Skunk Works' End of Year 1998 Summary

Overview

During 1998, the X-33 technology demonstrator vehicle jumped from the drawing board to the assembly floor, and 1999 will be even more dynamic as the X-33 program enters what managers explain will be an extremely busy period of testing and qualifying the X-33's cutting-edge components.

Three critical technologies to make single-stage-to-orbit (SSTO) and low-cost access to space a reality must be developed. These technologies are a rugged, durable, metallic thermal protection system; an efficient propulsion system ideally suited to power a lifting body; and most importantly, lightweight yet strong composite cryogenic fuel tanks and structures to keep vehicle weight down.

Components of these critical technologies have entered the test phase of the X-33 program, and the thermal protection system already has been declared "ready for flight."

"We've entered a period of the program almost entirely focused on testing the technologies critical to making a single-stage-to-orbit space plane a reality," said Jerry Rising, vice president of X-33/VentureStar at Lockheed Martin Skunk Works, Palmdale, Calif. "Now the importance of developing a half-scale prototype becomes clear. We're learning all the lessons - and some we never would have predicted - to really understand how to build a space plane of this nature, and how to ensure all the systems work as planned."

"The Skunk Works has a history of going where aerospace companies have never gone before, whether we're talking U-2, SR-71 or stealth technology," Rising added. "X-33 is a similar challenge we're determined to meet."

Team Completes Assembly of One Liquid Hydrogen Tank, Investigate Damage to Second

During the past few months, assembly of the X-33's two composite liquid hydrogen tanks had been progressing smoothly. While the tank designed for the right side of the X-33 has completed its eighth and final autoclave cure cycle, the left hand tank experienced damage to one of its four walls--or "lobe skins"--after completing a fifth cure cycle.

During a visual inspection, assembly technicians at the autoclave facility at Lockheed Martin Missiles and Space, Sunnyvale, Calif., noticed bubbles and cracks on the inner surface of the left hand tank's lobe skin No. 1. The tank had completed a curing cycle two days earlier to bond stabilization patches to lobe skins No. 1 and No. 4.

A team from Lockheed Martin and Alliant Techsystems, Magna, Utah, maker of the tank, is currently conducting a full analysis of the situation. Initial assessment of the situation determined that the lobe skin would have to be completely replaced. Alliant has begun manufacture of the replacement lobe skin, and crews are in the process of removing the damaged lobe skin.

Assembly of the right side liquid hydrogen tank is progressing according to schedule. Crews completed the tank's eighth and final autoclave cure cycle Jan. 11, so all major elements of the tank are now attached. After the installation of some final smaller-scale parts, the tank is scheduled to be shipped to Marshall Space Flight Center in mid- to late-March for final qualification testing.

"No composite cryogenic fuel tanks have ever been done of this size and complexity. Building and successfully flying lightweight yet strong composite cryogenic fuel tanks - especially tanks each with a complex geometry that allows them to fit within the shape of a lifting body - will be an enormous achievement," Rising said.

"The tanks are one of the toughest technical challenges we've taken on in a long time. We're working our way through the challenges, and it's all a learning process that allows us to better develop the full-scale components required for VentureStar," Rising added.

Testing Completed on First Powerpack for Linear Aerospike Engine

Rocketdyne successfully completed testing of the first powerpack for the X-33's linear aerospike engine on Jan. 16, with its seventh and final successful test on a stand at NASA Stennis Space Center, Miss. All the tests were conducted without any shutdowns caused by anomalous engine hardware.

The sixth test, completed Jan. 7, was the first to exceed the planned full engine duration of roughly three minutes. The test was run for 250 seconds and was successful in achieving all objectives.

The final test demonstrated operation of the pump at the abort throttle setting required for "powerpack out" operation. The vehicle would be required to operate in that mode if one of the two flight engine powerpacks was shut down in flight due to an anomaly. With a successful demonstration of the "powerpack out" throttle level, managers have gained increased confidence in the fact that the two-engine X-33 will be able to continue flying safely to a landing in the event one engine stops functioning during portions of the ascent.

This powerpack now will be shipped back to Rocketdyne's facility in Canoga Park, Calif., for disassembly and inspection. Meanwhile, the Canoga Park aerospike team has begun assembly of the first engine. A second powerpack will be installed on the Stennis test stand for its upcoming test series. After testing of this unit is completed, it too will be returned to Canoga Park where it will be installed into the first engine assembly. Also, major component subassemblies are progressing well in support of engine build.

