
04-69
Procurement Notice
January 23, 2012
MISCELLANEOUS ADMINISTRATIVE CHANGES
BACKGROUND: This Procurement Notice (PN) revises the NASA FAR Supplement (NFS) to make the following administrative and editorial changes:
1. NFS Part 1850 Extraordinary Contractual Actions is revised to be numerically consistent with FAR 50 which was changed in FAC 2005-21, dated November 7, 2007;
2. NFS Clause 1852.215-84 is revised to remove an insert where a fill-in was required by the Contracting Officer and replace it with a NASA URL website where the Agency and Center Ombudsman information will be continually maintained and updated; and
3. NFS Clauses 1852.217-71 and 1852.217-72 are revised to change the term “Commerce Business Daily (CBD)” to “Governmentwide Point of Entry (GPE)” consistent with the FAR Subpart 2.101 Definitions.
ACQUISITIONS AFFECTED BY CHANGES:
None.
ACTION REQUIRED BY CONTRACTING OFFICERS: Modify those contracts to incorporate the new updated NFS clauses 1852.215-84, 1852.217-71, and 1852.217-72 if the period of performance will extend beyond January 23, 2012. Include the updated revised clauses in all solicitations issued and contracts awarded after publication of this rule.
PROVISION AND CLAUSE CHANGES: NFS 1852.215-84, 1852.217-71, and 1852.217-72.
PARTS AFFECTED: Parts 1850 and 1852.
REPLACEMENT PAGES: You may use the enclosed pages to replace Part 1850, 52:21, 52:22, 52:23, 52:24, 52:33, and 52:34 of the NFS.
TYPE OF RULE AND PUBLICATION
DATE: The PN was published as a direct final rule in the Federal Register (76
FR 2011-30142) on November 23, 2011, and is effective January 23, 2012.
HEADQUARTERS CONTACT: Marilyn J. Seppi, Contract Management Division; 202-358-0447, email: marilyn.seppi-1@nasa.gov.
/s/
Ronald A. Poussard
Director, Contract Management Division
Enclosures
DISTRIBUTION LIST:
PN List
PART 1850
EXTRAORDINARY
CONTRACTUAL ACTIONS AND THE SAFETY ACT
TABLE OF CONTENTS
SUBPART 1850.1 EXTRAORDINARY CONTRACTUAL
ACTIONS
1850.102 Delegation
of and limitations of exercise of authority.
1850.102-2 Contract adjustment boards.
1850.103 Contract
adjustments.
1850.103-5 Processing cases.
1850.103-570 Submission
of request to the Contract Adjustment Board.
1850.103-6 Disposition.
1850.103-670 Implementation of the Contract Adjustment
Board's decision.
1850.104 Residual
powers.
1850.104-3 Special procedures for unusually hazardous
or nuclear risks.
1850.104-370 Subcontractor indemnification requests.
1850.104-70 Lead NASA installation.
PART
1850
EXTRAORDINARY
CONTRACTUAL ACTIONS AND THE SAFETY ACT
Subpart
1850.1 – Extraordinary Contractual Actions
1850.102 Delegation of and limitations
of exercise of authority.
1850.102-2 Contract adjustment boards.
14
CFR part 1209, subpart 3, Contract Adjustment Board, establishes the Contract
Adjustment Board (CAB) as the approving authority to consider and dispose of
requests from NASA contractors for extraordinary contractual actions.
1850.103 Contract adjustments.
1850.103-5 Processing cases.
1850.103-570 Submission of request to the Contract Adjustment
Board.
(a) After investigating the facts and issues
relevant to the contractor's request, the contracting officer shall forward the
request to the Associate General Counsel for General Law, including in the
forwarding letter --
(1) The nature of the case;
(2) The recommended disposition; and,
(3) If contractual action is recommended,
the contracting officer's opinion that the action will facilitate the national
defense.
(b) The forwarding letter shall enclose the
contractor's request, all supporting material submitted by the contractor, and
any material the contracting officer has obtained while investigating the facts
and issues relevant to the request. Any classified information in the material
forwarded shall be so identified.
(c) Electronic submittal is preferred for
unclassified material.
1850.103-6
Disposition.
1850.103-670 Implementation of the Contract Adjustment Board's decision.
(a) The contracting officer shall take action
authorized in the CAB’s decision.
