PART 1850
EXTRAORDINARY
CONTRACTUAL ACTIONS AND THE SAFETY ACT
TABLE OF CONTENTS
SUBPART 1850.1 EXTRAORDINARY
CONTRACTUAL ACTIONS
1850.102 Delegation of and
limitations of exercise of authority.
1850.102-2 Contract adjustment
boards.
1850.103 Contract
adjustments.
1850.103-5 Processing cases.
1850.103-570 Submission of request to
the Contract Adjustment Board.
1850.103-6 Disposition.
1850.103-670 Implementation of the
Contract Adjustment Board's decision.
1850.104 Residual powers.
1850.104-3 Special procedures for unusually hazardous
or nuclear risks.
1850.104-370 Subcontractor
indemnification requests.
1850.104-70 Lead NASA installation.
PART
1850
EXTRAORDINARY
CONTRACTUAL ACTIONS AND THE SAFETY ACT
Subpart
1850.1 – Extraordinary Contractual Actions
1850.102
Delegation of and limitations of exercise of authority.
1850.102-2 Contract adjustment boards.
14 CFR part 1209, subpart 3, Contract
Adjustment Board, establishes the Contract Adjustment Board (CAB) as the
approving authority to consider and dispose of requests from NASA contractors
for extraordinary contractual actions.
1850.103
Contract adjustments.
1850.103-5 Processing cases.
1850.103-570 Submission of
request to the Contract Adjustment Board.
(a)
After investigating the facts and issues relevant to the contractor's request,
the contracting officer shall forward the request to the Associate General
Counsel for General Law, including in the forwarding letter --
(1) The nature of the case;
(2)
The recommended disposition; and,
(3) If contractual action is
recommended, the contracting officer's opinion that the action will facilitate
the national defense.
(b)
The forwarding letter shall enclose the contractor's request, all supporting
material submitted by the contractor, and any material the contracting officer
has obtained while investigating the facts and issues relevant to the request.
Any classified information in the material forwarded shall be so identified.
(c)
Electronic submittal is preferred for unclassified material.
1850.103-6 Disposition.
1850.103-670 Implementation
of the Contract Adjustment Board's
decision.
(a)
The contracting officer shall take action authorized in the CAB’s decision.
(b)
Immediately upon execution, including any required Headquarters approval, of a
contract or contract modification or amendment implementing the CAB decision,
the contracting officer shall forward a copy of the contractual document to the
Associate General Counsel for General Law.
1850.104 Residual powers.
1850.104-3 Special procedures for
unusually hazardous or nuclear risks.
(a)
Indemnification requests.
(1) Contractor
indemnification requests must be submitted to the cognizant
contracting officer for the contract for which the indemnification clause is
requested. Contractors shall submit a
single request and shall ensure that duplicate requests are not submitted by
associate divisions, subsidiaries, or central offices of the contractor.
(iii) The contractor shall also provide evidence,
such as a certificate of insurance or other customary proof of insurance, that
such insurance is either in force or is available and will be in force during
the indemnified period.
(b)
Action on indemnification requests.
(1)
If recommending approval, the contracting officer shall forward the required
information to the Assistant Administrator for Procurement, Program Operations
Division, along with the following:
(i) For contracts of five years duration or
longer, a determination, with supporting rationale, whether the
indemnification approval and insurance coverage and premiums should be
reviewed for adequacy and continued validity at points in time within the
extended contract period.
(ii)
A recommended
(A) The
specific definition of the unusually hazardous risk to which the contractor is
exposed in the performance of the contract(s);
(B) A
complete discussion of the contractor's financial protection program; and
(C) The
extent to, and conditions under, which indemnification is being approved for
subcontracts.
(d)
If approving subcontractor indemnification, the contracting officer shall document
the file with a memorandum for record addressing the items set forth in FAR 50.104-3(b) and include an analysis of the subcontractor's
financial protection program. In
performing this analysis, the contracting officer shall take into consideration
the availability, cost, terms and conditions of insurance in relation to the
unusually hazardous risk.
1850.104-370 Subcontractor indemnification requests.
Subcontractors
shall submit requests for indemnification to the prime contractor and through
higher tier subcontractor(s), as applicable.
If the prime contractor agrees an indemnity clause should be flowed down
to the subcontractor, the prime contractor shall forward its written request
for subcontractor indemnification to the cognizant
contracting officer for approval in accordance with FAR 50.104-3. The prime
contractor's request shall provide information responsive to 1850.104-3, FAR
50.104-3, and FAR 50.104-3(b)(1)(i), (ii), (iv), (v), and (vii). The agreed upon definition of
the unusually hazardous risk to be incorporated into the subcontract shall be
the same as that incorporated in the prime contract.
1850.104-70 Lead NASA installation.
(a)
Contractors applying for indemnification shall determine which NASA
installation has the highest dollar amount of contracts for which
indemnification is requested. The
indemnification request should be submitted to the procurement officer for that
installation, who will then designate a cognizant
contracting officer. Contractors shall submit a single request and ensure
duplicate requests are not submitted by associate divisions, subsidiaries, or
central offices of the contractor.
(b)
The receiving installation will become the lead installation and will remain so
indefinitely. Lead installation
designation may change to another installation if the affected procurement
officers agree to the change. Should a change occur in the lead installation,
all records related to indemnification of that contractor shall be transferred
to the gaining installation.