RISK MANAGEMENT

PURPOSE: To emphasize considerations of risk management, including safety, security (including information technology security), health, export control, and damage to the environment, within the acquisition process.

BACKGROUND: It is critically important for NASA to achieve mission success without compromising safety. However, given that many of NASA's activities involve advanced research, aeronautics, and space flight, NASA cannot completely avoid risk. Therefore, risk must be managed, i.e., comprehensively identified, analyzed, planned, tracked, controlled, communicated, and documented. While risk management is not a new acquisition concept, NASA has initiated a risk-based acquisition management initiative to re-focus on risk as a core acquisition concern. That initiative will be implemented by providing training to NASA and contractor personnel, consultation to NASA projects and programs, and updated policy and guidance through revisions to several of NASA's internal processes and guidelines. This PN implements that part of the initiative pertaining directly to the procurement process. Since NASA's activities often include contractor efforts, NASA's focus on safety and mission success must be conveyed in NASA contracts.

REGULATION: Changes are made in Parts 1807, 1811, 1812, 1815, 1816, 1823, 1842, 1846, and 1852 as set forth in the enclosed replacement pages.

DO NOT FILE THIS PN UNTIL JULY 13, 2000.

REPLACEMENT PAGES: You may use the enclosed pages to replace Part 1807, Part 1811, Part 1812, Part 1815, 16:7, 16:8, 16:9, 16:10, 16:11, 16:12, 16:13 (added), Part 1823, 42:6.1, Part 1846, 52:1, 52:2, 52:27, 52:28, 52:29, 52:30, 52:30.1, 52:30.2, 52:30.3 (added), 52-93, and 52-94.

REGULATORY COMPLIANCE: This PN was published as an interim rule in the Federal Register (65 FR 37057-37061, June 13, 2000). A proposed rule was published in the Federal Register at 64 FR 38880-84 on June 20, 1999.

EFFECTIVE DATE: This PN is effective July 13, 2000, and shall remain in effect until canceled or superseded.

HEADQUARTERS CONTACT: James H. Dolvin, Code HK, (202) 358-1279, e-mail: jdolvin1@mail.hq.nasa.gov.

 

R. Scott Thompson
Director, Contract Management Division

Enclosures


PART 1807
ACQUISITION PLANNING

TABLE OF CONTENTS

SUBPART 1807.1 ACQUISITION PLANS

1807.103 Agency-head responsibilities.

1807.104 General procedures.

1807.105 Contents of written acquisition plans.

1807.170 Acquisition Strategy Meeting (ASM).

SUBPART 1807.2 PLANNING FOR THE PURCHASE OF SUPPLIES IN ECONOMIC QUANTITIES

1807.204 Responsibilities of contracting officers.

SUBPART 1807.3 CONTRACTOR VERSUS GOVERNMENT PERFORMANCE

1807.307 Appeals.

SUBPART 1807.5 INHERENTLY GOVERNMENTAL FUNCTIONS

1807.503 Policy.

SUBPART 1807.70 CONSOLIDATED CONTRACTING

1870.7000 General.

SUBPART 1807.71 MASTER BUY PLAN

1807.7100 General.

1807.7101 Applicability.

1807.7102 Submission, selection, and notification procedures.

1807.7102-1 Submission of Master Buy Plan.

1807.7102-2 Submission of amendments to the Master Buy Plan.

1807.7102-3 Selection and notification procedures.

1807.7103 Format of Master Buy Plan.

SUBPART 1807.72 ACQUISITION FORECASTING

1807.7200 Scope of subpart.

1807.7201 Definitions.

1807.7202 Policy.

1807.7203 Responsibilities.

1807.7204 Forecast data.

1807.7205 Public availability.

 

PART 1807
ACQUISITION PLANNING

Subpart 1807.1 - Acquisition Plans

1807.103 Agency-head responsibilities.

(d)(i) Except as provided in paragraph (d)(iii) of this section, acquisition plans shall be prepared according to the following:

(A) For acquisitions requiring Headquarters approval, by an Acquisition Strategy Meeting (ASM) (see 1807.170);

(B) For acquisitions not requiring Headquarters approval and expected to exceed $5 million, by installation-approved ASMs or written acquisition plans; and,

(C) For acquisitions not expected to exceed $5 million, in accordance with installation procedures.

(ii) The estimated dollar amounts shall include all options and later phases of the same program or project.

(iii) Acquisition plans are not required for the following acquisitions:

(A) Architect-engineering services;

(B) Broad agency announcements (see 1835.016) or unsolicited proposals;

(C) Basic research from nonprofit organizations;

(D) Utility services available from only one source;

(E) From or through other Government agencies;

(F) Industrial facilities required in support of related contracts; or

(G) MidRange procedure awards (see 1871). However, acquisition plans are required for commercial item acquisitions that exceed the MidRange dollar thresholds for noncommercial items.

(iv) Acquisition plans shall be approved before soliciting proposals.

(v) Approval of an acquisition plan does not constitute approval of any special conditions, or special clauses that may be required unless the plan so specifies, and the individual having approval authority is a signatory of the plan. All required deviations shall be approved through the procedures described in FAR 1.4 and 1801.4.

(vi) A single acquisition plan may be used for all phases of a phased acquisition provided the plan fully addresses each phase, and no significant changes occur after plan approval to invalidate the description of the phases. If such significant changes do occur, the plan shall be amended and approved at the same level as the original plan.

(e) Acquisition plans should be prepared on a program or system basis when practical. In such cases, the plan should fully address all component acquisitions of the program or system.

1807.104 General procedures.

(a) The acquisition planning team shall obtain input from the center offices responsible for matters of safety and mission assurance, occupational health, environmental protection, information technology, export control, and security. Their presence on the team shall help to ensure that all NASA acquisitions are structured in accordance with NASA safety, occupational health, environmental, export control, and security policy. As part of this process, the team shall recommend any appropriate solicitation or contract requirements for implementation of safety, occupational health, environmental, information technology, export control, and security concerns. (See NPG 8715.3, NASA Safety Manual; NPG 7120.5, NASA Program and Project Management Processes and Requirements; NPG 2810.1, Security of Information Technology, and NPG 1620.1, Security Procedures and Guidelines, all available at www.nodis.hq.nasa.gov).

1807.105 Contents of written acquisition plans.

Acquisition plans shall address each applicable topic listed in FAR 7.105, as supplemented by this section. Plans shall be structured by subject heading using each italicized topic heading in the same sequence as presented in the FAR. Subheadings should be used when appropriate (e.g., the separate items under contracting considerations at 7.105(b)(4)). Topics not applicable to a given acquisition (e.g., design-to-cost and should-cost are not compatible with service acquisitions), should be marked N/A. The requirements in FAR 7.105 regarding performance-based contracting methods shall not be limited to acquisition plans for service contracts.

(a)(1) Describe in nontechnical terms the supplies or services to be acquired. Include quantities.

(a)(2) NPG 7120.5 shall be an integral part of acquisition planning for programs and projects subject to its requirements. If the NPG does not apply, the acquisition plan shall clearly state that fact. If the NPG does apply, specify whether all required NPG 7120.5 documentation is current and approved (see 1804.7301(b)(2)(i)). If not, describe the approach for obtaining approval or the authority to proceed without approval before release of draft or final solicitations. For programs and projects under the NPG, all draft or final solicitations subject to, or directly or substantially in support of, those programs or projects shall clearly identify the program or project of which they are part.

(a)(3) Identify the estimated cost and describe the estimating methodology.

(a)(5) Specify the delivery or performance period requirements separately by the basic contract, each option, and the total.

(a)(7) Discuss project/program risks (see NPG 7120.5, NASA Program and Project Management Processes and Requirements). In addition to technical, schedule, and cost risks, the discussion shall include such considerations as: safety and security (including personnel, information technology, and facilities/property); the need to involve foreign sources (contractor and/or governmental), and risks of unauthorized technology transfer (see NPG 2190, NASA Export Control Program); and resource risk, including the necessary level and expertise of NASA personnel resources available to manage the project/program. For each area of risk identified, the discussion shall include a quantification of the relative magnitude (e.g., high, medium, low) together with the specific actions taken to structure the acquisition approach to manage the risks throughout the acquisition process. For example, this discussion would identify those areas that have safety risk, discuss how safety is addressed in contract requirements and evaluated in the source selection, and how it will be managed and incentivized during contract performance. Decisions to accept, mitigate, track, and/or research risk factors shall be identified and documented as part of acquisition planning.

