Key X-33 Events in 1997
Click on the date to go to a related news release and any associated photos.
Many thanks to Ann Gaudreaux, NASA Langley Research Center; Tony Jacob, NASA
Marshall Space Flight Center; and Jim Cast, NASA Headquarters, for supplying the
news releases and photographs found here.
1997
NASA Langley Research Center press release about X-33 wind tunnel testing during
Phase I in Langley's 22-Inch Mach 20 Helium Tunnel.
NASA held a public meeting in Idaho Falls, Idaho, to gather public comment on
its plan to conduct flight tests of the X-33. The meeting was part of NASA's Environmental
Impact Statement (EIS) process in support of the X-33 program. The formal scoping
process began on October 7, 1996, after NASA published Notice of Intent 96-118 in
the Federal Register. The Idaho Falls meeting was the twelfth public meeting held
by NASA to discuss the potential environmental impact of the X-33 test flights. Earlier
meetings were held in towns neighboring proposed takeoff and landing sites in Southern
California, Utah, Washington, and Montana.
1997
February 20
A 7.75 percent scale model of the X-33 completed two weeks of wind tunnel tests
in the 5.1-meter transonic wind tunnel at the Air Force's Arnold Engineering Development
Center at Arnold Air Force Base, Tullahoma, Tennessee, according to Space Log,
March 10-16, 1997.
1997 March
An aluminum and stainless steel model of the X-33 was tested in NASA Langley's
Low-Turbulence Pressure Tunnel.
NASA announcement that surveying was underway at Edwards Air Force Base, California,
in preparation for the construction of the X-33 launch site. Sverdrup Corporation,
the X-33 team's launch facility contractor, was undertaking the surveying of the
launch site, which is located at the Air Force's Phillips Laboratory's Propulsion
Directorate, specifically at Haystack Butte. Construction of the launch pad and facilities
was expected to be complete by September. 9, 1998. Launch facility activation, which
includes verification of the launch pad fueling system, was scheduled to be complete
by October 1, 1998.
NASA announced that an aluminum and stainless steel scale model of the X-33 ---
about 38 cm (15 inches) long by 38 cm (15 inches) wide --- was undergoing extensive
wind tunnel testing at NASA Langley Research Center in Hampton, Va, in Langley's
16-Foot Transonic Tunnel through mid-April 1997.
1997
April 16
Continuing wind tunnel testing at Marshall Space Flight Center to correct X-33
control deficiency at low supersonic speeds (Mach 1 to 2). Adding canards appeared
to be the only viable solution to date.
NASA's Marshall Space Flight Center announced that in Marshall Propulsion Laboratory's
East Test Area, Marshall had conducted hot-fire tests of components for the X-33
linear aerospike engine. The test apparatus consisted of three hydrogen-cooled thrust
cells constructed to represent a section of the X-33 engine, which will have two
banks of 10 side-by-side thrusters. Test results were to be reviewed with Rocketdyne,
which built the test thrust cells, and which will build the X-33 aerospike engine.
1997 May
Wind tunnel testing of a scale model X-33 in the Langley Research Center's Unitary
Wind Tunnel at supersonic speeds ranging from Mach 1.5 to 4.5 continued from mid-April
to early May. Wind tunnel testing also continued through May at the Marshall Space
Flight Center.
1997
May
A "tiger team" was working full-time on reducing 5000 to 6000 pounds
from the dry weight (without fuel) of the X-33. The team sorted through over 400
recommendations to reduce weight.
1997
May 21
Presentation by the "tiger team" working on the X-33 weight problem.
Weight reduction recommendations were ranked according to minor, medium, or major
cost and schedule impacts. The team indicated that about 8 000 to 11 000 pounds of
weight could be reduced, but the X-33 project costs and schedule would be affected.
1997 June
Additional wind tunnel testing of X-33 models took place in June 1997 in the
Langley Research Center's Hypersonic Facilities Complex. Also, X-33 wind tunnel testing
started in Langley's 14- by 22-Foot Subsonic Tunnel in mid-June.
1997
June 24
Aerospace Daily reported that "typical development problems"
had led to the postponement of the first X-33 test flight from March to July of 1999,
and the slippage of the Critical Design Review from September to an unspecified time
in the fall. A critical problem behind the postponement was fabrication of the liquid-hydrogen
fuel tank. In addition, Aerospace Daily reported that the Lockheed Martin
Skunk Works had consolidated X-33 project management at Palmdale, California, and
that Jerry Rising had been named vice president for X-33 and reusable launch vehicles.
Rising replaced T.K. Mattingly, who transferred to Lockheed Martin's aeronautical
division at corporate headquarters in Bethesda, Maryland.
NASA releases draft Environmental Impact Statement.
1997 July
In mid-July, wind tunnel testing of X-33 models in the Langley Research Center's
14- by 22-Foot Subsonic Tunnel concluded.
1997
July 3
Aerospace Daily reported on X-33 progress, based on an interview with
Jerry Rising, Lockheed Martin Skunk Works vice president and program director for
the X-33. The Skunk Works was considering use of a colder, denser cryogenic propellant,
and had dropped plans to add canards for vehicle stability in the low transonic range
(Mach 1 and 2). The canards were dropped in favor of changes in the tail structure.
Weight growth was under attack by a special "tiger team."
The Linear Acrospike SR-71 Experiment was mounted on a NASA SR-71 aircraft at
the NASA Dryden Flight Research Center, Edwards, Calif., in preparation for the experiment's
first flight, then scheduled for sometime in September.
1997
August 26
Aerospace Daily reported that a gas generator adapted for the X-33 aerospike
engine from a J-2 Saturn rocket engine had undergone fourteen hot-fire tests at NASA
Marshall Space Flight Center.
NASA Langley Research Center conducted load tests of a full-scale segment of
a composite intertank structure for the X-33 program.
1997
September 11
Aerospace Daily reported on X-33 progress. Five of eight 100-pound liquid
hydrogen tank panels had been fabricated by Alliant TechSystems in a Utah plant,
and tests of the composite seams were proceeding without any surprises. The liquid
oxygen tank had been welded together. A "big hunk" of vehicle weight was
cut by removing the turbo alternator. Cooling the liquid oxygen and hydrogen propellants
to temperatures lower than normal helped to cut overall vehicle weight even further,
and to allow the X-33 to carry additional fuel.
1997
September 18
End of two-day Design Review of the X-33 Thermal Protection System by Rohr at
its Chula Vista, California, facility.
1997
September 24
End of the two-day Critical Design Review of the X-33 aerospike engine (known
also as the XRS-2200 engine). The CDR took place at Rocketdyne's DeSoto campus in
Chattsworth, California, where the X-33 engines are being designed.
NASA released the Final Environmental Impact Statement for the X-33, and indicated
preferred flight testing launch and landing sites.
NASA announced that the X-33 had completed the five-day vehicle Critical Design
Review (CDR) successfully. This was a major event in the evolution of the X-33. With
completion of the CDR, NASA gave the Skunk Works approval to proceed with the fabrication
of all remaining components and the assembly of the flight vehicle. Over 590 people
selected by the Lockheed Martin Skunk Works attended the CDR. The package of CDR
technical information contained some 2750 charts in 11 volumes.
First successful flight of the LASRE experiment at NASA's Dryden Flight Research
Center.
NASA completed its Record of Decision (ROD) on the X-33 Environmental Impact
Statement (EIS), and announced it intended to proceed with the preferred X-33 flight
test program as described in the Final EIS issued October 3, 1997.
Groundbreaking ceremony took place at future X-33 launch site on Edwards Air
Force Base.