Key X-33 Events in 1998
Click on the date to go to a related news release and any associated photos.
Many thanks to Ann Gaudreaux, NASA Langley Research Center; Tony Jacob, NASA
Marshall Space Flight Center; and Jim Cast, NASA Headquarters, for supplying the
news releases and photographs found here.
1998
1998
January 1
The new year started off wet, when a faulty control system in the X-33 construction
hanger set off water canons intended to fight fires. A crew of about a dozen on New
Year's Eve worked to dry out the X-33 construction area. No permanent damage resulted,
and work continued as usual.
1998
January 14
Construction of the X-33 launch site at Haystack Butte progressed. Sverdrup completed
rough grading of the launch site. The new road to the launch site was driveable,
but , like the site in general, was still at subgrade level.
1998
January 21
Sverdrup completed rough grading of the X-33 launch site.
The first major X-33 component, the liquid oxygen tank, was delivered to the
Palmdale, California, hanger where construction of the vehicle was taking place.
Delivery was made by an Airbus A300-600ST.
1998 February 12
The ground cold flow test of the LASRE was performed on this date. This test
included one normal cold flow and one emergency systems cold flow. The emergency
systems cold flow tested the effects of control system power loss during flight.
The liquid oxygen tank pressurized normally during the first (normal cold flow) test,
validating the repair that had been made to the vent system. The emergency test appeared
to have been successful. A data review was scheduled for February 18, 1998.
1998 February 25
A routine X-33 quarterly review took place at Marshall Space Flight Center. Presentations
surveyed current program progress.
1998 February 25
Launch site construction continued to progress as all Edwards Air Force Base
infrastructure (roads, power, water, and communications) were extended to the site.
A NASA SR-71 completed its first cold flow flight as part of the Linear Aerospike
SR-71 Experiment (LASRE) at NASA's Dryden Flight Research Center, Edwards, Calif.
1998 March 11-12
The NASA Independent Annual Review of the X-33 program took place. X-33 technical
and cost performance was surveyed. A final report detailing findings and conclusions
was to be briefed to the NASA Program Management Council on April 15, 1998. The Review
indicated that the Skunk Works had addressed many of the concerns that arose during
the September 1997 Independent Annual Review. NASA's Gary Payton and Gene Austin
were very pleased with the review results.
1998 March 20
During a project review held at the Rocketdyne facility in Canoga Park, Rocketdyne
made known certain schedule hazards that had developed with two of their suppliers,
Weldmac and CFI. It was reported that, in the worst case, aerospike engine deliveries
might slip three to five months. Rocketdyne was looking into their suppliers' difficulties
in hopes of mitigating risk to the program schedule.
1998 April 8
With the exception of some fastener shortages, the center thrust structure of
the X-33 vehicle was now complete.
1998 April 19
The liquid oxygen tank was moved into the main assembly fixture. The move took
less than an hour, and was completed two days ahead of schedule.
NASA's F-15B Aerodynamic Flight Facility aircraft was flight testing thermal
protection materials intended for use on the X-33 on an F-15B fighter to determine
the durability of the materials, specifically measuring the shear and shock loads
to which the materials are exposed. The F-15B is a NASA test aircraft based at Dryden
Flight Research Center, Edwards, Calif. The materials tested included metallic Inconel
tiles, soft Advanced Flexible Reusable Surface Isolation tiles, and sealing materials.
1998 June 8
Aerospace Daily reported: "Lockheed Martin is carrying a 'three-month
hazard' on the linear aerospike engine it will need to power the X-33 testbed next
summer, but Rocketdyne has developed workarounds and fixes to get the engine back
on track," citing Lockheed Martin program manager Jerry Rising.
1998 June 8
Aerospace Daily reported that leakage into the structure of the subscale
aerospike mounted on NASA's SR-71 Blackbird had delayed the first hot-fire test of
the engine "a few weeks."
1998 June 8
As reported in Aerospace Daily, X-33 program manager Jerry Rising and
X-34 program manager Bob Lindberg threatened to not allow their X vehicles to fly,
unless Congress passes indemnification legislation protecting them against third-party
liability in case of an accident during flight testing.
NASA announced that pictures of the X-33 vehicle and launch site, taken every
fifteen minutes from three digital cameras, would be posted to an Internet address:
http://stp.msfc.nasa.gov/cameras/camera.html.