(b) Immediately upon execution, including any
required Headquarters approval, of a contract or contract modification or
amendment implementing the CAB decision, the contracting officer shall forward
a copy of the contractual document to the Associate General Counsel for General
Law.
1850.104 Residual powers.
1850.104-3 Special procedures for
unusually hazardous or nuclear risks.
(a)
Indemnification requests.
(1)
Contractor indemnification requests must be submitted to the cognizant
contracting officer for the contract for which the indemnification clause is
requested. Contractors shall submit a
single request and shall ensure that duplicate requests are not submitted by
associate divisions, subsidiaries, or central offices of the contractor.
(iii) The contractor shall also provide evidence,
such as a certificate of insurance or other customary proof of insurance, that
such insurance is either in force or is available and will be in force during
the indemnified period.
(b) Action on indemnification requests.
(1) If recommending approval, the
contracting officer shall forward the required information to the Assistant
Administrator for Procurement, Program Operations Division, along with the
following:
(i) For contracts of five years duration or
longer, a determination, with supporting rationale, whether the
indemnification approval and insurance coverage and premiums should be
reviewed for adequacy and continued validity at points in time within the
extended contract period.
(ii) A recommended
(A) The specific definition of the unusually
hazardous risk to which the contractor is exposed in the performance of the contract(s);
(B) A complete discussion of the contractor's
financial protection program; and
(C) The extent to, and conditions under, which
indemnification is being approved for subcontracts.
(d) If approving subcontractor
indemnification, the contracting officer shall document the file with a
memorandum for record addressing the items set forth in FAR 50.104-3(b) and include an analysis of the subcontractor's
financial protection program. In
performing this analysis, the contracting officer shall take into consideration
the availability, cost, terms and conditions of insurance in relation to the
unusually hazardous risk.
1850.104-370 Subcontractor indemnification
requests.
Subcontractors
shall submit requests for indemnification to the prime contractor and through
higher tier subcontractor(s), as applicable.
If the prime contractor agrees an indemnity clause should be flowed down
to the subcontractor, the prime contractor shall forward its written request
for subcontractor indemnification to the cognizant
contracting officer for approval in accordance with FAR 50.104-3. The prime
contractor's request shall provide information responsive to 1850.104-3, FAR
50.104-3, and FAR 50.104-3(b)(1)(i), (ii),
(iv), (v), and (vii). The agreed upon definition of the unusually
hazardous risk to be incorporated into the subcontract shall be the same as that
incorporated in the prime contract.
1850.104-70 Lead NASA installation.
(a) Contractors applying for indemnification
shall determine which NASA installation has the highest dollar amount of
contracts for which indemnification is requested. The indemnification request should be
submitted to the procurement officer for that installation, who will then
designate a cognizant contracting officer. Contractors
shall submit a single request and ensure duplicate requests are not submitted
by associate divisions, subsidiaries, or central offices of the contractor.
(b) The receiving installation will become the
lead installation and will remain so indefinitely. Lead installation designation may change to
another installation if the affected procurement officers agree to the change.
Should a change occur in the lead installation, all records related to
indemnification of that contractor shall be transferred to the gaining
installation.
1852.215-77 Preproposal/Pre-bid Conference.
As prescribed in 1815.209-70(a), insert the following provision:
PREPROPOSAL/PRE-BID CONFERENCE
(DECEMBER
1988)
(a) A preproposal/pre-bid conference will be held as indicated below:
Date:
Time:
Location:
Other Information, as applicable:
[Insert the applicable conference information.]
(b) Attendance at the preproposal/pre-bid conference is recommended; however, attendance is neither required nor a prerequisite for proposal/bid submission and will not be considered in the evaluation.
(End of provision)
1852.215-78 Make or Buy Program Requirements.
As prescribed in 1815.408-70(a), insert the following provision:
MAKE OR BUY PROGRAM REQUIREMENTS
(FEBRUARY 1998)
The offeror shall submit a Make-or-Buy Program in accordance with the requirements of Federal Acquisition Regulation (FAR) 15.407-2. The offeror shall include the following supporting documentation with its proposal:
(a) A description of each major item or work effort.
(b) Categorization of each major item or work effort as "must make," "must buy," or "can either make or buy."
