PERFORMANCE-BASED CONTRACTING

PURPOSE: To clarify that Performance-Based Contracting (PBC) is the preferred contracting technique for the acquisition of all supplies and services at NASA; provide guidance on the appropriate contract type for PBC requirements; provide common sense guidance as to when positive and negative incentives should not be used; and clarify the use of award fee incentives in conjunction with other contract types. Other miscellaneous revisions are made to conform with recent FAR numbering changes.

BACKGROUND: Federal Acquisition Circular 97-1 revised FAR 7.105 and added FAR 37.6 to address Performance-Based Service Contracting. These changes obviate the need for similar coverage in the NFS, although coverage is added to clarify that NASA policy on use of PBC is not limited to service contracts. In addition, the following changes are made:

1. New guidance is added regarding the use of incentives in performance-based contracts. Included in this guidance is the addition of new sections discussing the use of a CPAF contract type for PBC requirements and the use of performance incentives. Previous restrictions on the use of CPAF for PBC requirements are deleted.

2. The requirement in 1806.302-470(b) for competition advocate approval of a memorandum justifying not preparing a justification for other than full and open competition pursuant to FAR 6.302-4, International Agreement, is deleted to reflect a statutory change made by section 841(b) of the Defense Authorization Act for Fiscal Year 1998.

3. Miscellaneous editorial changes are made to align the NFS with FAR section titles and numbers.

REGULATION: Parts1806, 1807, 1816, 1819, and 1837 are amended as set forth in the enclosed replacement pages to the NFS.

REPLACEMENT PAGES: You may use the enclosed pages to replace 6:3, 6:4, 7:1, 7:2, Part 1816, TOC 19:1, TOC 19:2, 19:3, 19:4, Part 1837, 52-91, 52-92, 52-95, and 52-96 to the NFS.

REGULATORY COMPLIANCE: This PN was published as a final rule in the Federal Register (63, FR 12997-12998, dated March 17, 1998).

EFFECTIVE DATE: This PN is effective as dated and shall remain in effect until canceled or superseded.

HEADQUARTERS CONTACT: Tom O'Toole, Code HK, (202) 358-0478, e-mail: thomas.otoole@hq.nasa.gov.

R. Scott Thompson

Director, Contract Management Division

Enclosures


Date___________

NOTES:

1. Name of source to be excluded.

2. Description of estimated reduction in overall costs.

3. Description of how estimate was derived.

4. In paragraph 4 and in the Determination, the basic wording is appropriate when FAR 6.202(a)(1) applies; Alternate I is appropriate when FAR 6.202(a)(2) applies; and Alternate II is appropriate when FAR 6.202(a)(3) applies.

5. Description of circumstances necessitating the exclusion of the identified source.

Subpart 1806.3--Other Than Full and Open Competition

1806.302 Circumstances permitting other than full and open competition.

1806.302-4 International agreement.

1806.302-470 Documentation.

Pursuant to 10 U.S.C. 2304(f)(2)(E), an individual justification for other than full and open competition under the authority of FAR 6.302-4 is not required when the procurement officer signs a Memorandum for the Record that:

(a) describes the specific terms of the international agreement or treaty that limit acquisitions in support of, or as a result of, the agreement or treaty to less than full and open competition;

(b) is included in each official contract file in the place for filing a Justification for Other than Full and Open Competition (see NASA Form 1098).

1806.302-7 Public interest.

(c)(2) The notice to Congress shall be made by NASA Headquarters, Office of Legislative Affairs (Code LC). Code HS shall request the notice to be made immediately upon approval of a D&F and shall advise the contracting activity of the date upon which the notification period ends.

(3) The contracting officer shall prepare the D&F required by FAR 6.302-7(c)(1) in any format that clearly documents the determination and the supporting findings.

1806.303 Justifications.

1806.303-1 Requirements.

(b) Justifications for using less than full and open competition may be prepared by the technical office initiating the contract action when it is recommending the use of the justification authority, or by the contracting officer if the technical office does not make such a recommendation.

(d) The contracting officer shall send a copy of each approved justification or D&F that cites the authority of FAR 6.302-3(a)(2)(i) or FAR 6.302-7 to NASA Headquarters, International Relations Division (Code IR), unless one of the exceptions at FAR 25.403 applies to the acquisition. The transmittal shall indicate that the justification is being furnished under FAR 6.303-1(d).

1806.303-170 Sole-source purchases by contractors.

The requirements of FAR Part 6 and NFS Part 1806 apply if NASA directs a prime contractor (by specifications, drawings, parts lists, or otherwise) to purchase items on a sole-source basis. Accordingly, procurement officers shall take necessary actions to ensure that such sole-source acquisitions are properly justified. Where "brand name or equal" purchase descriptions list the salient physical, functional, or other characteristics of the item being procured and are properly used under 1811.104, the justification requirements of FAR Part 6 and NFS Part 1806 do not apply.

1806.303-2 Content.

1806.303-270 Use of unusual and compelling urgency authority.

If the authority at FAR 6.302-2 is used for extending the performance period of an existing services contract, the justification shall contain the information required by FAR 6.303-2 and;

(a) Documentation that the acquisition process for the successor contract was started early enough to allow for adequately planning and conducting a full and open competition, together with a description of the circumstances that prevented award in a timely manner; and

(b) Documentation of the reasons why no other source could practicably compete for the interim requirement.

1806.304-70 Approval of NASA justifications.

Concurrences and approvals for justifications of contract actions conducted in accordance with FAR Subparts 6.2 and 6.3 shall be obtained as follows:

(a) For proposed contracts over $500,000 but not exceeding $10,000,000 -

(1) Concurring official: Procurement Officer

(2) Approving official: Center or Headquarters Competition Advocate.

(b) For proposed contracts over $10,000,000 but not exceeding $50,000,000 -

(1) Concurring officials:

(i) Procurement Officer

(ii) Center or Headquarters Competition Advocate

(2) Approving official: Center Director or Associate Administrator for Headquarters Operations.

(c) For proposed contracts over $50,000,000 -

(1) Concurring officials:

(i) Procurement Officer

(ii) Center or Headquarters Competition Advocate

(iii) Center Director or Associate Administrator for Headquarters Operations

(iv) Agency Competition Advocate

(2) Approving Official: Associate Administrator for Procurement

(d) The approval authority of FAR 6.304(a)(3) may not be delegated to other than the installation's Deputy Director.