(a)(8) Streamlining applies to all NASA acquisitions. Describe all planned streamlining procedures.

(b)(1) If the acquisition represents a consolidation of efforts previously contracted for separately, address the reasons for the consolidation, the expected benefits, and any potential adverse impact (including the effect on small, small disadvantaged, and women-owned small business participation) and planned actions to mitigate the impact (see 1819.202-170).

(b)(3) Address how cost realism will be evaluated.

(b)(4)(A) If an incentive contract is planned, describe the planned incentive(s) and the anticipated effects.

(B) Describe subcontracting issues, including all applicable subcontracting goals. (See FAR part 19 and part 1819).

(b)(5)(A) Identify the estimated cost separately by the basic contract, each option and total amount.

(B) Identify the funding by fiscal year and unique project number (UPN).

(C) Discuss planned approaches to eliminate funding shortfalls (vs. the estimated cost).

(b)(6) Identify the type of work statement/specification planned. Specifically address the applicability of performance-based requirement descriptions and the availability of commercial sources for the supplies/services.

(b)(10) Address contract management issues, including planned delegations of administrative functions.

(b)(20) If the period between release of solicitation to contract award is more than 120 calendar days (180 days for formal SEB competitions), explain why that goal cannot be met.

1807.170 Acquisition Strategy Meeting (ASM).

(a) The ASM is an acquisition plan conducted through a meeting attended by all interested NASA offices. At the meeting, the acquisition plan topics and structure specified in 1807.105 are presented in briefing format, and formal written minutes prepared to summarize the decisions, actions, and conclusions of the ASM members. The approved minutes, along with the briefing charts, shall be included in the contract file to document completion of the acquisition plan required by 1807.103.

(b) The ASM is not a requirements definition meeting. It is a meeting to seek approval for the proposed acquisition approach for requirements that were previously defined and agreed to by the cognizant offices.

(c) Headquarters ASMs will be chaired by the Associate Administrator for Procurement or designee. The Headquarters Office of Procurement (Code HS) will prepare the minutes of Headquarters ASMs and distribute them to all attendees for review prior to approval by the ASM chairperson.

(d) For field installation ASMs, the minutes shall be approved in accordance with installation procedures.

Subpart 1807.2--Planning for the Purchase of Supplies in Economic Quantities

1807.204 Responsibilities of contracting officers.

(a) The contracting officer shall transmit in writing to the cognizant inventory management/requirements office either the actual offeror responses or a summary of their salient points. The transmittal should be made within five working days after the closing date for receipt of offers; however, if a response indicates the potential for a significant savings, it should be transmitted immediately.

Subpart 1807.3--Contractor Versus Government Performance

1807.307 Appeals.

(a) Installations shall establish appeals procedures in accordance with NMI 7410.3, Delegation of Authority for Acquisition of Commercial Activities for NASA's Use.

Subpart 1807.5--Inherently Governmental Functions

1807.503 Policy.

(e) The field installation requirements office shall provide the contracting officer the written determination that none of the statement of work tasks are inherently governmental. Disagreements regarding the determination shall be resolved in accordance with installation procedures.

Subpart 1807.70--Consolidated Contracting

1807.7000 General.

The Consolidated Contracting Initiative (CCI) is NASA's commitment to the cooperative creation and utilization of contracts, whenever practicable, to meet common Agency needs. CCI aims at improving acquisition efficiency by identifying and logically combining similar requirements. Complete information on the initiative, with its implementation guidance, is available in the internet (http://ec.msfc.nasa.gov/hq/cci/first.html).

Subpart 1807.71--Master Buy Plan

1807.7100 General.

The Master Buy Plan provides information on planned acquisitions to enable management to focus its attention on a representative selection of high-dollar-value and otherwise sensitive acquisitions.

1807.7101 Applicability.

(a) The Master Buy Plan applies to each negotiated acquisition, including supplemental agreements, where the dollar value, including the aggregate amount of options, follow-on acquisitions, or later phases of multi-phase acquisitions, is expected to equal or exceed $50,000,000.

(b) For initial annual Master Buy Plan submission only, each installation shall submit its three largest acquisitions regardless of dollar value and all acquisitions over $50,000,000.

(c) The procedure also applies to:

(1) Any supplemental agreement that contains either new work, a debit change order, or a credit change order (or any combination/ consolidation thereof), if the absolute value of the actions equals or exceeds $50,000,000 (e.g., the absolute value of a supplemental agreement adding $30,000,000 of new work and deleting $30,000,000 of work is $60,000,000, and is therefore subject to the Master Buy Plan).

(2) Any supplement agreement that contains one or more elements (new work and/or individual change orders) of a sensitive nature that, in the judgment of the installation or Headquarters, warrants Headquarters consideration under the Master Buy Plan, even though the value does not equal or exceed $50,000,000.

(d) The Master Buy Plan does not apply to incremental funding actions or termination settlement agreements.

1807.7102 Submission, selection, and notification procedures.

1807.7102-1 Submission of Master Buy Plan.

(a) Prior to July 15th of every year, each installation shall submit to the Headquarters Office of Procurement (Code HS) a Master Buy Plan (electronically or original and eight copies) for the next fiscal year, listing every known acquisition that (1) meets the criteria in 1807.7101, (2) is expected to be initiated in that fiscal year, and (3) has not been included in a previous Master Buy Plan or amendment to a Master Buy Plan.

(b) The fiscal year Master Buy Plan shall list all uncompleted acquisitions selected for Headquarters review and approval from prior Master Buy Plans and amendments to Master Buy Plans. These acquisitions should be listed by the appropriate fiscal year Master Buy Plan and individual item numbers, and should indicate the current status of the individual acquisition documents previously selected for Headquarters review and approval.

(c) Plans shall be prepared in accordance with 1807.7103 and shall identify the individual acquisition documents involved for every acquisition listed. Acquisition documents that may require Headquarters approval will be held in abeyance until receipt of the notification required by 1807.7102-3. This is not to preclude the planning for or initiation of such documents up to that point where Headquarters approval may be required.

1807.7102-2 Submission of amendments to the Master Buy Plan.

(a) Acquisitions identified by installations after submission of their Master Buy Plan and meeting the criteria in 1807.7102-1(a) shall be submitted to Headquarters in accordance with 1807.7103 and identified as an amendment to the fiscal year Master Buy Plan submission.

(b) Master Buy Plan submissions should not be accomplished after the fact. Amendments shall be submitted sufficiently in advance of contract award date to allow Headquarters to select those acquisition documents that will be subject to Headquarters review and approval without creating an unacceptable delay in contract placement.

(c) When timely submittal is not possible, the installation shall provide with the amendment a narrative explaining the circumstances leading to the late submittal. A Master Buy Plan submission for a contract change order expected to meet the criteria in 1807.7101 shall be submitted to Headquarters immediately upon issuance of the change order.

1807.7102-3 Selection and notification procedures.

(a) The Headquarters Office of Procurement (Code HS) shall select acquisition documents from the Master Buy Plan and amendments to Master Buy Plans to receive Headquarters review and approval and shall designate source selection officials.

(b) When, subsequent to document selection or delegation, an acquisition is changed (for example, increase or decrease in dollar amount, change in requirement), canceled, superseded, deferred, or becomes no longer subject to the Master Buy Plan procedures in accordance with the criteria in 1807.7101, the installation shall immediately notify Code HS, giving the reasons. Code HS shall notify the installation's procurement office in writing of any further action that may be required.

(c) Acquisition documents not selected for Headquarters review will be subject to after-the-fact reviews by Headquarters during normal procurement management surveys or other special reviews. Acquisition delegations may subsequently be rescinded if a Headquarters review is deemed appropriate.

1807.7103 Format of Master Buy Plan.

In accordance with the requirements of 1807.7102-1 and 1807.7102-2, Master Buy Plans and amendments to Master Buy Plans shall be prepared in accordance with the format illustrated in Table 1807-1.

Subpart 1807.72--Acquisition Forecasting

1807.7200 Scope of subpart.

This subpart prescribes the acquisition forecasting procedure required to comply with the Business Opportunity Development Reform Act of 1988.

1807.7201 Definitions.

"Class of contracts" means a grouping of acquisitions, either by dollar value or by the nature of supplies and services to be acquired.

"Contract opportunity" means planned new contract awards exceeding $25,000.

