CANCELLED BY PIC 09-09
June 15, 2001
CONTRACTOR PERFORMANCE INFORMATION AND PAST PERFORMANCE DATA BASE (PPDB)
PURPOSE: Provide updated guidance for use of NASA's automated PPDB. This updated guidance will enable more uniform Agencywide compliance with the requirements of FAR Subpart 42.15, Contractor Performance Information, and implementation of the NASA PPDB.
BACKGROUND: In April 2000, required use of NASA's automated PPDB was initiated. Recent discussions with several Centers has revealed different interpretations and implementations of FAR Subpart 42.15 and NASA FAR Supplement (NFS) Subpart 1842.15 policy regarding the PPDB.
GUIDANCE: Guidance is provided in the following Questions and Answers:
1. Q. Must performance on all contracts be evaluated?
A. No. Agencies shall not evaluate
performance for contracts awarded under FAR Subpart 8.6, Acquisition from
Federal Prison Industries, Inc. and Subpart 8.7, Acquisition from Nonprofit
Agencies Employing People Who Are Blind or Severely Disabled. Otherwise,
agencies shall prepare an evaluation of contractor performance for each
contract in excess of $100,000.
2. Q. How does NASA document evaluations required by FAR
42.15?
A. NASA uses NASA Form (NF) 1680,
entitled, "Evaluation of Performance."
3. Q. Do evaluations used in determining award fee earned
require completion of NF 1680?
A. Not completion, per se, but award
fee evaluations must be summarized on NF 1680 and entered into the NASA PPDB.
Summarize means completing all blocks on page one of the NF 1680, except the
block entitled, "Discussion of Evaluation with Contractor," and
omitting all blocks on page two.
4. Q. Are there any situations in which evaluation is
documented using other than NF 1680?
A. Yes. Agencies evaluate
construction contractor performance using SF 1420, and architect/engineer
contractor performance using SF 1421.
5. Q. Must evaluation be performed for orders?
A. Yes, if individual orders
exceeding $100,000 constitute separate contracts, e.g., purchase orders, orders
under Basic Ordering Agreements (BOA’s), their evaluation is required.
6. Q. When orders do not constitute separate contracts, e.g.
task orders issued under indefinite delivery contracts, must performance be
evaluated under each order?
A. No. Because orders under
indefinite delivery contracts are not contracts, such orders do not require
individual evaluation. Instead, you must evaluate the overall contract under
which the orders are issued. Nonetheless, contracting officers also have
discretion to evaluate task or delivery orders under indefinite delivery
contracts if deemed appropriate.
7. Q. When purchase orders are used to implement interagency
agreements, must evaluation be performed?
A. No. Interagency transactions are
not contracts. Only contracts are subject to FAR 42.15. Therefore, by
definition, all interagency transactions are excluded from the requirement for
evaluation.
8. Q. How frequently are evaluations to be made?
A. While the FAR requires a final
evaluation and annual interim evaluations, contracting officers also have
discretion to evaluate more frequently, e.g., quarterly, monthly, etc.
9. Q. How much time should be allowed for conducting interim
evaluations?
A. While interim evaluations should
be conducted within 60 days of the anniversary of the award of the contract,
such time might begin 60 days before and end 60 days after the anniversary.
Thus, a total of 120 days is available for completion of evaluations, including
any reviews at a level above the contracting officer.
10. Q. Are all past performance evaluations entered into the
NASA PPDB?
A. No. Evaluations documented on SF
1420 and SF 1421 are not entered into the PPDB.
11. Q. Should past performance evaluations (and summaries of
award fee evaluations) be entered into PPDB system using Informed Filler or the
web-based form?
A. Either is acceptable. However,
the procurement officer at each center must select either Informed Filler or
the web-based form for all entries from that Center.
12. Q. PIC 00-02, INITIATION OF PAST PERFORMANCE DATA BASE
(PPDB), advised that "Moreover, to enhance its utility, procurement
officers must ensure that NF 1680s completed after October 1, 1998, are entered
into the PPDB before July 10, 2000." Is that guidance still current?
A. No. There is no requirement to
enter so-called "legacy evaluations," i.e., past performance
evaluations completed before July 1, 2000.
EFFECTIVE DATE: This PIC is effective as dated and shall remain in effect until canceled or superseded.
CANCELLATION: PIC 00-02 is canceled.
HEADQUARTERS CONTACT: Paul Brundage Code HK, (202) 358-0481, e-mail: paul.brundage@hq.nasa.gov.
R. Scott Thompson, Director
Contract Management Division