PART 1807

ACQUISITION PLANNING

Subpart 1807.1 - Acquisition Plans

1807.103 Agency-head responsibilities.

(d)(i) Except as provided in paragraph (d)(iii) of this section, acquisition plans shall be prepared according to the following:

(A) For acquisitions requiring Headquarters approval, by an Acquisition Strategy Meeting (ASM) (see 1807.170);

(B) For acquisitions not requiring Headquarters approval and expected to exceed $5 million, by installation-approved ASMs or written acquisition plans; and,

(C) For acquisitions not expected to exceed $5 million, in accordance with installation procedures.

(ii) The estimated dollar amounts shall include all options and later phases of the same program or project.

(iii) Acquisition plans are not required for the following acquisitions:

(A) Architect-engineering services;

(B) Broad agency announcements (see 1835.016) or unsolicited proposals;

(C) Basic research from nonprofit organizations;

(D) Utility services available from only one source;

(E) From or through other Government agencies;

(F) Industrial facilities required in support of related contracts; or

(G) MidRange procedure awards (see 1871). However, acquisition plans are required for commercial item acquisitions that exceed the MidRange dollar thresholds for noncommercial items.

(iv) Acquisition plans shall be approved before soliciting proposals.

(v) Approval of an acquisition plan does not constitute approval of any special conditions, or special clauses that may be required unless the plan so specifies, and the individual having approval authority is a signatory of the plan. All required deviations shall be approved through the procedures described in FAR 1.4 and 1801.4.

(vi) A single acquisition plan may be used for all phases of a phased acquisition provided the plan fully addresses each phase, and no significant changes occur after plan approval to invalidate the description of the phases. If such significant changes do occur, the plan shall be amended and approved at the same level as the original plan.

(e) Acquisition plans should be prepared on a program or system basis when practical. In such cases, the plan should fully address all component acquisitions of the program or system.

1807.105 Contents of written acquisition plans.

Acquisition plans shall address each applicable topic listed in FAR 7.105, as supplemented by this section. Plans shall be structured by subject heading using each italicized topic heading in the same sequence as presented in the FAR. Subheadings should be used when appropriate (e.g., the separate items under contracting considerations at 7.105(b)(4)). Topics not applicable to a given acquisition (e.g., design-to-cost and should-cost are not compatible with service acquisitions), should be marked N/A. The requirements in FAR 7.105 regarding performance-based contracting methods shall not be limited to acquisition plans for service contracts.

(a)(1) Describe in nontechnical terms the supplies or services to be acquired. Include quantities.

(a)(3) Identify the estimated cost and describe the estimating methodology.

(a)(5) Specify the delivery or performance period requirements separately by the basic contract, each option, and the total.

(a)(8) Streamlining applies to all NASA acquisitions. Describe all planned streamlining procedures.

(b)(1) If the acquisition represents a consolidation of efforts previously contracted for separately, address the reasons for the consolidation, the expected benefits, and any potential adverse impact (including the effect on small, small disadvantaged, and women-owned small business participation) and planned actions to mitigate the impact (see 1819.202-170).

(b)(3) Address how cost realism will be evaluated.

(b)(4)(A) If an incentive contract is planned, describe the planned incentive(s) and the anticipated effects.

(B) Describe subcontracting issues, including all applicable subcontracting goals. (See FAR part 19 and part 1819).

(b)(5)(A) Identify the estimated cost separately by the basic contract, each option and total amount.

(B) Identify the funding by fiscal year and unique project number (UPN).

(C) Discuss planned approaches to eliminate funding shortfalls (vs. the estimated cost).

(b)(6) Identify the type of work statement/specification planned. Specifically address the applicability of performance-based requirement descriptions and the availability of commercial sources for the supplies/services.

(b)(10) Address contract management issues, including planned delegations of administrative functions.

(b)(20) If the period between release of solicitation to contract award is more than 120 calendar days (180 days for formal SEB competitions), explain why that goal cannot be met.

1807.170 Acquisition Strategy Meeting (ASM).

(a) The ASM is an acquisition plan conducted through a meeting attended by all interested NASA offices. At the meeting, the acquisition plan topics and structure specified in 1807.105 are presented in briefing format, and formal written minutes prepared to summarize the decisions, actions, and conclusions of the ASM members. The approved minutes, along with the briefing charts, shall be included in the contract file to document completion of the acquisition plan required by 1807.103.

(b) The ASM is not a requirements definition meeting. It is a meeting to seek approval for the proposed acquisition approach for requirements that were previously defined and agreed to by the cognizant offices.

(c) Headquarters ASMs will be chaired by the Associate Administrator for Procurement or designee. The Headquarters Office of Procurement (Code HS) will prepare the minutes of Headquarters ASMs and distribute them to all attendees for review prior to approval by the ASM chairperson.

(d) For field installation ASMs, the minutes shall be approved in accordance with installation procedures.


PART 1816

TYPES OF CONTRACTS

TABLE OF CONTENTS

SUBPART 1816.1 SELECTING CONTRACT TYPES

1816.104 Factors in selecting contract types.

1816.104-70 Contract type of performance-based contracting (PBC).

SUBPART 1816.2 FIXED-PRICE CONTRACTS

1816.202 Firm-fixed-price contracts.

1816.202-70 NASA contract clause.

1816.203 Fixed-price contracts with economic price adjustment.

1816.203-4 Contract clauses.

SUBPART 1816.3 COST-REIMBURSEMENT CONTRACTS

1816.303-70 Cost-sharing contracts.

1816.306 Cost-plus-fixed-fee contracts.

1816.307 Contract clauses.

1816.307-70 NASA contract clauses.

SUBPART 1816.4 INCENTIVE CONTRACTS

1816.402 Application of pre-determined, formula-type incentives.

1816.402-2 Performance incentives.

1816.402-270 NASA technical performance incentives.

1816.404 Fixed-price contracts with award fees.

1816.405 Cost-reimbursement incentive contracts.

1816.405-2 Cost-plus-award-fee (CPAF) contracts.

1816.405-270 CPAF contracts.

1816.405-271 Base fee.

1816.405-272 Award fee evaluation periods.

1816.405-273 Award fee evaluations.

1816.405-274 Award fee evaluation factors.

1816.405-275 Award fee evaluation scoring.

1816.406 Contract clauses.

1816.406-70 NASA contract clauses.