1807.7202 Policy.

As required by statute, it is NASA policy to (a) prepare an annual forecast and semiannual update of expected contract opportunities or classes of contract opportunities for each fiscal year; (b) include in the forecast contract opportunities that small business concerns, including those owned and controlled by socially and economically disadvantaged individuals, may be capable of performing; and (c) make available such forecasts to the public.

1807.7203 Responsibilities.

(a) NASA Procurement Officers shall post the data required by 1807.7204 directly to the NASA Acquisition Internet Service not later than October 1 for the annual forecast and April 15 for the semiannual update.

(b) Code HS will manage policy and monitor compliance with the NASA Acquisition Forecast process.

1807.7204 Forecast data.

(a) The annual forecast shall contain--

(1) Summary historical data (based on information provided by the Headquarters Office of Procurement (Codes HC and HS)) on the class of contract opportunities below the simplified acquisition threshold;

(2) Identification of all known contract opportunities in excess of the simplified acquisition threshold. Each such action should be identified as one of the three broad categories of acquisition -- Research and Development, Services, or Supplies and Equipment and shall include the following information:

(i) A brief description not to exceed ten typed lines;

(ii) Approximate dollar value within the following dollar ranges: $100,000 to $1,000,000; $1,000,000 to $5,000,000; and over $5,000,000;

(iii) Anticipated time (by fiscal year quarter) for the issuance of the solicitation;

(iv) Identification if it is reserved for performance by small business concerns including those owned and controlled by socially and economically disadvantaged individuals;

(v) Identification as competitive or noncompetitive; and

(vi) Identification and telephone number of a center point of contact.

(b) The semiannual report shall be an update of the data provided by the annual forecast. This update should provide information on new requirements not previously reported and on changes in data related to actions previously identified.

1807.7205 Public availability.

The annual forecast and semiannual update are available on the NASA Acquisition Internet Service (http://www.hq.nasa.gov/office/procurement/).


PART 1811
DESCRIBING AGENCY NEEDS

TABLE OF CONTENTS

1811.002 Policy.

SUBPART 1811.1 SELECTING AND DEVELOPING REQUIREMENTS DOCUMENTS

1811.101 Order of precedence for requirements documents.

1811.107 Solicitation provisions.

SUBPART 1811.4 DELIVERY OR PERFORMANCE SCHEDULES

1811.403 Supplies or services.

1811.403-70 Packaging, handling, and transportation.

1811.404 Contract clauses.

1811.404-70 NASA contract clauses.

SUBPART 1811.5 LIQUIDATED DAMAGES

1811.502 Policy.

SUBPART 1811.6 PRIORITIES AND ALLOCATIONS

1811.602 General.

1811.603 Procedures.

 

PART 1811
DESCRIBING AGENCY NEEDS

1811.002 Policy.

(b) Implementation of the Metric Conversion Act of 1975, as amended, must be in accordance with NPD 8010.2B, Use of the Metric System of Measurements in NASA Programs.

Subpart 1811.1--Selecting and Developing Requirements Documents

1811.101 Order of precedence for requirements documents.

(b) When establishing product descriptions in either a solicitation or contract, contracting officers shall include safeguards, as applicable, to ensure safety, security, and environmental protection.

1811.107 Solicitation provisions.

(b) NASA uses the categorical method to report its use of voluntary consensus standards. Therefore, use of the provision at 52.211-7 is not required. However, contracting officers must include in draft RFPs (DRFPs) the information required by 1815.201(c)(6)(A).

Subpart 1811.4--Delivery or Performance Schedules

1811.403 Supplies or services.

(a)(3) Contract delivery or performance schedules must not be expressed in terms of a notice of award. A notice of award as a specific document, separate from the award document itself, is not a contractual document and shall not be used as a reference point for contract performance. See 1814.408 for additional information on notices of award.

1811.403-70 Packaging, handling, and transportation.

(a) NPG 6000.1E, "Requirements for Packaging, Handling, and Transportation for Aeronautical and Space Systems, Equipment, and Associated Components" provides guidance for shipment of certain NASA items.

(b) Contracting officers, with the advice of the requiring activity and the Center Transportation Officer, must include a designation of each deliverable item, or groupings of deliverable items, as Class I, II, III, or IV for purposes of contractor compliance with the NPG.

1811.404 Contract clauses.

(a)(2) FAR 52.211-8, Time of Delivery, Alternates II and III, must not be used in NASA contracts.

(3) FAR 52.211-9, Desired and Required Time of Delivery, Alternates II and III, must not be used in NASA contracts.

1811.404-70 NASA contract clauses.

The clause at 1852.211-70, Packaging, Handling, and Transportation, must be included in solicitations and contracts for deliverable items, including software, designated as Class I (mission essential), Class II (delicate or sensitive), or Class III (requires special handling or monitoring).

Subpart 1811.5--Liquidated Damages

1811.502 Policy.

(d) The procurement officer must forward recommendations concerning remission of liquidated damages to the Headquarters Office of Procurement (Code HS).

Subpart 1811.6--Priorities and Allocations

1811.602 General.

(c) The Department of Defense is the "Delegate Agency" for NASA. The Headquarters Office of Procurement (Code HS) must coordinate with DOD, as necessary, to ensure that any DOD requirements are met.

1811.603 Procedures.

(e)(i) The use of priority ratings on NASA contracts and purchase orders is mandatory except as noted in paragraph (e)(ii) of this section. Priority ratings are assigned on individual contracts and purchase orders by the contracting officer.

(ii) Priority ratings will not be issued for the following:

(A) Items ordered or requisitioned from the GSA Federal Supply Service.

(B) Items for plant improvement, expansion, or construction, unless they will be physically incorporated into a construction project covered by a rated order, or unless NASA has obtained specific priority rating authority.

(C) Production or construction equipment or items to be used for the manufacture of production equipment, unless NASA has obtained specific priority rating authority.

(D) Items falling under the jurisdiction of agencies other than NASA's Delegate Agency. These are: petroleum, gas, solid fuel, electric power, and all other forms of energy; food; civil transportation and the movement of persons and property by all modes; minerals; water; housing facilities; health facilities; radio-isotopes, stable isotopes, source material and special nuclear material produced in Government-owned plants or facilities operated by or for the Department of Energy; communication services; copper raw materials; crushed stone; gravel; sand; scrap; slag; central steam heat; and waste paper.

(iii) All other NASA orders must be assigned a DO rating, unless NASA has obtained a DX rating from the Delegate Agency.

(iv) The program identification numbers (DPAS, 15 CFR Part 700, SCH L.) to be used by NASA are as follows:

A1 Aircraft

A2 Missiles

A3 Ships

A5 Weapons

A6 Ammunition

A7 Electronic and Communications Equipment

B1 Military Building Supplies

B8 Production Equipment (For Contractor's Account)

B9 Production Equipment (Government-Owned)

C2 Construction

C3 Maintenance, Repair, and Operating Supplies for Facilities

C9 Miscellaneous/Other

(g) Installation requests for assistance shall be directed to the Headquarters Office of Procurement (Code HS).


PART 1812
ACQUISITION OF COMMERCIAL ITEMS

TABLE OF CONTENTS

SUBPART 1812.1 ACQUISITION OF COMMERCIAL ITEMS--GENERAL

1812.102 Applicability.

SUBPART 1812.3 SOLICITATION PROVISIONS AND CONTRACT CLAUSES FOR THE ACQUISITION OF COMMERCIAL ITEMS

1812.301 Solicitation provisions and contract clauses for the acquisition of commercial items.

1812.302 Tailoring of provisions and clauses for the acquisition of commercial items.

SUBPART 1812.4 UNIQUE REQUIREMENTS REGARDING TERMS AND CONDITIONS FOR COMMERCIAL ITEMS

1812.404 Warranties.

SUBPART 1812.70 COMMERCIAL SPACE HARDWARE OR SERVICES

1812.7000 Prohibition on guaranteed customer bases for new commercial space hardware or services.

  

PART 1812
ACQUISITION OF COMMERCIAL ITEMS

Subpart 1812.1--Acquisition of Commercial Items--General

1812.102 Applicability.

(c) For the acquisition of commercial items of any value, the MidRange procedures described in NFS part 1871 may be used to the extent they are consistent and compliant with FAR part 12 and NFS part 1812. Unless specifically stated, in any conflict between these parts the descending order of precedence is FAR part 12, part 1812, and part 1871.

