Key Dates in Assessment of
Viking Science Proposals
|
|
.
|
|
11-12 Sept. 1969
|
Pre-proposal briefing for
potential experimenters.
|
|
20 Oct. 1969
|
Proposals due at NASA
Headquarters.
|
|
23 0ct. 1969
|
Copies of proposals due at Langley
and JPL; meeting held at Langley to discuss
proposals.
|
|
3-4 Nov. 1969
|
First Space Science and
Applications Steering Committee (SSASC) subcommittee
meetings to initiate evaluation process, Goddard Space
Flight Center.
|
|
7-8 Nov. 1969
|
Review of science proposals at
Langley.
|
|
12-14 Nov. 1969
|
Second subcommittee meetings,
Goddard.
|
|
17 Nov. 1969
|
Viking Project Office assessments
of proposals due at NASA Headquarters.
|
|
18-20 Nov. 1969
|
Definition of science payload by
Headquarters Planetary Program Office.
|
|
21 Nov. 1969
|
Tentative payload presentation to
D. P. Hearth, director, Planetary Program Office.
|
|
26 Nov 1969
|
Planetary Program Office
recommendations made to SSASC.
|
|
3 Dec. 1969
|
Recommendations presented to SSASC
in writing.
|
|
8 Dec. 1969
|
Oral presentation to SSASC.
|
|
15 Dec. 1969
|
Selection of Viking science
payload by John E. Naugle, associate administrator for
space science and applications, based on SSASC
recommendations.
|