SUBPART 1816.5 INDEFINITE-DELIVERY CONTRACTS

1816.504 Indefinite quantity contracts.

1816.505 Ordering.

1816.505-70 Task Ordering.

1816.506-70 NASA contract clause.

SUBPART 1816.6 TIME-AND-MATERIALS, LABOR-HOUR, AND LETTER CONTRACTS

1816.603 Letter contracts.

1816.603-370 Approvals.

PART 1816

TYPES OF CONTRACTS

Subpart 1816.1 -- Selecting Contract Types

1816.104 Factors in selecting contract types.

1816.104-70 Contract type for performance-based contracting (PBC).

(a) PBC is defined in FAR 37.101 and discussed in FAR 37.6. Although FAR Part 37 primarily addresses services contracts, PBC is not limited to these contracts. PBC is the preferred way of contracting for all supplies and services at NASA. Generally, when contract performance risk under a PBC specification can be fairly shifted to the contractor to allow for the operation of objective incentives, a contract type with objectively measurable incentives (e.g., FFP, FPIF, or CPIF) is appropriate. However, when contractor performance (e.g., cost control, schedule, or quality/technical) is best evaluated subjectively using quantitative measures, a CPAF contract may be used.

(b) A level-of-effort contract is not PBC.

Subpart 1816.2--Fixed-Price Contracts

1816.202 Firm-fixed-price contracts.

1816.202-70 NASA contract clause.

The contracting officer shall insert the clause at 1852.216-78, Firm-Fixed-Price, in firm-fixed-price solicitations and contracts. Insert the appropriate amount in the resulting contract.

1816.203 Fixed-price contracts with economic price adjustment.

1816.203-4 Contract clauses.

(a) In addition to the approval requirements in the prescriptions at FAR 52.216-2 through 52.216-4, the contracting officer shall coordinate with the installation's Deputy Chief Financial Officer (Finance) before exceeding the ten-percent limit in paragraph (c)(1) of the clauses at FAR 52.216-2 through 52.216-4.

(d)(2) Contracting officers shall contact the Office of Procurement, Code HC, for specific guidance on preparing clauses using cost indexes. Such clauses require advance approval by the Associate Administrator for Procurement. Requests for approval shall be submitted to the Headquarters Office of Procurement (Code HS).

Subpart 1816.3--Cost-Reimbursement Contracts

1816.303-70 Cost-sharing contracts.

(a) Cost-sharing with for-profit organizations.

(1) Cost sharing by for-profit organizations is mandatory in any contract for basic or applied research resulting from an unsolicited proposal, and may be accepted in any other contract when offered by the proposing organization. The requirement for cost-sharing may be waived when the contracting officer determines in writing that the contractor has no commercial, production, education, or service activities that would benefit from the results of the research, and the contractor has no means of recovering its shared costs on such projects.

(2) The contractor's cost-sharing may be any percentage of the project cost. In determining the amount of cost-sharing, the contracting officer shall consider the relative benefits to the contractor and the Government. Factors that should be considered include--

(i) the potential for the contractor to recover its contribution from non-Federal sources;

(ii) the extent to which the particular area of research requires special stimulus in the national interest; and

(iii) the extent to which the research effort or result is likely to enhance the contractor's capability, expertise, or competitive advantage.

(b) Cost-sharing with not-for-profit organizations.

(1) Costs to perform research stemming from an unsolicited proposal by universities and other educational or not-for-profit institutions are usually fully reimbursed. When the contracting officer determines that there is a potential for significant benefit to the institution cost-sharing will be considered.

(2) The contracting officer will normally limit the institution's share to no more than 10 percent of the project's cost.

(c) Implementation.

Cost-sharing shall be stated as a minimum percentage of the total allowable costs of the project. The contractor's contributed costs may not be charged to the Government under any other contract or grant, including allocation to other contracts and grants as part of an independent research and development program.

1816.306 Cost-plus-fixed-fee contracts.

(d) Completion and term forms.

(4) Term form contracts are incompatible with performance base contracting (PBC) and should not be used with PBC requirements.

1816.307 Contract clauses.

(a) In paragraph (h)(2)(ii)(B) of the Allowable Cost and Payment clause at FAR 52.216-7, the period of years may be increased to correspond with any statutory period of limitation applicable to claims of third parties against the contractor; provided, that a corresponding increase is made in the period for retention of records required in paragraph (f) of the clause at FAR 52.215-2, Audit and Records - Negotiation.

(b) In solicitations and contracts containing the clause at FAR 52.216-8, Fixed Fee, the Schedule shall include appropriate terms, if any, for provisional billing against fee.

(d) In solicitations and contracts containing the clause at FAR 52.216-10, Incentive Fee, the Schedule shall include appropriate terms, if any, for provisional billing against fee.

(g) In paragraph (g)(2)(ii) of the Allowable Cost and Payment--Facilities clause at FAR 52.216-13, the period of years may be increased to correspond with any statutory period of limitation applicable to claims of third parties against the contractor; provided, that a corresponding increase is made in the period for retention of records required in paragraph (f) of the clause at FAR 52.215-2, Audit and Records - Negotiation.

1816.307-70 NASA contract clauses.

(a) The contracting officer shall insert the clause at 1852.216-73, Estimated Cost and Cost Sharing, in each contract in which costs are shared by the contractor pursuant to 1816.303-70.

(b)The contracting officer shall insert the clause substantially as stated at 1852.216-74, Estimated Cost and Fixed Fee, in cost-plus-fixed-fee contracts.

(c) The contracting officer may insert the clause at 1852.216-75, Payment of Fixed Fee, in cost-plus-fixed-fee contracts. Modifications to the clause are authorized.

(d) The contracting officer shall insert the clause at 1852.216-81, Estimated Cost, in cost-no-fee contracts that are not cost sharing or facilities contracts.

(e) The contracting officer may insert a clause substantially as stated at 1852.216-87, Submission of Vouchers for Payment, in cost-reimbursement solicitations and contracts.

(f) When either FAR clause 52.216-7, Allowable Cost and Payment, or FAR clause 52.216-13, Allowable Cost and Payment---Facilities, is included in the contract, as prescribed at FAR 16.307(a) and (g), the contracting officer should include the clause at 1852.216-89, Assignment and Release Forms.

Subpart 1816.4--Incentive Contracts

1816.402 Application of predetermined, formula-type incentives.

When considering the use of a quality, performance, or schedule incentive, the following guidance applies.