Subpart 1812.3--Solicitation Provisions and Contract
Clauses for the Acquisition of Commercial Items

1812.301 Solicitation provisions and contract clauses for the acquisition of commercial items.

(f)(i) The following clauses are authorized for use in acquisitions of commercial items when required by the clause prescription:

(A) 1852.214-71, Grouping for Aggregate Award.

(B) 1852.214-72, Full Quantities.

(C) 1852.215-84, Ombudsman.

(D) 1852.219-75, Small Business Subcontracting Reporting.

(E) 1852.219-76, NASA 8 Percent Goal.

(F) 1852.223-70, Safety and Health.

(G)1852.223-71, Frequency Authorization.

(H)1852.223-73, Safety and Health Plan.

(I) 1852.223-75, Major Breach of Safety and Security.

(J) 1852.228-72, Cross-Waiver of Liability for Space Shuttle Services.

(K)1852.228-76, Cross-Waiver of Liability for Space Station Activities.

(L )1852.228-78, Cross-Waiver of Liability for NASA Expendable Launch Vehicles.

(M)1852.246-72, Material Inspection and Receiving Report.

(ii) No other provisions and clauses prescribed in the NFS or center documents shall be used in acquisitions of commercial items, except as permitted by FAR 12.302.

1812.302 Tailoring of provisions and clauses for the acquisition of commercial items.

(c) The Associate Administrator for Procurement (Code HS) is the approval authority for waivers. Requests shall be prepared and submitted in accordance with 1801.471.

Subpart 1812.4--Unique Requirements Regarding Terms and
Conditions for Commercial Items

1812.404 Warranties.

(b) In acquisitions under the Simplified Acquisition Threshold specified in FAR Part 13, no express warranty should be required other than the offeror's commercial warranty.

Subpart 1812.70--Commercial Space Hardware or Services

1812.7000 Prohibition on guaranteed customer bases for new commercial space hardware or services.

Public Law 102-139, title III, Section 2459d, prohibits NASA from awarding a contract with an expected duration of more than one year if the primary effect of the contract is to provide a guaranteed customer base for, or establish an anchor tenancy in, new commercial space hardware or services. Exception to this prohibition may be authorized only by an appropriations Act specifically providing otherwise.


PART 1815
CONTRACTING BY NEGOTIATION

TABLE OF CONTENTS

SUBPART 1815.2 SOLICITATION AND RECEIPT OF PROPOSALS AND INFORMATION

1815.201 Exchanges with industry before receipt of proposals.

1815.203 Requests for proposals.

1815.203-70 Installation reviews.

1815.203-71 Headquarters reviews.

1815.203-72 Risk management.

1815.204 Contract format.

1815.204-2 Part I-The Schedule.

1815.204-5 Part IV-Representations and instructions.

1815.204-70 Page limitations.

1815.207 Handling proposals and information.

1815.207-70 Release of proposal information.

1815.207-71 Appointing non-Government evaluators as special Government employees.

1815.208 Submission, modification, revision, and withdrawal of proposals.

1815.209 Solicitation provisions and contract clauses.

1815.209-70 NASA solicitation provisions.

SUBPART 1815.3 SOURCE SELECTION

1815.300 Scope of subpart.

1815.300-70 Applicability of subpart.

1815.303 Responsibilities.

1815.304 Evaluation factors and significant subfactors.

1815.304-70 NASA evaluation factors.

1815.305 Proposal evaluation.

1815.305-70 Identification of unacceptable proposals.

1815.305-71 Evaluation of a single proposal.

1815.306 Exchanges with offerors after receipt of proposals.

1815.307 Proposal revisions.

1815.308 Source selection decision.

1815.370 NASA source evaluation boards.

SUBPART 1815.4 CONTRACT PRICING

1815.403 Obtaining cost or pricing data.

1815.403-1 Prohibition on obtaining cost or pricing data.

1815.403-170 Waivers of cost or pricing data.

1815.403-3 Requiring information other than cost or pricing data.

1815.403-4 Requiring cost or pricing data.

1815.404 Proposal analysis.

1815.404-2 Information to support proposal analysis.

1815.404-4 Profit.

1815.404-470 NASA Form 634

1815.404-471 NASA structured approach for profit or fee objective.

1815.404-471-1 General.

1815.404-471-2 Performance risk.

1815.404-471-3 Contract type risk and working capital adjustment.

1815.404-471-4 Other considerations.

1815.404-471-5 Facilities capital cost of money.

1815.404-472 Payment of profit or fee under letter contracts.

1815.406 Documentation.

1815.406-1 Prenegotiation objectives.

1815.406-170 Content of the prenegotiation position memorandum.

1815.406-171 Installation reviews.

1815.406-172 Headquarters reviews.

1815.406-3 Documenting the negotiation.

1815.407 Special cost or pricing areas.

1815.407-2 Make-or-buy programs.

1815.408 Solicitation provisions and contract clauses.

1815.408-70 NASA solicitation provisions and contract clauses.

SUBPART 1815.5 PREAWARD, AWARD, AND POSTAWARD NOTIFICATIONS, PROTESTS, AND MISTAKES

1815.504 Award to successful offeror.

1815.506 Postaward debriefing of offerors.

1815.506-70 Debriefing of offerors - Major System acquisitions.

SUBPART 1815.6 UNSOLICITED PROPOSALS

1815.602 Policy.

1815.604 Agency points of contact.

1815.606 Agency procedures.

1815.606-70 Relationship of unsolicited proposals to NRAs.

1815.609 Limited use of data.

1815.609-70 Limited use of proposals.

1815.670 Foreign proposals.

SUBPART 1815.70 OMBUDSMAN

1815.7001 NASA Ombudsman Program.

1815.7002 Synopses of solicitations and contracts.

1815.7003 Contract clause.

 

PART 1815
CONTRACTING BY NEGOTIATION

Subpart 1815. 2--Solicitation and Receipt of Proposals and Information

1815.201 Exchanges with industry before receipt of proposals.

(c)(6)(A) Except for acquisitions described in 1815.300-70(b), contracting officers shall issue draft requests for proposals (DRFPs) for all competitive negotiated acquisitions expected to exceed $1,000,000 (including all options or later phases of the same project). DRFPs shall invite comments from potential offerors on all aspects of the draft solicitation, including the requirements, schedules, proposal instructions, and evaluation approaches. Potential offerors should be specifically requested to identify unnecessary or inefficient requirements. If the DRFP contains Government-unique standards, potential offerors should be invited to identify voluntary consensus standards that meet the Government's requirements as alternatives to Government-unique standards cited as requirements, in accordance with FAR 11.101 and OMB Circular A-119. Comments should also be requested on any perceived safety, occupational health, security (including information technology security), environmental, export control, and/or other programmatic risk issues associated with performance of the work. When considered appropriate, the statement of work or the specifications may be issued in advance of other solicitation sections.

(B) Contracting officers shall plan the acquisition schedule to include adequate time for issuance of the DRFP, potential offeror review and comment, and NASA evaluation and disposition of the comments.

(C) When issuing DRFPs, potential offerors should be advised that the DRFP is not a solicitation and NASA is not requesting proposals.

(D) Whenever feasible, contracting officers should include a summary of the disposition of significant DRFP comments with the final RFP.

(E) If performance-based payments are planned to be used in a competitive negotiated acquisition, the DRFP shall request potential offerors to suggest terms, including performance events or payment criteria. Contracting officers shall use that information to establish a common set of performance-based payments parameters in the formal RFP when practicable.

(F) The procurement officer may waive the requirement for a DRFP upon written determination that the expected benefits will not be realized given the nature of the supply or service being acquired. The DRFP shall not be waived because of poor or inadequate planning.

(f)(i) Upon release of the formal RFP, the contracting officer shall direct all personnel associated with the acquisition to refrain from communicating with prospective offerors and to refer all inquiries to the contracting officer or other authorized representative. This procedure is commonly known as a "blackout notice" and shall not be imposed before release of the RFP. The notice may be issued in any format (e.g., letter or electronic) appropriate to the complexity of the acquisition.

(ii) Blackout notices are not intended to terminate all communication with offerors. Contracting officers should continue to provide information as long as it does not create an unfair competitive advantage or reveal proprietary data.

1815.203 Requests for proposals.

1815.203-70 Installation reviews.

(a) Installations shall establish procedures to review all RFPs before release. When appropriate given the complexity of the acquisition or the number of offices involved in solicitation review, centers should consider use of a single review meeting called a Solicitation Review Board (SRB) as a streamlined alternative to the serial or sequential coordination of the solicitation with reviewing offices. The SRB is a meeting in which all offices having review and approval responsibilities discuss the solicitation and their concerns. Actions assigned and changes required by the SRB shall be documented.