Camera A shows the vehicle's primary assembly structure, while Camera B shows
side-by-side tooling structures for the X-33's upper thermal protection system and
the vehicle's upper internal support structure. A third camera focuses on the vehicle's
launch pad. The vehicle images will not be current, but will be delayed one day.
NASA announced completion of the F-15B flight testing of thermal protection materials
for the X-33 at NASA's Dryden Flight Research Center, Edwards, CA. The six flights
tested the durability of the materials at hypersonic velocities. The F-15B reached
an altitude of 36,000 feet and a top speed of Mach 1.4. The material samples tested
included metallic Inconel tiles, soft Advanced Flexible Reusable Surface Insulation
tiles, and sealing materials.
1998 July 6
Aerospace Daily, in an article titled "Wagons Ho!" reported
that the Lockheed Martin Skunk Works had abandoned flying the X-33 back to its launch
pad at Edwards AFB in favor of trucking the experimental aircraft overland, "because
the Shuttle program won't give up one of its two Boeing 747s for ferry flights."
1998 July 22
Difficulties with fabricating the X-33 liquid hydrogen tanks continued. as a
result, delivery dates for the two tanks slipped from July 31st and September 2nd
to mid-October and mid-November, respectively. The impact of these delays on vehicle
assembly was still be assessed.
1998 July 29
Aerojet recommended to NASA and Lockheed Martin that they use a thruster configuration
that includes a nozzle made of columbium to correct for the thermal problems that
had caused nozzles to burn through in earlier tests. Using columbium nozzle parts
will not increase the X-33's net weight, however preparing the parts will require
a long lead time. To minimize schedule impact, Aerojet proposed delivering the thrusters
without nozzles to allow continuation of vehicle assembly and supplying the columbium
nozzles at a later date.
1998 August 5
The X-33 System Architecture Review (SAR) and Optimized Design Review (ODR) were
held in Palmdale with representatives from each Skunk Works partner, NASA, and the
Gray Beards attending. The panel of experts known as the Gray Beards was composed
mainly of NASA senior personnel led by Del Freeman of NASA's Langley Research Center.
1998 August 26
AlliedSignal delivered the X-33 nose landing gear strut. It will be modified
into the X-33 configuration for a test fit. This same test fit already has been accomplished
for the main trunion pivots and the drag link attachments without any problems.
1998 September 2
Sam Armstrong, recently named NASA Associate Administrator for the Office of
Aeronautics and Space Transportation Technology (Code R), revealed a reorganization
during a staff briefing that would dilute the responsibilities of Gary Payton, who,
as deputy associate administrator for space transportation technology, currently
heads the X-33, X-34, and advanced space transportation programs, moving him more
into the aeronautical half of the Office. Payton would occupy a lower position, division
director, under the proposed reorganization, which was scheduled to take place on
October 1. Payton has been a champion of single-stage-to-orbit vehicles for many
years. The change seriously jeopardized the status of the program within the NASA
hierarchy.
1998 September 11
Aerospace Daily reported that the pending reorganization in NASA's Office
of Aeronautics and Space Transportation Technology (Code R) "raised the hackles"
of Rep. Dana Rohrabacher (R-Calif.), a long-time champion of single-stage-to-orbit
technology and chairman of the NASA authorization subcommittee. Rohrabacher expressed
his concerns in a letter to NASA Administrator Daniel Goldin.
1998 September 23
A nine-panel thermal protection system array was test fitted on the bottom of
the X-33 last week by a joint team of BF Goodrich and Skunk Works technicians. The
metallic panels were equipped with the new secondary seal designs. One panel also
was removed from the center of the array to prove that any panel could be replaced.
1998 September 27
Continuing difficulties with fabrication of the two liquid hydrogen tanks. A
cure cycle was lost during the first doubler installation process on tank #2. The
tank was removed early from the cure cycle after blowing a bag at the end of a ramp
up point. The combination of the out time and this cure cycle resulted in an unacceptable
strength impact to the bond joints. The doublers were removed over the weekend (26-27
September) and can be replaced with existing materials. Loss of the cure cycle delayed
fabrication of tank #2 by 30 days. Construction of the vehicle structure and electronics
continued.