(1) A positive incentive is generally not appropriate unless-

(i) Performance above the target (or minimum, if there are no negative incentives) level is of significant value to the Government;

(ii) The value of the higher level of performance is worth the additional cost/fee;

(iii) The attainment of the higher level of performance is clearly within the

control of the contractor; and

(iv) An upper limit is identified, beyond which no further incentive is earned.

(2) A negative incentive is generally not appropriate unless-

(i) A target level of performance can be established, which the contractor can reasonably be expected to reach with a diligent effort, but a lower level of performance is also minimally acceptable;

(ii) The value of the negative incentive is commensurate with the lower level of performance and any additional administrative costs; and

(iii) Factors likely to prevent attainment of the target level of performance are clearly within the control of the contractor.

(3) When a negative incentive is used, the contract must indicate a level below which performance is not acceptable.

1816.402-2 Performance incentives.

1816.402-270 NASA technical performance incentives.

(a) A performance incentive shall be included in all contracts based on performance-oriented documents (see FAR 11.101(a)) where the primary deliverable(s) is (are) hardware and where total value (including options) is greater than $25 million unless it is determined that the nature of the acquisition (for example, commercial off-the-shelf computers) would not effectively lend itself to a performance incentive. Any exception to this requirement shall be approved in writing by the Center Director. Performance incentives may be included in hardware contracts valued under $25 million at the discretion of the procurement officer. Performance incentives, which are objective and measure hardware performance after delivery and acceptance, are separate from other incentives, such as cost or delivery incentives.

(b) When a performance incentive is used, it shall be structured to be both positive and negative based on hardware performance after delivery and acceptance. In doing so, the contract shall establish a standard level of performance based on the salient hardware performance requirement. This standard performance level is normally the contract's minimum performance requirement. No incentive amount is earned at this standard performance level. Discrete units of measurement based on the same performance parameter shall be identified for performance both above and below the standard. Specific incentive amounts shall be associated with each performance level from maximum beneficial performance (maximum positive incentive) to minimal beneficial performance or total failure (maximum negative incentive) . The relationship between any given incentive, both positive and negative, and its associated unit of measurement should reflect the value to the Government of that level of hardware performance. The contractor should not be rewarded for above-standard performance levels that are of no benefit to the Government.

(c) The final calculation of the performance incentive shall be done when hardware performance, as defined in the contract, ceases or when the maximum positive incentive is reached. When hardware performance ceases below the standard established in the contract, the Government shall calculate the amount due and the contractor shall pay the Government that amount. Once hardware performance exceeds the standard, the contractor may request payment of the incentive amount associated with a given level of performance, provided that such payments shall not be more frequent than monthly. When hardware performance ceases above the standard level of performance, or when the maximum positive incentive is reached, the Government shall calculate the final performance incentive earned and unpaid and promptly remit it to the contractor. The exclusion at FAR 16.405(e)(3) does not apply to decisions made as to the amount(s) of positive or negative incentive.

(d) When the deliverable hardware lends itself to multiple, meaningful measures of performance, multiple performance incentives may be established. When the contract requires the sequential delivery of several hardware items (e.g., multiple spacecraft), separate performance incentive structures may be established to parallel the sequential delivery and use of the deliverables.

(e) In determining the value of the maximum performance incentives available, the contracting officer shall follow the following rules.

(1) For a CPFF contract, the sum of the maximum positive performance incentive and fixed fee shall not exceed the limitations in FAR 15.404-4(c)(4)(i).

(2) For an award fee contract.

(i) The individual values of the maximum positive performance incentive and the total potential award fee (including any base fee) shall each be at least one-third of the total potential contract fee. The remaining one-third of the total potential contract fee may be divided between award fee and the maximum performance incentive at the discretion of the contracting officer.

(ii) The maximum negative performance incentive for research and development hardware (e.g., the first and second units) shall be equal in amount to the total earned award fee (including any base fee). The maximum negative performance incentives for production hardware (e.g., the third and all subsequent units of any hardware items) shall be equal in amount to the total potential award fee (including any base fee). Where one contract contains both cases described above, any base fee shall be allocated reasonably among the items.

(3) For cost reimbursement contracts other than award fee contracts, the maximum negative performance incentives shall not exceed the total earned fee under the contract.

1816.404 Fixed-price contracts with award fees.

Section 1816.405-2 applies to the use of FPAF contracts as if they were CPAF contracts. However, neither base fee (see 1816.405-271) nor evaluation of cost control (see 1816.405-274) apply to FPAF contracts.

1816.405 Cost-reimbursement incentive contracts.

1816.405-2 Cost-plus-award-fee (CPAF) contracts.

1816.405-270 CPAF contracts.

(a) Use of an award fee incentive shall be approved in writing by the procurement officer. The procurement officer's approval shall include a discussion of the other types of contracts considered and shall indicate why an award fee incentive is the appropriate choice. Award fee incentives should not be used on contracts with a total estimated cost and fee less than $2 million per year. The procurement officer may authorize use of award fee for lower-valued acquisitions, but should do so only in exceptional situations, such as contract requirements having direct health or safety impacts, where the judgmental assessment of the quality of contractor performance is critical.

(b) Except as provided in paragraph (c) of this section, an award fee incentive may be used in conjunction with other contract types for aspects of performance that cannot be objectively assessed. In such cases, the cost incentive is based on objective formulas inherent in the other contract types (e.g., FPI, CPIF), and the award fee provision should not separately incentivize cost performance.

(c) Award fee incentives shall not be used with a cost-plus-fixed-fee (CPFF) contract.

1816.405-271 Base fee.

(a) A base fee shall not be used on CPAF contracts for which the periodic award fee evaluations are final (1816.405-273(a)). In these circumstances, contractor performance during any award fee period is independent of and has no effect on subsequent performance periods or the final product/results at contract completion. For other contracts, such as those for hardware or software development, the procurement officer may authorize the use of a base fee not to exceed 3 percent. Base fee shall not be used when an award fee incentive is used in conjunction with a performance based contract structure, such as an incentive fee arrangement.

(b) When a base fee is authorized for use in a CPAF contract, it shall be paid only if the final award fee evaluation is "satisfactory" or better. (See 1816.405-273 and 1816.405-275) Pending final evaluation, base fee may be paid during the life of the contract at defined intervals on a provisional basis. If the final award fee evaluation is "poor/unsatisfactory", all provisional base fee payments shall be refunded to the Government.