(b) When source evaluation board (SEB) procedures are used in accordance with 1815.370, the SEB shall review and approve the RFP prior to issuance.

1815.203-71 Headquarters reviews.

For RFPs requiring Headquarters review and approval, the procurement officer shall submit ten copies of the RFP to the Associate Administrator for Procurement (Code HS). Any significant information relating to the RFP or the planned evaluation methodology omitted from the RFP itself should also be provided.

1815.203-72 Risk management.

In all RFPs for supplies or services for which a technical proposal is required, proposal instructions shall require offerors to identify and discuss risk factors and issues throughout the proposal where they are relevant, and describe their approach to managing these risks.

1815.204 Contract format.

1815.204-2 Part I-The Schedule.

(c) To the maximum extent practicable, requirements should be defined as performance based specifications/statements of work that focus on required outcomes or results, not methods of performance or processes.

1815.204-5 Part IV-Representations and instructions.

(b) The information required in proposals should be kept to the minimum necessary for the source selection decision.

1815.204-70 Page limitations.

(a) Technical and contracting personnel will agree on page limitations for their respective portions of an RFP. Unless approved in writing by the procurement officer, the page limitation for the contracting portion of an RFP (all sections except Section C, Description/ specifications/work statement) shall not exceed 150 pages, and the page limitation for the technical portion (Section C) shall not exceed 200 pages. Attachments to the RFP count as part of the section to which they relate. In determining page counts, a page is defined as one side of a sheet, 8 1/2" x 11", with at least one inch margins on all sides, using not smaller than 12-point type. Foldouts count as an equivalent number of 8 1/2" x 11" pages. The metric standard format most closely approximating the described standard 8 1/2" x 11" size may also be used.

(b) Page limitations shall also be established for proposals submitted in competitive acquisitions. Accordingly, technical and contracting personnel will agree on page limitations for each portion of the proposal. Unless a different limitation is approved in writing by the procurement officer, the total initial proposal, excluding title pages, tables of content, and cost/price information, shall not exceed 500 pages using the page definition of 1815.204-70(a). Firm page limitations shall also be established for final proposal revisions, if requested. The appropriate page limitations for final proposal revisions should be determined by considering the complexity of the acquisition and the extent of any discussions. The same page limitations shall apply to all offerors. Pages submitted in excess of specified limitations will not be evaluated by the Government and will be returned to the offeror.

1815.207 Handling proposals and information.

1815.207-70 Release of proposal information.

(a) NASA personnel participating in any way in the evaluation may not reveal any information concerning the evaluation to anyone not also participating, and then only to the extent that the information is required in connection with the evaluation. When non-NASA personnel participate, they shall be instructed to observe these restrictions.

(b)(1) Except as provided in paragraph (b)(2) of this section, the procurement officer is the approval authority to disclose proposal information outside the Government. If outside evaluators are involved, this authorization may be granted only after compliance with FAR 37.2 and 1837.204, except that the determination of unavailability of Government personnel required by FAR 37.2 is not required for disclosure of proposal information to JPL employees.

(2) Proposal information in the following classes of proposals may be disclosed with the prior written approval of a NASA official one level above the NASA program official responsible for the overall conduct of the evaluation. If outside evaluators are involved, the determination of unavailability of Government personnel required by FAR 37.2 is not required for disclosure in these instances.

(i) Proposals submitted in response to broad agency announcements such as Announcements of Opportunity and NASA Research Announcements;

(ii) Unsolicited proposals; and

(iii) SBIR and STTR proposals.

(3) If JPL personnel, in evaluating proposal information released to them by NASA, require assistance from non-JPL, non-Government evaluators, JPL must obtain written approval to release the information in accordance with paragraphs (b)(1) and (b)(2) of this section.

1815.207-71 Appointing non-Government evaluators as special Government employees.

(a) Except as provided in paragraph (c) of this section, non-Government evaluators, except employees of JPL, shall be appointed as special Government employees.

(b) Appointment as a special Government employee is a separate action from the approval required by paragraph 1815.207-70(b) and may be processed concurrently. Appointment as a special Government employee shall be made by:

(1) the NASA Headquarters personnel office when the release of proposal information is to be made by a NASA Headquarters office; or

(2) the installation personnel office when the release of proposal information is to be made by the installation.

(c) Non-Government evaluators need not be appointed as special Government employees when they evaluate:

(1) Proposals submitted in response to broad agency announcements such as Announcements of Opportunity and NASA Research Announcements;

(2) Unsolicited proposals; and

(3) SBIR and STTR proposals.

1815.208 Submission, modification, revision, and withdrawal of proposals.

(b) The FAR late proposal criteria do not apply to Announcements of Opportunity (see 1872.705-1 paragraph VII), NASA Research Announcements (see 1852.235-72), and Small Business Innovative Research (SBIR) Phase I and Phase II solicitations, and Small Business Technology Transfer (STTR) solicitations. For these solicitations, proposals or proposal modifications received from qualified firms after the latest date specified for receipt may be considered if a significant reduction in cost to the Government is probable or if there are significant technical advantages, as compared with proposals previously received. In such cases, the project office shall investigate the circumstances surrounding the late submission, evaluate its content, and submit written recommendations and findings to the selection official or a designee as to whether there is an advantage to the Government in considering it. The selection official or a designee shall determine whether to consider the late submission.

1815.209 Solicitation provisions and contract clauses.

(a) The contracting officer shall insert FAR 52.215-1 in all competitive negotiated solicitations.

1815.209-70 NASA solicitation provisions.

(a) The contracting officer shall insert the provision at 1852.215-77, Preproposal/Pre-bid Conference, in competitive requests for proposals and invitations for bids where the Government intends to conduct a preproposal or pre-bid conference. Insert the appropriate specific information relating to the conference.

(b) The contracting officer shall insert the clause at 1852.214-71, Grouping for Aggregate Award, in solicitations when it is in the Government's best interest not to make award for less than specified quantities solicited for certain items or groupings of items. Insert the item numbers and/or descriptions applicable for the particular acquisition.

(c) The contracting officer shall insert the clause at 1852.214-72, Full Quantities, in solicitations when award will be made only on the full quantities solicited.

(d) The contracting officer shall insert the provision at 1852.215-81, Proposal Page Limitations, in all competitive requests for proposals.

Subpart 1815. 3--Source Selection

1815.300 Scope of subpart.

1815.300-70 Applicability of subpart.

(a)(1) Except as indicated in paragraph (b) of this section, NASA competitive negotiated acquisitions shall be conducted as follows:

(i) Acquisitions of $50 million or more -- in accordance with FAR 15.3 and this subpart.

(ii) Other acquisitions -- in accordance with FAR 15.3 and this subpart except section 1815.370.

(2) Estimated dollar values of acquisitions shall include the values of multiple awards, options, and later phases of the same project.

(b) FAR 15. 3 and this subpart are not applicable to acquisitions conducted under the following procedures:

(1) MidRange (see Part 1871).

(2) Announcements of Opportunity (see Part 1872).

(3) NASA Research Announcements (see 1835.016-71).

(4) The Small Business Innovative Research (SBIR) program and the Small Business Technology Transfer (STTR) pilot program under the authority of the Small Business Act (15 U.S.C. 638).

(5) Architect and Engineering (A&E) services (see FAR 36.6 and 1836.6).

1815.303 Responsibilities.

(a) The SSA shall be established at the lowest reasonable level for each acquisition. Notwithstanding the FAR designation of the contracting officer as SSA, the SSA for center acquisitions shall be established in accordance with center procedures. For acquisitions designated as Headquarters selections, the SSA will be identified as part of the Master Buy Plan process (see 1807.71).

(b)(i) The source selection authority (SSA) is the Agency official responsible for proper and efficient conduct of the source selection process and for making the final source selection decision. The SSA has the following responsibilities in addition to those listed in the FAR:

(A) Approve the evaluation factors, subfactors, the weight of the evaluation factors and subfactors, and any special standards of responsibility (see FAR 9.104-2) before release of the RFP, or delegate this authority to appropriate management personnel;

(B) Appoint the source selection team. However, when the Administrator will serve as the SSA, the Official-in-Charge of the cognizant Headquarters Program Office will appoint the team; and

(C) Provide the source selection team with appropriate guidance and special instructions to conduct the evaluation and selection procedures.