(c) For each item or work effort categorized as "can either make or buy," a proposal either to "make" or "buy."
(d) Reasons for (i) categorizing items and work effort as "must make" or "must buy" and (ii) proposing to "make" or "buy" those categorized as "can either make or buy." The reasons must include the consideration given to the applicable evaluation factors described in the solicitation and be in sufficient detail to permit the Contracting Officer to evaluate the categorization and proposal.
(e) Designation of the offeror's plant or division proposed to make each item or perform each work effort and a statement as to whether the existing or proposed new facility is in or near a labor surplus area.
(f) Identification of proposed subcontractors, if known, and their location and size status.
(g) Any recommendations to defer make-or-buy decisions when categorization of some items or work efforts is impracticable at the time of submission.
(End of provision)
1852.215-79 Price Adjustment for "Make-or-Buy" Changes.
As prescribed in 1815.408-70(b), insert the following clause:
PRICE ADJUSTMENT FOR
"MAKE-OR-BUY" CHANGES
(DECEMBER
1988)
The following make-or-buy items are subject to the provisions of paragraph (d) of the clause at FAR 52.215-21, Change or Additions to Make-or-Buy Program, of this contract:
|
ITEM DESCRIPTION |
MAKE-OR-BUY DETERMINATION |
|
|
|
|
|
|
(End of clause)
1852.215-81 Proposal Page Limitations.
As prescribed in 1815.209-70(d), insert the following provision:
PROPOSAL PAGE LIMITATIONS
(FEBRUARY
1998)
(a) The following page limitations are established for each portion of the proposal submitted in response to this solicitation.
Proposal Section(List each volume or section) |
Page Limit(Specify limit) |
|
|
|
|
|
|
|
|
|
|
|
|
(b) A page is defined as one side of a sheet, 8 1/2" x 11", with at least one inch margins on all sides, using not smaller than 12 point type. Foldouts count as an equivalent number of 8 1/2" x 11" pages. The metric standard format most closely approximating the described standard 8 1/2" x 11" size may also be used.
(c) Title pages and tables of contents are excluded from the page counts specified in paragraph (a) of this provision. In addition, the Cost section of your proposal is not page limited. However, this section is to be strictly limited to cost and price information. Information that can be construed as belonging in one of the other sections of the proposal will be so construed and counted against that section's page limitation.
(d) If final revisions are requested, separate page limitations will be specified in the Government's request for that submission.
(e) Pages submitted in excess of the limitations specified in this provision will not be evaluated by the Government and will be returned to the offeror.
(End of provision)
1852.215-84 Ombudsman.
As prescribed in 1815.7003, insert the following clause:
OMBUDSMAN
(NOVEMBER 2011)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and contractors during the preaward and postaward phases of this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman is not to diminish the authority of the contracting officer, the Source Evaluation Board, or the selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of formal contract disputes. Therefore, before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution.
(b)
If resolution cannot be made by the contracting officer, interested
parties may contact the installation ombudsman, whose name, address, telephone
number, facsimile number, and e-mail address may be found at: http://prod.nais.nasa.gov/pub/pub_library/Omb.html.
Concerns, issues, disagreements, and recommendations which cannot be resolved
at the installation may be referred to the Agency ombudsman identified at the
above URL. Please do not contact the
ombudsman to request copies of the solicitation, verify offer due date, or clarify
technical requirements. Such inquiries
shall be directed to the Contracting Officer or as specified elsewhere in this
document.
(End
of clause)
ALTERNATE I
(JUNE 2000)
As prescribed in 1815.7003, insert the following paragraph (c):
(c) If this is a task or delivery order contract, the ombudsman shall review complaints from contractors and ensure they are afforded a fair opportunity to be considered, consistent with the procedures of the contract.
(End of clause)
1852.216-73 Estimated Cost and Cost Sharing.
As prescribed in 1816.307-70(a), insert the following clause:
ESTIMATED COST AND
COST SHARING
(DECEMBER 1991)
(a)
It is
estimated that the total cost of performing the work under this contract
will be
$
.
(b) For performance of the work under this
contract, the Contractor shall be reimbursed for not more than
percent of the costs of
performance determined to be allowable under the Allowable Cost and Payment
clause. The remaining percent or more of the costs of
performance so determined shall constitute the Contractor's share, for which it
will not be reimbursed by the Government.