1816.405-272 Award fee evaluation periods.

(a) Award fee evaluation periods should be at least 6 months in length. When appropriate, the procurement officer may authorize shorter evaluation periods after ensuring that the additional administrative costs associated with the shorter periods are offset by benefits accruing to the Government. Where practicable, such as developmental contracts with defined performance milestones (e.g., Preliminary Design Review, Critical Design Review, initial system test), establishing evaluation periods at conclusion of the milestones rather than calendar dates, or in combination with calendar dates should be considered. In no case shall an evaluation period be longer than 12 months.

(b) A portion of the total available award fee contract shall be allocated to each of the evaluation periods. This allocation may result in an equal or unequal distribution of fee among the periods. The contracting officer should consider the nature of each contract and the incentive effects of fee distribution in determining the appropriate allocation structure.

1816.405-273 Award fee evaluations.

(a) Award fee evaluations are either interim or final. On contracts where the contract deliverable is the performance of a service over any given time period, contractor performance is often definitively measurable within each evaluation period. In these cases, all evaluations are final, and the contractor keeps the fee earned in any period regardless of the evaluations of subsequent periods. Unearned award fee in any given period in a service contract is lost and shall not be carried forward, or "rolled-over," into subsequent periods.

(b) On other contracts, such as those for end item deliverables where the true quality of contractor performance cannot be measured until the end of the contract, only the last evaluation is final. At that point, the total contract award fee pool is available, and the contractor's total performance is evaluated against the award fee plan to determine total earned award fee. In addition, interim evaluations are done to monitor performance prior to contract completion and provide feedback to the contractor on the Government's assessment of the quality of its performance. Interim evaluations are also used to establish the basis for making interim award fee payments. These interim payments are superseded by the fee determination made in the final evaluation at contract completion. The Government will then pay the contractor, or the contractor will refund to the Government, the difference between the final award fee determination and the cumulative interim fee payment.

(c) Provisional award fee payments, i.e., payments made within evaluation periods, may be included in the contract and should be negotiated on a case-by-case basis. The amount of the provisional award fee payment is determined by applying the lesser of the prior period's interim evaluation score (see 1816.405-275) or 80 percent of the fee allocated to the current period. The provisional award fee payments are superseded by the fee determinations made at the conclusion of each award fee performance period.

(d) The Fee Determination Official's rating for both interim and final evaluations will be provided to the contractor within 45 calendar days of the end of the period being evaluated. Any fee, interim or final, due the contractor will be paid no later than 60 calendar days after the end of the period being evaluated.

(e) Interim and final evaluations may be used to provide past performance information during the source selection process and should be marked and controlled as "Source Selection Information".

1816.405-274 Award fee evaluation factors.

(a) Explicit evaluation factors shall be established for each award fee period.

(b) Evaluation factors will be developed by the contracting officer based upon the characteristics of an individual procurement. Normally, technical and schedule considerations will be included in all CPAF contracts as evaluation factors. Cost control shall be included as an evaluation factor in all CPAF contracts. When explicit evaluation factor weightings are used, cost control shall be no less than 25 percent of the total weighted evaluation factors. The predominant consideration of the cost control evaluation should be a measurement of the contractor's performance against the negotiated estimated cost of the contract. This estimated cost may include the value of undefinitized change orders when appropriate.

(c) In rare circumstances, contract costs may increase for reasons outside the contractor's control and for which the contractor is not entitled to an equitable adjustment. One example is a weather-related launch delay on a launch support contract. The Government shall take such situations into consideration when evaluating contractor cost control.

(d) Emphasis on cost control should be balanced against other performance requirement objectives. The contractor should not be incentivized to pursue cost control to the point that overall performance is significantly degraded. For example, incentivizing an underrun that results in direct negative impacts on technical performance, safety, or other critical contract objectives is both undesirable and counterproductive. Therefore, evaluation of cost control shall conform to the following guidelines:

(1) Normally, the contractor should be given a score of 0 for cost control when there is a significant overrun within its control. However, the contractor may receive higher scores for cost control if the overrun is insignificant. Scores should decrease sharply as the size of the overrun increases. In any evaluation of contractor overrun performance, the Government shall consider the reasons for the overrun and assess the extent and effectiveness of the contractor's efforts to control or mitigate the overrun.

(2) The contractor should normally be rewarded for an underrun within its control, up to the maximum score allocated for cost control, provided the average numerical rating for all other award fee evaluation factors is 81 or greater (see 1816.405-275). An underrun shall be rewarded as if the contractor has met the estimated cost of the contract (see 1816.405-274(d)(3)) when the average numerical rating for all other factors is less than 81 but greater than 60.

(3) The contractor should be rewarded for meeting the estimated cost of the contract, but not to the maximum score allocated for cost control, to the degree that the contractor has prudently managed costs while meeting contract requirements. No award shall be given in this circumstance unless the average numerical rating for all other award fee evaluation factors is 61 or greater.

(e) When an AF arrangement is used in conjunction with another contract type, the award fee's cost control factor will only apply to a subjective assessment of the contractor's efforts to control costs and not the actual cost outcome incentivized under the basic contract type (e.g. CPIF, FPIF).

(f) The contractor's performance against the subcontracting plan incorporated in the contract shall also be evaluated. Small disadvantaged business utilization may be an area of particular emphasis, including the contractor's achievements in subcontracting high technology efforts as well as the contractor's performance under the Mentor-Protégé Program, if applicable. The evaluation weight given to subcontracting plan performance should be significant (up to 15 percent of available award fee). It should motivate the contractor to focus management attention to subcontracting with small, small disadvantaged, and women-owned small business concerns to the maximum extent practicable consistent with efficient contract performance.

(g) Only the award fee performance evaluation factors set forth in the performance evaluation plan shall be used to determine award fee scores.

(h) The Government may unilaterally modify the applicable award fee performance evaluation factors and performance evaluation areas prior to the start of an evaluation period. The contracting officer shall notify the contractor in writing of any such changes 30 days prior to the start of the relevant evaluation period.

1816.405-275 Award fee evaluation scoring.

(a) A scoring system of 0-100 shall be used for all award fee ratings. Award fee earned is determined by applying the numerical score to the award fee pool. For example, a score of 85 yields an award fee of 85 percent of the award fee pool. No award fee shall be paid unless the total score is 61 or greater.

(b) The following standard adjectival ratings and the associated numerical scores shall be used on all award fee contracts.