(b)(2) Approval authorities for Acquisition Plans and Acquisition Strategy Meetings are in accordance with 1807.103.

1815.304 Evaluation factors and significant subfactors.

(c)(4)(A) The extent of participation of small disadvantaged business (SDB) concerns shall be evaluated as a subfactor under the Mission Suitability factor. If a Mission Suitability factor is not used, the SDB participation shall be evaluated as a separate factor or subfactor, as appropriate.

(B) SDB concerns that choose the FAR 19.11 price evaluation adjustment shall receive the lowest possible score/rating under the FAR 15.304(c)(4) evaluation.

1815.304-70 NASA evaluation factors.

(a) Typically, NASA establishes three evaluation factors: Mission Suitability, Cost/Price, and Past Performance. Evaluation factors may be further defined by subfactors. Evaluation subfactors should be structured to identify significant discriminators, or "key swingers" - the essential information required to support a source selection decision. Too many subfactors undermine effective proposal evaluation. All evaluation subfactors should be clearly defined to avoid overlap and redundancy.

(b) Mission Suitability factor.

(1) This factor indicates the merit or excellence of the work to be performed or product to be delivered. It includes, as appropriate, both technical and management subfactors. Mission Suitability shall be numerically weighted and scored on a 1000-point scale.

(2) The Mission Suitability factor may identify evaluation subfactors to further define the content of the factor. Each Mission Suitability subfactor shall be weighted and scored. The adjectival rating percentages in 1815.305(a)(3)(A) shall be applied to the subfactor weight to determine the point score. The number of Mission Suitability subfactors is limited to five. The Mission Suitability evaluation subfactors and their weights shall be identified in the RFP.

(3) For cost reimbursement acquisitions, the Mission Suitability evaluation shall also include the results of any cost realism analysis. The RFP shall notify offerors that the realism of proposed costs may significantly affect their Mission Suitability scores.

(4) If the solicitation requires the submission of a Safety and Health Plan (see 1823.7001(c) and NPG 8715.3, NASA Safety Manual, Appendix H), safety and health must be a consideration in the evaluation. For acquisitions valued at $10 million or more, or $25 million or more for commercial items, then the Mission Suitability factor, if used, shall include a subfactor for safety and health. Otherwise, use of that subfactor is optional.

(c) Cost/Price factor. This factor evaluates the reasonableness and, if necessary, the cost realism, of proposed costs/prices. The Cost/Price factor is not numerically weighted or scored.

(d) Past Performance factor.

(1) This factor indicates the relevant quantitative and qualitative aspects of each offeror's record of performing services or delivering products similar in size, content, and complexity to the requirements of the instant acquisition.

(2) The RFP shall instruct offerors to submit data (including data from relevant Federal, State, and local governments and private contracts) that can be used to evaluate their past performance. Typically, the RFP will require:

(i) A list of contracts similar in size, content, and complexity to the instant acquisition, showing each contract number, the type of contract, a brief description of the work, and a point of contact from the organization placing the contract. Normally, the requested contracts are limited to those received in the last three years. However, in acquisitions that require longer periods to demonstrate performance quality, such as hardware development, the time period should be tailored accordingly.

(ii) The identification and explanation of any cost overruns or underruns, completion delays, performance problems, and terminations.

(3) The contracting officer may start collecting past performance data before proposal receipt. One method for early evaluation of past performance is to request offerors to submit their past performance information in advance of the proposal due date. The RFP could also include a past performance questionnaire for offerors to send their previous customers with instructions to return the completed questionnaire to the Government. Failure of the offeror to submit its past performance information early or of the customers to submit the completed questionnaires shall not be a cause for rejection of the proposal nor shall it be reflected in the Government's evaluation of the offeror's past performance.

(4) The contracting officer shall evaluate the offeror's past performance in occupational health, security, safety, and mission success (e.g., mishap rates and problems in delivered hardware and software that resulted in mishaps or failures) when these areas are germane to the requirement.

1815.305 Proposal evaluation.

(a) Each proposal shall be evaluated to identify and document:

(i) Any deficiencies;

(ii) All strengths and significant weaknesses;

(iii) The numerical score and/or adjectival rating of each Mission Suitability subfactor and for the Mission Suitability factor in total;

(iv) Cost realism, if appropriate;

(v) The Past Performance evaluation factor; and

(vi) Any programmatic risk to mission success, e.g., technical, schedule, cost, safety, occupational health, security, export control, or environmental. Risks may result from the offeror's technical approach, manufacturing plan, selection of materials, processes, equipment, or as a result of the cost, schedule, and performance impacts associated with its approach. Risk evaluations must consider the probability of the risk occurring, the impact and severity of the risk, the timeframe when the risk should be addressed, and the alternatives available to meet the requirements. Risk assessments shall be considered in determining Mission Suitability strengths, weaknesses, deficiencies, and numerical or adjectival ratings. Identified risks and the potential for cost impact shall be considered in the cost or price evaluation.

(a)(1) Cost or price evaluation.

(A) Cost or pricing data shall not be requested in competitive acquisitions. See 1815.403-1(b)(1) and 1815.403-3(b).

(B) When contracting on a basis other than firm-fixed-price, the contracting officer shall perform price and cost realism analyses to assess the reasonableness and realism of the proposed costs. A cost realism analysis will determine if the costs in an offeror's proposal are realistic for the work to be performed, reflect a clear understanding of the requirements, and are consistent with the various elements of the offeror's technical proposal. The analysis should include:

(a) The probable cost to the Government of each proposal, including any recommended additions or reductions in materials, equipment, labor hours, direct rates, and indirect rates. The probable cost should reflect the best estimate of the cost of any contract which might result from that offeror's proposal.

(b) The differences in business methods, operating procedures, and practices as they affect cost.

(c) A level of confidence in the probable cost assessment for each proposal.

(C) The cost realism analysis may result in adjustments to Mission Suitability scores in accordance with the procedure described in 1815.305(a)(3)(B).

(a)(2) Past performance evaluation.

(A) The Past Performance evaluation assesses the contractor's performance under previously awarded contracts.

(B) The evaluation may be limited to specific areas of past performance considered most germane for the instant acquisition. It may include any or all of the items listed in FAR 42.1501, and/or any other aspects of past performance considered pertinent to the solicitation requirements or challenges. Regardless of the areas of past performance selected for evaluation, the same areas shall be evaluated for all offerors in that acquisition.

(C) Questionnaires and interviews may be used to solicit assessments of the offeror's performance, as either a prime or subcontractor, from the offeror's previous customers.

(D) All pertinent information, including customer assessments and any offeror rebuttals, will be made part of the source selection records and included in the evaluation.

(a)(3) Technical Evaluation.

(A) Mission Suitability subfactors and the total Mission Suitability factor shall be evaluated using the following adjectival ratings, definitions, and percentile ranges.

ADJECTIVAL RATING

DEFINITIONS

PERCENTILE RANGE

Excellent

A comprehensive and thorough proposal of exceptional merit with one or more significant strengths. No deficiency or significant weakness exists.

91-100

Very Good

A proposal having no deficiency and which demonstrates over-all competence. One or more significant strengths have been found, and strengths outbalance any weaknesses that exist.

71-90

Good

A proposal having no deficiency and which shows a reasonably sound response. There may be strengths or weaknesses, or both. As a whole, weaknesses not off-set by strengths do not significantly detract from the offeror's response.

51-70

Fair

A proposal having no deficiency and which has one or more weaknesses. Weaknesses outbalance any strengths.

31-50

Poor

A proposal that has one or more deficiencies or significant weaknesses that demonstrate a lack of overall competence or would require a major proposal revision to correct.

0-30

(B) When contracting on a cost reimbursement basis, the Mission Suitability evaluation shall reflect the results of any required cost realism analysis performed under the cost/price factor. A structured approach shall be used to adjust Mission Suitability scores based on the degree of assessed cost realism. An example of such an approach would:

(a) Establish a threshold at which Mission Suitability adjustments would start. The threshold should reflect the acquisition's estimating uncertainty (i.e., the higher the degree of estimating uncertainty, the higher the threshold);

(b) Use a graduated scale that proportionally adjusts a proposal's Mission Suitability score for its assessed cost realism;

(c) Affect a significant number of points to induce realistic pricing.