1998 October 2
The X-33 engine testing program began. At 12:13am Central Time, the first successful
aerospike engine-related test took place at NASA's John C. Stennis Space Center (Hancock
County, Mississippi). The test was intended to calibrate the liquid hydrogen and
liquid oxygen fuel turbopumps, to check facility settings, and to verify valve timing
to prime the gas generator. The test lasted 2.81 seconds, and no flaws or anomalies
were detected. The tested powerpack hardware consisted of the main power generating
and pumping components of the aerospike engine, including the liquid oxygen and liquid
hydrogen turbopumps, a gas generator for the turbopump drive, vehicle connect lines,
and interconnecting flight ducts. These powerpack tests are critical to the development
of the linear aerospike engine, because they allow various performance levels to
be tested in parallel with the design and construction of the engine. Full-scale
engine tests are scheduled to occur at NASA's Stennis Space Center later this year.
Steve Nunez is the Stennis X-33 project manager.
1998 October 7
B.F. Goodrich completed the last major testing of the metallic panels for the
X-33 thermal protection system at NASA's Marshall Space Flight Center, Alabama.
The reorganization of NASA's Code R--the Office of Aeronautics and Space Transportation
Technology--under Associate Administrator Spence M. Armstrong to the Office of Aero-Space
Technology. In the NASA press release, Armstrong stated that "Goldin
wanted me to personally be an advocate for the Reusable Launch Vehicle programs to
effect a cheaper means of access to space." The press release made no mention
of Gary Payton's changed role within Code R or on the X-33 program.
1998 October 14
Boeing presented their current estimate to complete. Their plan transferred $36
million from the VentureStar reusable launch vehicle (RLV) to the X-33 by eliminating
the fabrication, assembly, and testing of the RLV power pack. By adding a second
engine test stand in Phase III (the program is presently in Phase II), Boeing has
been able to develop a schedule that would support a first flight of VentureStar
within six months of the current Skunk Works schedule. In addition, Boeing declined
additional investment in the project. The $36 million transferred from VentureStar
to X-33 is the same amount as the additional X-33 costs caused by Boeing's delay
in delivering the aerospike engine (see 1998 October 27 below).
1998 October 21
The first two upper thermal protection system panels arrived at the hanger from
B.F. Goodrich's Riverside plant. They were to be test fitted on the forward most
position of the liquid oxygen tank. Repair patches for liquid hydrogen tank #1 were
completed and shipped, while work continued on the second tank.
1998 October 23
NASA announced that it and Lockheed Martin would hold a "media teleconference"
on Tuesday, Oct. 27th, at 1pm EST, with program officials Gary Payton, NASA deputy
associate administrator for space transportation technology, NASA Headquarters; Gene
Austin, NASA X-33 program manager; Jerry Rising, Lockheed Martin Skunk Works vice
president for the X-33 and VentureStar; and Cleon Lacefield, Lockheed Martin Skunk
Works X-33 program manager. A similar teleconference was the previous October to
update the media on the status of the program following the Critical Design Review.
This teleconference is expected to announce a six-month delay in the X-33 flight
tests.
1998 October 27
In a joint NASA and Lockheed Martin media teleconference, Jerry Rising, Lockheed
Martin Skunk Works vice president for the X-33 and VentureStar, announced that the
first flight of the X-33 would be delayed six months until December 1999, because
of late delivery of the aerospike engine in September 1999. This delay in engine
delivery will cost an additional $36 million. Lockheed Martin expects Rocketdyne
to absorb the additional cost. Lockheed Martin has cut out all overtime on the program
and plans to cut project personnel in order to reduce escalating costs.
1998 October 28
The two leeward #1 composite panels were delivered to the hanger for a fit check
on the vehicle. The two leeward #2 panels were to be shipped on Monday, 1 November,
for a fit check. Once the panel fit checks are made, all composite panels will be
shipped back to B.F. Goodrich's Riverside plant for completion. Also, a successful
cure cycle on liquid hydrogen tank #2 was accomplished over the weekend, 24-25 October.
As a result, all lobe skins were bonded on both tanks.
1998 November 6
NASA released the Hawthorne Report, named after the Boston firm, Hawthorne, Krauss,
and Associates, LLC, that conducted the study titled "Analysis of Potential
Alternatives to Reduce NASA's Cost of Human Access to Space." NASA intends to
use the Hawthorne Report, and the Space Transportation Architecture Study currently
under way, as guides for planning future space launchers. The Hawthorne report strongly
supported the economics of commercial reusable launch vehicles (RLVs) over continued
use of the Space Shuttle. Hawthorne, Krauss & Associates also urged NASA to exercise
caution in setting up loan guarantees to support development of commercial RLVs.