(1) Excellent (100-91): Of exceptional merit; exemplary performance in a timely, efficient, and economical manner; very minor (if any) deficiencies with no adverse effect on overall performance.

(2) Very good (90-81): Very effective performance, fully responsive to contract requirements accomplished in a timely, efficient, and economical manner for the most part; only minor deficiencies.

(3) Good (80-71): Effective performance; fully responsive to contract requirements; reportable deficiencies, but with little identifiable effect on overall performance.

(4) Satisfactory (70-61): Meets or slightly exceeds minimum acceptable standards; adequate results; reportable deficiencies with identifiable, but not substantial, effects on overall performance.

(5) Poor/Unsatisfactory (less than 61): Does not meet minimum acceptable standards in one or more areas; remedial action required in one or more areas; deficiencies in one or more areas which adversely affect overall performance.

(c) As a benchmark for evaluation, in order to be rated "Excellent," the contractor must be under cost, on or ahead of schedule, and have provided excellent technical performance.

(d) A scoring system appropriate for the circumstances of the individual contract requirement should be developed. Weighted scoring is recommended. In this system, each evaluation factor (e.g., technical, schedule, cost control) is assigned a specific percentage weighting with the cumulative weightings of all factors totaling 100. During the award fee evaluation, each factor is scored from 0-100 according to the ratings defined in 1816.405-275(b). The numerical score for each factor is then multiplied by the weighting for that factor to determine the weighted score. For example, if the technical factor has a weighting of 60 percent and the numerical score for that factor is 80, the weighted technical score is 48 (80 x 60 percent). The weighted scores for each evaluation factor are then added to determine the total award fee score.

1816.406 Contract clauses.

1816.406-70 NASA contract clauses.

(a) As authorized by FAR 16.406(e), the contracting officer shall insert the clause at 1852.216-76, Award Fee for Service Contracts, in solicitations and contracts when an award-fee contract is contemplated and the contract deliverable is the performance of a service. When provisional award fee payments are authorized, use Alternate I.

(b) As authorized by FAR 16.406(e), the contracting officer shall insert the clause at 1852.216-77, Award Fee for End Item Contracts, in solicitations and contracts when an award fee contract is contemplated and the contract deliverables are hardware or other end items for which total contractor performance cannot be measured until the end of the contract. When the clause is used in a fixed-price award-fee contract, it shall be modified by deleting references to base fee in paragraphs (a), and by deleting paragraph (c)(1), the last sentence of (c)(4), and the first sentence of (c)(5).

(c) The contracting officer may insert a clause substantially as stated at 1852.216-83, Fixed Price Incentive, in fixed-price-incentive solicitations and contracts utilizing firm or successive targets. For items subject to incentive price revision, identify the target cost, target profit, target price, and ceiling price for each item.

(d) The contracting officer shall insert the clause at 1852.216-84, Estimated Cost and Incentive Fee, in cost-plus-incentive-fee solicitations and contracts.

(e) The contracting officer may insert the clause at 1852.216-85, Estimated Cost and Award Fee, in award-fee solicitations and contracts. When the contract includes performance incentives, use Alternate I. When the clause is used in a fixed-price award fee contract, it shall be modified to delete references to base fee and to reflect the contract type.

(f) As provided at 1816.402-270, the contracting officer shall insert a clause substantially as stated at 1852.216-88, Performance Incentive, when the primary deliverable(s) is (are) hardware and total estimated cost and fee is greater than $25 million. A clause substantially as stated at 1852.216-88 may be included in lower dollar value hardware contracts with the approval of the procurement officer.

Subpart 1816.5--Indefinite-Delivery Contracts

1816.504 Indefinite quantity contracts.

(a)(4)(ii) ID/IQ service contract values and task order values shall be expressed only in dollars.

1816.505 Ordering.

(a)(2) Task and delivery orders shall be issued by the contracting officer.

(b)(4) The Agency and installation ombudsmen designated in accordance with 1815.70 shall review complaints from contractors on task order contracts and delivery order contracts.

1816.505-70 Task ordering.

(a) The contracting officer shall, to the maximum extent possible, state task order requirements in terms of functions and the related performance and quality standards such that the standards may be objectively measured.

(b) To the maximum extent possible, contracting officers shall solicit contractor task plans to use as the basis for finalizing task order requirements and enable evaluation and pricing of the contractor's proposed work on a performance based approach as described in 1816.404-270(a).

(c) Task order contract type shall be individually determined, based on the nature of each task order's requirements.

(1) Task orders may be grouped by contract type for administrative convenience (e.g., all CPIF orders, all FFP orders, etc.) for contractor progress and cost reporting.

(2) Under multiple awards, solicitations for individual task plans shall request the same pricing structure from all offerors.

(d) Any undefinitized task order issued under paragraph (f) of the clause at 1852.216-80, Task Ordering Procedure, shall be treated and reported as an undefinitized contract action in accordance with 1843-70.

1816.506-70 NASA contract clause.

Insert the clause at 1852.216-80, Task Ordering Procedure, in solicitations and contracts when an indefinite-delivery, task order contract is contemplated. The clause is applicable to both fixed-price and cost-reimbursement type contracts. If the contract does not require 533M reporting (See NHB 9501.2), use the clause with its Alternate I.

Subpart 1816.6--Time-and-Materials, Labor-Hour, and Letter Contracts

1816.603 Letter contracts.

1816.603-370 Approvals.

(a) All requests for authority to issue a letter contract shall include the following:

(1) Proposed contractor's name and address.

(2) Location where contract is to be performed.

(3) Contract number, including modification number, if applicable.

(4) Brief description of the work or services to be performed.

(5) Performance period or delivery schedule.

(6) Amount of letter contract.

(7) Performance period of letter contract.

(8) Estimated total amount of definitive contract.

(9) Type of definitive contract to be executed.

(10) A statement that the definitive contract will contain all required clauses or identification of specific clause deviations that have been approved.

(11) A statement as to the necessity and advantage to the Government of the proposed letter contract.

(12) The definitization schedule described in FAR 16.603-2(c) expected to be negotiated with the contractor.

(b) Requests for authority to issue letter contracts having an estimated definitive contract amount equal to or greater than the Master Buy Plan submission thresholds of 1807.7101 (or modifications thereto) shall be signed by the procurement officer and submitted to the Associate Administrator for Procurement (Code HS) for approval.