(d) Calculate a Mission Suitability point adjustment based on the percentage difference between proposed and probable cost as follows:

Services

Hardware Development

Point Adjustment

+/- 5 percent

+/- 30 percent

0

+/- 6 to 10 percent

+/- 31 to 40 percent

-50

+/- 11 to 15 percent

+/- 41 to 50 percent

-100

+/- 16 to 20 percent

+/- 51 to 60 percent

-150

+/- 21 to 30 percent

+/- 61 to 70 percent

-200

+/- more than 30 percent

+/- more than 70 percent

-300

(a)(4) The cost or price evaluation, specifically the cost realism analysis, often requires a technical evaluation of proposed costs. Contracting officers may provide technical evaluators a copy of the cost volume or relevant information from it to use in the analysis.

(b) The contracting officer is authorized to make the determination to reject all proposals received in response to a solicitation.

1815.305-70 Identification of unacceptable proposals.

(a) The contracting officer shall not complete the initial evaluation of any proposal when it is determined that the proposal is unacceptable because:

(1) It does not represent a reasonable initial effort to address the essential requirements of the RFP or clearly demonstrates that the offeror does not understand the requirements;

(2) In research and development acquisitions, a substantial design drawback is evident in the proposal, and sufficient correction or improvement to consider the proposal acceptable would require virtually an entirely new technical proposal; or

(3) It contains major deficiencies or omissions or out-of-line costs which discussions with the offeror could not reasonably be expected to cure.

(b) The contracting officer shall document the rationale for discontinuing the initial evaluation of a proposal in accordance with this section.

1815.305-71 Evaluation of a single proposal.

(a) If only one proposal is received in response to the solicitation, the contracting officer shall determine if the solicitation was flawed or unduly restrictive and determine if the single proposal is an acceptable proposal. Based on these findings, the SSA shall direct the contracting officer to:

(1) Award without discussions provided the contracting officer determines that adequate price competition exists (see FAR 15.403-1(c)(1)(ii));

(2) Award after negotiating an acceptable contract. (The requirement for submission of cost or pricing data shall be determined in accordance with FAR 15.403-1); or

(3) Reject the proposal and cancel the solicitation.

(b) The procedure in 1815.305-71(a) also applies when the number of proposals equals the number of awards contemplated or when only one acceptable proposal is received.

1815.306 Exchanges with offerors after receipt of proposals.

(c)(2) A total of no more than three proposals shall be a working goal in establishing the competitive range. Field installations may establish procedures for approval of competitive range determinations commensurate with the complexity or dollar value of an acquisition.

(d)(3)(A) The contracting officer shall identify any cost/price elements that do not appear to be justified and encourage offerors to submit their most favorable and realistic cost/price proposals, but shall not discuss, disclose, or compare cost/price elements of any other offeror. The contracting officer should question inadequate, conflicting, unrealistic, or unsupported cost information; differences between the offeror's proposal and most probable cost assessments; cost realism concerns; differences between audit findings and proposed costs; proposed rates that are too high/low; and labor mixes that do not appear responsive to the requirements. No agreement on cost/price elements or a "bottom line " is necessary.

(B) The contracting officer shall discuss contract terms and conditions so that a "model" contract can be sent to each offeror with the request for final proposal revisions. If the solicitation allows, any proposed technical performance capabilities above those specified in the RFP that have value to the Government and are considered proposal strengths should be discussed with the offeror and proposed for inclusion in that offeror's "model" contract. If the offeror declines to include these strengths in its "model" contract, the Government evaluators should reconsider their characterization as strengths.

(e)(1) In no case shall the contracting officer relax or amend RFP requirements for any offeror without amending the RFP and permitting the other offerors an opportunity to propose against the relaxed requirements.

1815.307 Proposal revisions.

(b)(i) The request for final proposal revisions (FPRs) shall also:

(A) Instruct offerors to incorporate all changes to their offers resulting from discussions, and require clear traceability from initial proposals;

(B) Require offerors to complete and execute the "model" contract, which includes any special provisions or performance capabilities the offeror proposed above those specified in the RFP;

(C) Caution offerors against unsubstantiated changes to their proposals; and

(D) Establish a page limit for FPRs.

(ii) Approval of the Associate Administrator for Procurement (Code HS) is required to reopen discussions for acquisitions of $50 million or more. Approval of the procurement officer is required for all other acquisitions.

(iii) Proposals are rescored based on FPR evaluations. Scoring changes between initial and FPRs shall be clearly traceable.

1815.308 Source selection decision.

(1) All significant evaluation findings shall be fully documented and considered in the source selection decision. A clear and logical audit trail shall be maintained for the rationale for ratings and scores, including a detailed account of the decisions leading to the selection. Selection is made on the basis of the evaluation criteria established in the RFP.

(2) Before award, the SSA shall sign a source selection statement that clearly and succinctly justifies the selection. Source selection statements must describe: the acquisition; the evaluation procedures; the substance of the Mission Suitability evaluation; and the evaluation of the Cost/Price and Past Performance factors. The statement also addresses unacceptable proposals, the competitive range determination, late proposals, or any other considerations pertinent to the decision. The statement shall not reveal any confidential business information. Except for certain major system acquisition competitions (see 1815.506-70), source selection statements shall be releasable to competing offerors and the general public upon request. The statement shall be available to the Debriefing Official to use in postaward debriefings of unsuccessful offerors and shall be provided to debriefed offerors upon request.

(3) Once the selection decision is made, the contracting officer shall award the contract.

1815.370 NASA source evaluation boards.

(a) The source evaluation board (SEB) procedures shall be used for those acquisitions identified in 1815.300-70(a)(1)(i).

(b) The SEB assists the SSA by providing expert analyses of the offerors' proposals in relation to the evaluation factors and subfactors contained in the solicitation. The SEB will prepare and present its findings to the SSA, avoiding trade-off judgments among either the individual offerors or among the evaluation factors. The SEB will not make recommendations for selection to the SSA.

(c) Designation.

(1) The SEB shall be comprised of competent individuals fully qualified to identify the strengths, weaknesses, and risks associated with proposals submitted in response to the solicitation. The SEB shall be appointed as early as possible in the acquisition process, but not later than acquisition plan or acquisition strategy meeting approval.

(2) While SEB participants are normally drawn from the cognizant installation, personnel from other NASA installations or other Government agencies may participate. When it is necessary to disclose the proposal (in whole or in part) outside the Government, approval shall be obtained in accordance with 1815.207-70.

(3) When Headquarters retains SSA authority, the Headquarters Office of Procurement (Code HS) must concur on the SEB appointments. Qualifications of voting members, including functional title, grade level, and related SEB experience, shall be provided.

(d) Organization.

(1) The organization of an SEB is tailored to the requirements of the particular acquisition. This can range from the simplest situation, where the SEB conducts the evaluation and fact-finding without the use of committees or panels/consultants (as described in paragraphs (d)(4) and (5) of this section) to a highly complex situation involving a major acquisition where two or more committees are formed and these, in turn, are assisted by special panels or consultants in particular areas. The number of committees or panels/consultants shall be kept to a minimum.

(2) The SEB Chairperson is the principal operating executive of the SEB. The Chairperson is expected to manage the team efficiently without compromising the validity of the findings provided to the SSA as the basis for a sound selection decision.

(3) The SEB Recorder functions as the principal administrative assistant to the SEB Chairperson and is principally responsible for logistical support and recordkeeping of SEB activities.

(4) An SEB committee functions as a factfinding arm of the SEB, usually in a broad grouping of related disciplines (e.g., technical or management). The committee evaluates in detail each proposal, or portion thereof, assigned by the SEB in accordance with the approved evaluation factors and subfactors and summarizes its evaluation in a written report to the SEB. The committee will also respond to requirements assigned by the SEB, including further justification or reconsideration of its findings. Committee chairpersons shall manage the administrative and procedural matters of their committees.

(5) An SEB panel or consultant functions as a factfinding arm of the committee in a specialized area of the committee's responsibilities. Panels are established or consultants named when a particular area requires deeper analysis than the committee can provide.

(6) The total of all such evaluators (committees, panels, consultants, etc. excluding SEB voting members and ex officio members) shall be limited to a maximum of 20, unless approved in writing by the procurement officer.

(e) Voting members.

(1) Voting members of the SEB shall include people who will have key assignments on the project to which the acquisition is directed. However, it is important that this should be tempered to ensure objectivity and to avoid an improper balance. It may even be appropriate to designate a management official from outside the project as SEB Chairperson.

(2) Non-government personnel shall not serve as voting members of an SEB.