NASA has made the Hawthorne Report available on the Internet at:
ftp://ftp.hq.nasa.gov/pub/pao/reports/1998/Hawrep.pdf
1998 November 11
The X-33's electronics achieved an important milestone when Sanders shipped two
Vehicle Health Monitoring computers to the Skunk Works. Also, the Skunk Works had
identified a potential winner of the contract to transport the X-33 over land.
1998 November 13
A test of the aerospike engine power pack took place at 100% power over a period
of 30 seconds during the week ending 13 November. A 250 second test was planned for
the following week.
1998 November 18
Work began on the ballast bulkhead assembly. Faced with a continually slipping
schedule at the Sunnyvale plant, subcontractor Alliant and the Skunk Works formulated
plans to speed up work. Shift schedules will be changed so as to effectively double
manpower.
Announcement that NASA and the Lockheed Martin Skunk Works have terminated the
Linear Aerospike SR-71 Experiment (LASRE). The LASRE sought to obtain data on the
aerospike engine intended for use on the X-33 and VentureStar by mounting half of
a scale-model aerospike engine on the back of an SR-71 aircraft and studying the
effects of gas flow. The modified SR-71 carried out seven LASRE test flights. Those
flights, however, tested only cold flow gas conditions; all hot flow experiments
are now cancelled. Two flights collected aerodynamic data on the combination of the
aerospike engine with the SR-71 aircraft. In two others, gaseous helium and liquid
nitrogen were cycled through the test rig to test its plumbing, and three more flights,
liquid oxygen flowed through the system. The two hot-fire test flights planned to
validate computer models of aerospike performance in flight are now cancelled. The
LASRE was repeatedly delayed by hardware and other problems. Cancellation of the
LASRE allows any remaining funds to be used by the Skunk Works to cover X-33 cost
overruns.
1998 November 24
In its December 2, 1998, issue, Aerospace Daily reported that on November
24, 1998, Boeing's Rocketdyne Division completed the first four tests of its XRS-2200
linear aerospike engine at NASA's Stennis Space Center in Mississippi . In these
tests, the engine's turbomachinery and gas generator were run at full power, then
throttled back to 57% power.
1998 December 2
Aerospace Daily reported that NASA's Office of the Inspector General,
in an audit titled "X-33 Funding Issues" (IG-99-001), found that the NASA
Marshall Space Flight Center allowed $56 million in year-end obligations for the
X-33 to go unrecorded in fiscal years 1996 and 1997, thereby giving Congress an inaccurate
picture of the program's status at the ends of those two years. The Inspector General
reported that Marshall Space Flight Center contract officers had established an arrangement
with the Lockheed Martin Skunk Works to delay billing for completed X-33 work until
the following fiscal year. In fiscal 1996, that amounted to $22 million, and in fiscal
1997, to $34 million. The Inspector General maintained that obligations "should
be recorded not later than NASA's acceptance of the completed milestone work"
and recommended that NASA adjust its financial records to reveal the X-33 program's
financial status "fully and accurately," and that NASA review the funding
and payment practices used on the X-33 program to ensure that they meet the requirements
of the Antideficiency Act and internal controls.
1998 December 4
Senior NASA staff, Boeing representatives, and X-33 project personnel from Boeing
Rocketdyne and Lockheed Martin attended a meeting at Lockheed Martin's corporate
headquarters in Bethesda, Maryland, to discuss the development of the X-33 aerospike
engine. At the meeting, Boeing proposed to downsize the ground portion of the propulsion
demonstration program in order to use the resulting savings to fund X-33 engine cost
overruns. Three teams were formed in order to evaluate Boeing's proposal and to assess
opportunities that NASA centers might have to mitigate the impact on technology development.
The results of these independent team assessments are to be reviewed in mid-January.
1998 December 16
Construction of the X-33 continued. Both liquid hydrogen tanks completed cures.
Two gaseous oxygen tanks and two methane tanks belonging to the auxiliary propellant
system were installed on the liquid oxygen tank. The thrust structure is nearly complete.
Some clearance issues have emerged during installation of the nose gear support structure.
Power pack assembly no. 2 was completed and sent to NASA Stennis for testing, while
power pack assembly no. 1 was still having problems.
Construction of the X-33 launch site continued. The four vehicle hold down posts
were installed onto the rotating launch mount. The diesel generator for the site's
electrical supply was run for the first time. The Vehicle Positioning System was
unpacked and set up for testing. Sanders completed delivery of the Operations Control
Center hardware. The X-33 launch site is now completed.