(c) For purposes of the [insert "Limitation of Cost" or "Limitation of Funds"] clause, the total estimated cost to the Government is hereby established as $ (insert estimated Government share); this amount is the maximum Government liability.
(d) The Contractor shall maintain records of all contract costs claimed by the Contractor as constituting part of its share. Those records shall be subject to audit by the Government. Costs contributed by the Contractor shall not be charged to the Government under any other grant, contract, or agreement (including allocation to other grants, contracts, or agreements as part of an independent research and development program).
(End of clause)
1852.216-74 Estimated Cost and Fixed Fee.
As prescribed in 1816.307-70(b), insert the following clause:
ESTIMATED COST AND
FIXED FEE
(DECEMBER 1991)
The estimated cost of this contract is exclusive of the fixed fee of . The total estimated cost and fixed fee is .
(End of clause)
1852.216-75 Payment of Fixed Fee.
As prescribed in 1816.307-70(c), insert the following clause:
PAYMENT OF FIXED FEE
(DECEMBER 1988)
The fixed fee shall be paid in monthly installments based upon the percentage of completion of work as determined by the Contracting Officer.
(End of clause)
1852.216-76 Award Fee for Service Contracts.
As prescribed in 1816.406-70(a), insert the following clause:
AWARD FEE FOR SERVICE
CONTRACTS
(JUNE 2000)
(a)
The contractor can earn award fee from a minimum of zero dollars to the
maximum stated in NASA FAR Supplement clause 1852.216-85, "Estimated Cost and Award Fee" in
this contract.
(b)
Beginning 6* months after the effective date of this contract, the
Government shall evaluate the Contractor's performance every 6* months to
determine the amount of award fee earned by the contractor during the
period. The Contractor may submit a
self-evaluation of performance for each evaluation period under
consideration. These self-evaluations
will be considered by the Government in its evaluation. The Government's Fee Determination Official
(FDO) will determine the award fee amounts based on the Contractor's
performance in accordance with [identify performance evaluation plan].
The plan may be revised unilaterally by the Government prior to the
beginning of any rating period to redirect emphasis.
(c)
The Government will advise the Contractor in writing of the evaluation
results. The [insert payment office] will make payment based on [Insert
method of authorizing award fee payment, e.g., issuance
of unilateral modification by contracting officer].
(d) After 85 percent of the potential award
fee has been paid, the Contracting Officer may direct the withholding of
further payment of award fee until a reserve is set aside in an amount that the
Contracting Officer considers necessary to protect the Government's
interest. This reserve shall not exceed
15 percent of the total potential award fee.
(e) The amount of award fee which can be awarded in each evaluation period is limited to the amounts set forth at [identify location of award fee amounts]. Award fee which is not earned in an evaluation period cannot be reallocated to future evaluation periods.
(f)(1)Provisional award fee payments [insert
“will” or "will not", as applicable] be made under this contract pending the
determination of the amount of fee earned for an evaluation period. If applicable, provisional award fee payments
will be made to the Contractor on a [insert the
1852.217-70
Property Administration and Reporting.
As prescribed in 1817.7004-6 and 1817.7005-3, insert the following clause:
PROPERTY
ADMINISTRATION AND REPORTING
(DECEMBER 2005)
All property acquired for, and reimbursed by, NASA or transferred by NASA for use under this NASA-Interagency Purchase Request shall be controlled and accounted for in accordance with the servicing agency’s normal procedures. All excess items, however, costing $500 or more and in condition Code 7 or better (GSA Condition Codes) shall be reported to the NASA originating office for possible reutilization before disposition.
(End of clause)
1852.217-71 Phased Acquisition Using Down-Selection Procedures.
As prescribed in 1817.7302(a), insert the following clause:
PHASED ACQUISITION
USING DOWN-SELECTION PROCEDURES
(NOVEMBER 2011)
(a) This solicitation is for the acquisition of ______ [insert Program title]. The acquisition will be conducted as a two-phased procurement using a competitive down-selection technique between phases. In this technique, two or more contractors will be selected for Phase 1. It is expected that the single contractor for Phase 2 will be chosen from among these contractors after a competitive down-selection.
(b) Phase 1 is for the _____ [insert purpose of phase]. Phase 2 is for _____ [insert general Phase 2 goals].
