles.
Ibid., p. 1.
During the Month
Three flights were made with the lunar landing research vehicle (LLRV)
by FRC pilot Don Mallick for the purpose of checking the initial
weighing, the thrust-to-weight, and the automatic throttle systems.
General Electric would update the LLRV CF-700 jet engines at their
Edwards AFB facility rather than at Lynn, Mass. The change in work
location would mean an earlier delivery date and a significant cost
reduction. The updating would make the engines comparable to the
production engines and would add an additional 890 newtons (200 lbs) of
thrust.
Letter, Paul F. Bikle, FRC, to NASA Headquarters, "Lunar Landing
Research Vehicle progress report No. 23 for the period ending May 31,
1965."