(c) Authority to approve the issuance of letter contracts below the Master Buy Plan submission thresholds specified in 1807.7101 is delegated to the procurement officer.

(d) Any modification of an undefinitized letter contract approved by a procurement officer in accordance with paragraph (c) of this section that increases the estimated definitized contract amount to or above the Master Buy Plan submission thresholds must have the prior approval of the Associate Administrator for Procurement (Code HS).


PART 1819

SMALL BUSINESS PROGRAMS

TABLE OF CONTENTS

1819.001 Definitions.

SUBPART 1819.2 POLICIES

1819.201 General policy.

1819.202 Specific policies.

1819.202-1 Encouraging small business participation in acquisitions.

1819.202-170 Contract consolidations.

SUBPART 1819.3 DETERMINATION OF STATUS AS A SMALL BUSINESS CONCERN

1819.302 Protesting a small business representation.

SUBPART 1819.5 SET-ASIDES FOR SMALL BUSINESS

1819.502 Setting aside acquisitions.

1819.502-70 Non-initiation of set-asides.

1819.502-3 Partial set-asides.

1819.502-370 NASA reporting requirements.

1819.505 Rejecting Small Business Administration recommendations.

1819.506 Withdrawing or modifying set-asides.

SUBPART 1819.6 CERTIFICATES OF COMPETENCY AND DETERMINATIONS OF RESPONSIBILITY

1819.602 Procedures.

1819.602-1 Referral.

1819.602-3 Resolving differences between the agency and the Small Business Administration.

1819.602-370 NASA procedures.

SUBPART 1819.7 SUBCONTRACTING WITH SMALL BUSINESS, SMALL DISADVANTAGED BUSINESS AND WOMEN-OWNED SMALL BUSINESS CONCERNS

1819.705-2 Determining the need for a subcontracting plan.

1819.705-4 Reviewing the subcontracting plan.

1819.705-470 Acquisition-specific subcontracting goals.

1819.708 Solicitation provisions and contract clauses.

1819.708-70 NASA solicitation provision and contract clause.

SUBPART 1819.8 CONTRACTING WITH THE SMALL BUSINESS ADMINISTRATION (THE 8(a) PROGRAM)

1819.804 Evaluation, offering, and acceptance.

1819.804-1 Agency evaluation.

SUBPART   1819.10 SMALL BUSINESS COMPETITIVENESS DEMONSTRATION PROGRAM

1819.1005 Applicability.

SUBPART 1819.70 NASA 8 PERCENT GOAL

1819.7000 General.

1819.7001 Definitions.

1819.7002 Contracting officer responsibility.

1819.7003 Contract clause.

SUBPART   1819.71 NASA RURAL AREA SMALL BUSINESS PLAN

1819.7101 Definition.

1819.7102 General.

1819.7103 Solicitation provision and contract clause.

SUBPART 1819.72 NASA MENTOR-PROTÉGÉ PROGRAM

1819.7201 Scope of subpart.

1819.7202 Definitions.

1819.7203 Non-affiliation.

1819.7204 Transportability of features from the Department of Defense DOD) Mentor-Protégé program to NASA contractors.

1819.7205 General policy.

1819.7206 Incentives for prime contractor participation.

1819.7207 Measurement of Program success.

1819.7208 Mentor firms.

1819.7209 Protégé firms.

1819.7210 Selection of protégé firms.

1819.7211 Application process for mentor firms to participate in the Program.

1819.7212 OSDBU review and approval process of agreement.

1819.7213 Agreement contents.

1819.7214 Developmental assistance.

1819.7215 Obligation.

1819.7216 Internal controls.

1819.7217 Reports.

1819.7218 Program review.

1819.7219 Solicitation provision and contract clauses.


the small business specialist and the cognizant technical office, shall prepare an impact assessment of the effects of the consolidation on present and future contracting and subcontracting opportunities for small, small disadvantaged, and women-owned small business. The impact assessment shall address the reasons for the proposed consolidation (especially where apparently unrelated efforts are being combined), the expected benefits, and any actions planned to mitigate or eliminate the impact on small business entities. The impact assessment shall be forwarded to the Associate Administrator for Procurement (Code HS) for concurrence by cognizant Headquarters offices and approval by the Associate Deputy Administrator (Technical).

Subpart 1819.3--Determination of Status as a Small Business Concern

1819.302 Protesting a small business representation.

(d)(1) The contracting officer shall not make awards of small business set-aside acquisitions before the expiration of the period for receipt of a size standard protest.

Subpart 1819.5--Set-Asides for Small Business

1819.502 Setting aside acquisitions.

1819.502-70 Non-initiation of set-asides.

(a) All cases involving the non-initiation of a set-aside, whether resulting from a joint decision of the small business specialist and the contracting officer or a decision by the contracting officer alone, require referral to the SBA representative (if one is assigned and available) for review.

(b) If the small business specialist recommends that an individual acquisition or a class of acquisitions, or a portion thereof, be set aside, the contracting officer shall promptly either concur in or disapprove the recommendation, stating in writing the reasons for disapproval.

(c) When an SBA representative is assigned and available and the contracting officer disapproves the small business specialist's recommendation, the contracting officer shall promptly refer the case to the SBA representative for review. The small business specialist shall take no further appeal action. The SBA representative must either concur with the decision or appeal the case to the procurement officer under FAR 19.505. If the procurement officer approves the contracting officer's decision and the SBA appeals under FAR 19.505(c), the procurement officer shall forward the required written justification, including a history of discussions between the center and the SBA and rationale for the decision, to the Headquarters Office of Procurement (HS).

(d) When an SBA representative is not assigned or available and the contracting officer disapproves the small business specialist's recommendation, the small business specialist may appeal in writing to the procurement officer. The procurement officer's decision shall be final. The contracting officer shall place a memorandum of the procurement officer's decision in the contract file. If the procurement officer's decision approves the contracting officer's action, the small business specialist shall forward complete documentation of the case to the Headquarters Office of Small and Disadvantaged Business Utilization (Code K).

(e) The contracting officer shall prepare, sign, and retain in the contract file a memorandum of nonconcurrence in a recommended set-aside action.

1819.502-3 Partial set-asides.

1819.502-370 NASA Reporting Requirements.

The contracting officer shall separately report, in accordance with Subpart 1804.6, awards of the non-set-aside portions of small business set-aside acquisitions.

1819.505 Rejecting Small Business Administration recommendations.

See 1819.502-70.