(c) The competition for Phase 2 will be based on the results of Phase 1, and the award criteria for Phase 2 will include successful completion of Phase 1 requirements.
(d) NASA will issue a separate, formal solicitation for Phase 2 that will include all information required for preparation of proposals, including the final evaluation factors.
(e) Phase 2 will be synopsized in the Governmentwide Point of Entry (GPE) in accordance with FAR 5.201 and 5.203 unless one of the exceptions in FAR 5.202 applies. Notwithstanding NASA's expectation that only the Phase 1 contractors will be capable of successfully competing for Phase 2, all proposals will be considered. Any other responsible source may indicate its desire to submit a proposal by responding to the Phase 2 synopsis, and NASA will provide that source a solicitation.
(f) To be considered for Phase 2 award, offerors must demonstrate a design maturity equivalent to that of the Phase 1 contractors. This demonstration shall include the following Phase 1 deliverables upon which Phase 2 award will be based: _____ [insert the specific Phase 1 deliverables]. Failure to fully and completely demonstrate the appropriate level of design maturity may render the proposal unacceptable with no further consideration for contract award.
(g) The following draft Phase 2 evaluation factors are provided for your information. Please note that these evaluation factors are not final, and NASA reserves the right to change them at any time up to and including the date upon which Phase 2 proposals are solicited.
[Insert draft Phase 2 evaluation factors (and subfactors, if available), including demonstration of successful completion of Phase 1 requirements.]
(h) Although NASA will request Phase 2 proposals from Phase 1 contractors, submission of the Phase 2 proposal is not a requirement of the Phase 1 contract. Accordingly, the costs of preparing these proposals shall not be a direct charge to the Phase 1 contract or any other Government contract.
(i) The anticipated schedule for conducting this phased procurement is provided for your information. These dates are projections only and are not intended to commit NASA to complete a particular action at a given time. [Insert dates below].
Phase 1 award -
Phase 2 synopsis -
Phase 2 proposal requested -
Phase 2 proposal receipt -
Phase 2 award -
(End of clause)
1852.217-72 Phased
Acquisition Using Progressive Competition Down-Selection Procedures.
As prescribed in 1817.7302(b), insert the following clause:
PHASED ACQUISITION
USING PROGRESSIVE COMPETITION
DOWN-SELECTION
PROCEDURES
(NOVEMBER 2011)
(a) This solicitation is for the acquisition of ________ [insert Program title]. The acquisition will be conducted as a two-phased procurement using a progressive competition down-selection technique between phases. In this technique, two or more contractors will be selected for Phase 1. It is expected that the single contractor for Phase 2 will be chosen from among these contractors after a competitive down-selection.
(b) Phase 1 is for the ________ [insert purpose of phase]. Phase 2 is for ________ [insert general Phase 2 goals].
(c) The competition for Phase 2 will be based on the results of Phase 1, and the award criteria for Phase 2 will include successful completion of Phase 1 requirements.
(d) NASA does not intend to issue a separate, formal solicitation for Phase 2. Instead, Phase 2 proposals will be requested from the Phase 1 contractors by means of ________ [indicate method of requesting proposals, e.g., by a letter]. All information required for preparation of Phase 2 proposals, including the final evaluation criteria and factors, will be provided at that time.
(e) Phase 2 will be synopsized in the Governmentwide Point of Entry (GPE) in accordance with FAR 5.201 and 5.203 unless one of the exceptions in FAR 5.202 applies. Notwithstanding NASA's expectation that only the Phase 1 contractors will be capable of successfully competing for Phase 2, all proposals will be considered. Any other responsible source may indicate its desire to submit a proposal by responding to the Phase 2 synopsis, and NASA will provide that source all the material furnished to the Phase 1 contractors necessary to submit a proposal.
(f) To be considered for Phase 2 award, offerors must demonstrate a design maturity equivalent to that of the Phase 1 contractors. This demonstration shall include the following Phase 1 deliverables upon which Phase 2 award will be based: ________ [insert the specific Phase 1 deliverables]. Failure to fully and completely demonstrate the appropriate level of design maturity may render the proposal unacceptable with no further consideration for contract award.
(g) The following
draft Phase 2 evaluation factors are provided for your information. Please note that these evaluation factors are
not final, and NASA reserves the right to change them at