Launch Site Construction Complete

Construction of the X-33 launch site, located at Edwards Air Force Base, Calif., was completed in December 1998, just a little more than 12 months after groundbreaking and under budget. This unique complex is designed to minimize operational activities between test flights and support the program's goal of low-cost access to space. Taking full advantage of the X-33 single-stage-to-orbit architecture, the complex provides for maintenance of the vehicle in the horizontal position, rotation of the vehicle to the vertical position for pre-flight servicing, and vertical launch -- all from the same location, eliminating movement of the vehicle on the ground between these operations.

One of the most distinguishing features of the launch site is the 90-foot-wide by 105-foot-long movable building that will serve as an "airplane hangar" when the X-33 is housed and serviced in the horizontal position. This simplified, low-cost launch site exemplifies the overall program philosophy of building a reusable launch system that operates more like an airplane.

Sverdrup Corp. of St. Louis accomplished the design and construction of the site in record time. "Throughout our company's history we have developed many advanced technology projects, including many launch facilities," said Ron Williams, Sverdrup vice president of aerospace. "The X-33 launch site, of which we are very proud, is a significant advancement in reducing the cost of these systems and their operation."

The X-33 launch site, which encompasses 30 acres, includes 4,000 cubic yards of concrete, liquid hydrogen and oxygen tanks capable of storing more than 300,000 gallons of cryogenic liquids, and a 250-foot-tall, 250,000-gallon water tower that will supply the deluge system at launch.

The X-33 Operations Control Center (OCC), located at Haystack Butte nearly a mile from the launch site, will serve as mission control for the X-33 flight tests. The OCC is linked to the launch site's data and communications systems through fiber optics and standard telephone cables. Locations on NASA Dryden Flight Research Center and Edwards AFB also are connected to the systems.

The X-33 launch site will be decommissioned and returned to a safe and "no-maintenance" status after the completion of the X-33 flight test program.

Thermal Protection System Declared "Ready for Flight"

The X-33's rugged, metallic thermal protection system successfully passed a rigorous test series in November that included testing in high-heat, high-speed wind tunnels; structural and thermal loads testing; and the Mach 1.4 flight aboard a NASA F-15 aircraft. Also, a thermal panel fit test was completed in mid-September at the Lockheed Martin Skunk Works. This demonstration illustrated the ease of installing TPS panels and the minimal processing time involved in removing metallic panels for replacement or to gain access to X-33 systems during flight test operations.

As the X-33 flies through the upper atmosphere, the metallic thermal panels will protect the vehicle from aerodynamic loads and heat comparable to those the VentureStar will encounter while re-entering Earth's atmosphere from orbit. The thermal protection system represents a marriage between aircraft and launch vehicle design, using easy-to-maintain metallic panels placed over insulating material. Tests have verified that the thermal protection system will protect launch vehicles from temperatures near 1,800 degrees Fahrenheit.

NASA expects the metallic thermal protection panels--developed and built by B.F. Goodrich Aerospace/Aerostructures Group in Chula Vista, Calif.--will dramatically cut maintenance time and costs associated with more fragile thermal tile systems. As the metallic panels on the lower surfaces of the X-33 and the rigid blankets on the upper surfaces make up the vehicle's aerodynamic structural shell, the system also will result in a significant weight savings over traditional thermal systems while being much more durable and waterproof.

Manufacture of X-33 TPS flight test hardware is progressing smoothly. The bulk of the TPS panels will be installed on the X-33 after installation of the vehicle's two composite liquid hydrogen tanks and surrounding support
structure.

Reaction Control System Testing Complete

The X-33 Reaction Control System (RCS) verification testing has been successfully completed by Gencorp Aerojet, Sacramento, Calif. The RCS system utilizes environmentally benign gaseous oxygen and methane as propellants to power eight rocket engines and nozzles that will be used to control the X-33's flight at high altitudes.

In December, Aerojet completed a successful mission simulation of an X-33 flight to Dugway Proving Ground, Utah. The simulation involved regulator switch-over tests and hot fire testing representative of having five thrusters operating at one time. All hardware is in excellent post-test condition.

Return to 1998 Time Line Clock