1819.506 Withdrawing or modifying set-asides.

(b) If an SBA representative is not assigned or available, and the small business specialist disagrees with the contracting officer's written decision of withdrawal or modification of a set-aside determination, the small business specialist may appeal to the procurement officer in accordance with the procedures in 1819.502-70(d).

Subpart 1819.6--Certificates of Competency and Determinations of Responsibility

1819.602 Procedures.

1819.602-1 Referral.

(a) On proposed awards exceeding the simplified acquisition threshold, the contracting officer should consider requesting a preaward survey (see FAR 9.106) before determining that a responsive small business firm is not responsible. The scope of the preaward survey request should be limited to those elements of responsibility that are questioned.

(2) The contracting officer shall forward a copy of the referral to SBA through the procurement officer to the Headquarters Office of Small and Disadvantaged Business Utilization (Code K).

1819.602-3 Resolving differences between the agency and the Small Business Administration.

1819.602-370 NASA Procedures.

(a) When agreement cannot be reached between the contracting officer and the SBA Area Office, the contracting officer shall forward to the Headquarters Office of Procurement (Code HS) on an expedited basis, a complete case file with a request that the case be considered for appeal to SBA Headquarters. The contracting officer shall include the data already furnished to SBA, SBA's rationale for proposing to issue a COC, and the contracting officer's comments. The contracting officer shall suspend acquisition action until informed by Code HS of the final decision in the case.

(b) If the Office of Procurement concludes that the referral to SBA should be withdrawn and a contract awarded without benefit of a COC, Code HS shall inform the contracting officer.

(c) If the Office of Procurement agrees with the contracting officer's recommended appeal action, the Associate Administrator for Procurement shall forward the appeal through the Office of Small and Disadvantaged Business Utilization (Code K) to SBA Headquarters.

Subpart 1819.7--Subcontracting with Small Business, Small Disadvantaged Business and Women-Owned Small Business Concerns


PART 1837

SERVICE CONTRACTING

TABLE OF CONTENTS

SUBPART 1837.1 SERVICE CONTRACTS--GENERAL

1837.101 Definitions.

1837.104 Personal services contracts.

1837.110 Solicitation provisions and contract clauses.

1837.110-70 NASA solicitation provision and contract clauses.

1837.170 Pension portability.

SUBPART 1837.2 ADVISORY AND ASSISTANCE SERVICES

1837.203 Policy.

1837.204 Guidelines for determining availability of personnel.

SUBPART 1837.70 ACQUISITION OF TRAINING

1837.7000 Acquisition of off-the-shelf training courses.

1837.7001 Acquisition of new training courses.

PART 1837

SERVICE CONTRACTING

Subpart 1837.1--Service Contracts--General

1837.101 Definitions.

"Pension portability" means the recognition and continuation in a successor service contract of the predecessor service contract employees' pension rights and benefits.

1837.104 Personal services contracts.

(b) Section 203(c)(9) of the National Aeronautics and Space Act of 1958 (42 U.S.C. 2473(c)(9)) authorizes NASA "to obtain services as authorized by Section 3109 of Title 5, United States Code." It is NASA policy to obtain the personal services of experts and consultants by appointment rather than by contract. The policies, responsibilities, and procedures pertaining to the appointment of experts and consultants are in NMI 3304.1G.

1837.110 Solicitation provisions and contract clauses.

1837.110-70 NASA solicitation provision and contract clauses.

(a) The contracting officer shall insert the clause at 1852.237-70, Emergency Evacuation Procedures, in solicitations and contracts for on-site support services where emergency evacuations of the NASA installation may occur, e.g., snow, hurricanes, tornadoes, earthquakes, or other emergencies.

(b) The contracting officer shall insert the clause at 1852.237-71, Pension Portability, in solicitations, contracts or negotiated contract modifications for additional work when the procurement officer makes the determination in 1837.170(a)(2).

1837.170 Pension portability.

(a) It is NASA's policy not to require pension portability in service contracts. However, pension portability requirements may be included in solicitations, contracts, or contract modifications for additional work under the following conditions:

(1)(i) There is a continuing need for the same or similar services for a minimum of five years (inclusive of options), and, if the contractor changes, a high percentage of the predecessor contractor's employees are expected to remain with the program; or

(ii) The employees under a predecessor contract were covered by a portable pension plan, a follow-on contract or a contract consolidating existing services is awarded, and the total contract period covered by the plan covers a minimum of five years (including both the predecessor and successor contracts); and

(2) The procurement officer determines in writing, with full supporting rationale, that such a requirement is in the Government's best interest. The procurement officer shall maintain a record of all such determinations.

(b) When pension portability is required, the plan shall comply with the requirements of the clause at 1852.237-71, Pension Portability, (see 1837.110-70(b)), and the contract shall also include a clear description of the plan, including service, pay, liabilities, vesting, termination, and benefits from prior contracts.

Subpart 1837.2--Advisory and Assistance Services

1837.203 Policy.

(c) Advisory and assistance services of individual experts and consultants shall normally be obtained by appointment rather than by contract (see NMI 3304.1, Employment of Experts and Consultants).

1837.204 Guidelines for determining availability of personnel.

(a)(i) Outside peer review evaluators may be used to evaluate SBIR, STTR, NRA, AO, and unsolicited proposals without making the determination of non-availability.

(ii) For all other actions, the NASA official one level above the NASA program official responsible for the evaluation shall make the determination, with the concurrence of the legal office. The contracting officer shall ensure that a copy of the determination is in the contract file prior to issuance of a solicitation.

(b) The official designated in paragraph (a)(ii) of this section is responsible for the actions required in FAR 37.204(b).

(c) The agreement shall be made by the program official responsible for the evaluation and the contracting officer.

(e) The Associate Administrator for Procurement (Code HS) is the approval authority for class determinations. The class determination request shall include the assessment required by FAR 37.204(b).

Subpart 1837.70--Acquisition of Training

1837.7000 Acquisition of off-the-shelf training courses.

The Training Act of 1958 (5 U.S.C. 4101 et seq.) may be used as the authority for training of NASA employees by, in, or through non-Government off-the-shelf training courses which are available to the public. These include established university catalog courses or commercial course offerings that are offered to the general public at catalog or market prices.

1837.7001 Acquisition of new training courses.

The acquisition of a new training course that must be developed to fulfill a specific NASA need shall be conducted in accordance with the FAR and the NFS.