(3) The SEB shall review the findings of committees, panels, or consultants and use its own collective judgment to develop the SEB evaluation findings reported to the SSA. All voting members of the SEB shall have equal status as rating officials.

(4) SEB membership shall be limited to a maximum of 7 voting individuals. Wherever feasible, an assignment to SEB membership as a voting member shall be on a full-time basis. When not feasible, SEB membership shall take precedence over other duties.

(5) The following people shall be voting members of all SEBs:

(i) Chairperson.

(ii) A senior, key technical representative for the project.

(iii) An experienced procurement representative.

(iv) A senior Safety & Mission Assurance (S&MA) representative, as appropriate.

(v) Committee chairpersons (except where this imposes an undue workload).

(f) Ex officio members.

(1) The number of nonvoting ex officio (advisory) members shall be kept as small as possible. Ex officio members should be selected for the experience and expertise they can provide to the SEB. Since their advisory role may require access to highly sensitive SEB material and findings, ex officio membership for persons other than those identified in paragraph (f)(3) of this section is discouraged.

(2) Nonvoting ex officio members may state their views and contribute to the discussions in SEB deliberations, but they may not participate in the actual rating process. However, the SEB recorder should be present during rating sessions.

(3) For field installation selections, the following shall be nonvoting ex officio members on all SEBs:

(i) Chairpersons of SEB committees, unless designated as voting members.

(ii) The procurement officer of the installation, unless designated a voting member.

(iii) The contracting officer responsible for the acquisition, unless designated a voting member.

(iv) The Chief Counsel and/or designee of the installation.

(v) The installation small business specialist.

(vi) The SEB recorder.

(g) Evaluation.

(1) If committees are used, the SEB Chairperson shall send them the proposals or portions thereof to be evaluated, along with instructions regarding the expected function of each committee, and all data considered necessary or helpful.

(2) While oral reports may be given to the SEB, each committee shall submit a written report which should include the following:

(i) Copies of individual worksheets and supporting comments to the lowest level evaluated;

(ii) An evaluation sheet summarized for the committee as a whole; and

(iii) A statement for each proposal describing any strengths, deficiencies, or significant weaknesses which significantly affected the evaluation and stating any reservations or concerns, together with supporting rationale, which the committee or any of its members want to bring to the attention of the SEB.

(3) The SEB process must be adequately documented. Clear traceability must exist at all levels of the SEB process. All reports submitted by committees or panels will be retained as part of the SEB records.

(4) Each voting SEB member shall thoroughly review each proposal and any committee reports and findings. The SEB shall rate or score the proposals for each evaluation factor and subfactor according to its own collective judgment. SEB minutes shall reflect this evaluation process.

(h) SEB presentation.

(1) The SEB Chairperson shall brief the SSA on the results of the SEB deliberations to permit an informed and objective selection of the best source(s) for the particular acquisition.

(2) The presentation shall focus on the significant strengths, deficiencies, and significant weaknesses found in the proposals, the probable cost of each proposal, and any significant issues and problems identified by the SEB. This presentation must explain any applicable special standards of responsibility; evaluation factors and subfactors; the significant strengths and significant weaknesses of the offerors; the Government cost estimate, if applicable; the offerors' proposed cost/price; the probable cost; the proposed fee arrangements; and the final adjectival ratings and scores to the subfactor level.

(3) Attendance at the presentation is restricted to people involved in the selection process or who have a valid need to know. The designated individuals attending the SEB presentation(s) shall:

(i) Ensure that the solicitation and evaluation processes complied with all applicable agency policies and that the presentation accurately conveys the SEB's activities and findings;

(ii) Not change the established evaluation factors, subfactors, weights, or scoring systems; or the substance of the SEB's findings. They may, however, advise the SEB to rectify procedural omissions, irregularities or inconsistencies, substantiate its findings, or revise the presentation.

(4) The SEB recorder will coordinate the formal presentation including arranging the time and place of the presentation, assuring proper attendance, and distributing presentation material.

(5) For Headquarters selections, the Headquarters Office of Procurement (Code HS) will coordinate the presentation, including approval of attendees. When the Administrator is the SSA, a preliminary presentation should be made to the center director and to the Official-in-Charge of the cognizant Headquarters Program Office.

(i) Recommended SEB presentation format.

(1) Identification of the Acquisition. Identifies the installation, the nature of the services or hardware to be acquired, some quantitative measure including the Government cost estimate for the acquisition, and the planned contractual arrangement. Avoids detailed objectives of the acquisition.

(2) Background. Identifies any earlier phases of a phased acquisition or, as in the case of continuing support services, identifies the incumbent and any consolidations or proposed changes from the existing structure.

(3) Evaluation Factors and Subfactors. Explains the evaluation factors, subfactors, and any special standards of responsibility. Lists the relative order of importance of the evaluation factors and the numerical weights of the Mission Suitability subfactors. Presents the adjectival scoring system used in the Mission Suitability and Past Performance evaluations.

(4) Sources. Indicates the number of offerors solicited and the number of offerors expressing interest (e.g., attendance at a preproposal conference). Identifies the offerors submitting proposals, indicating any small businesses, small disadvantaged businesses, and women-owned businesses.

(5) Summary of Findings. Lists the initial and final Mission Suitability ratings and scores, the offerors' proposed costs/prices, and any assessment of the probable costs. Introduces any clear discriminator, problem, or issue which could affect the selection. Addresses any competitive range determination.

(6) Significant Strengths, Deficiencies, and Significant Weaknesses of Offerors. Summarizes the SEB's findings, using the following guidelines:

(i) Present only the significant strengths, deficiencies, and significant weaknesses of individual offerors.

(ii) Directly relate the significant strengths, deficiencies, and significant weaknesses to the evaluation factors and subfactors.

(iii) Indicate the results and impact, if any, of discussions and FPRs on ratings and scores.

(7) Final Mission Suitability Ratings and Scores. Summarizes the evaluation subfactors, the maximum points achievable, and the scores of the offerors in the competitive range.

(8) Final Cost/Price Evaluation. Summarizes proposed costs/prices and any probable costs associated with each offeror including proposed fee arrangements. Presents the data as accurately as possible, showing SEB adjustments to achieve comparability. Identifies the SEB's confidence in the probable costs of the individual offerors, noting the reasons for low or high confidence.

(9) Past Performance. Reflects the summary conclusions, supported by specific case data.

(10) Special Interest. Includes only information of special interest to the SSA that has not been discussed elsewhere, e.g., procedural errors or other matters that could affect the selection decision.

(j) A source selection statement shall be prepared in accordance with 1815.308. For installation selections, the installation Chief Counsel or designee will prepare the source selection statement. For Headquarters selections, the Office of General Counsel or designee will prepare the statement.

Subpart 1815.4--Contract Pricing

1815.403 Obtaining cost or pricing data.

1815.403-1 Prohibition on obtaining cost or pricing data.

(b)(1) The adequate price competition exception is applicable to both fixed-price and cost-reimbursement type acquisitions. Contracting officers shall assume that all competitive acquisitions qualify for this exception.

(c)(4) Waivers of the requirement for submission of cost or pricing data shall be prepared in accordance with FAR 1.704. A copy of each waiver shall be sent to the Headquarters Office of Procurement (Code HK).

1815.403-170 Waivers of cost or pricing data.

(a) NASA has waived the requirement for the submission of cost or pricing data when contracting with the Canadian Commercial Corporation (CCC). This waiver applies to the CCC and its subcontractors. The CCC will provide assurance of the fairness and reasonableness of the proposed price. This assurance should be relied on; however, contracting officers shall ensure that the appropriate level of information other than cost or pricing data is submitted by subcontractors to support any required proposal analysis, including a technical analysis and a cost realism analysis. The CCC also will provide for follow-up audit activity to ensure that any excess profits are found and refunded to NASA.

(b) NASA has waived the requirement for the submission of cost or pricing data when contracting for Small Business Innovation Research (SBIR) program Phase II contracts. However, contracting officers shall ensure that the appropriate level of information other than cost or pricing data is submitted to determine price reasonableness and cost realism.

1815.403-3 Requiring information other than cost or pricing data.

(b) As indicated in 1815.403-1(b)(1), the adequate price competition exception applies to all competitive acquisitions. For other than firm-fixed price competitions, only the minimum information other than cost or pricing data necessary to ensure price reasonableness and assess cost realism should be requested. For firm-fixed price competitions, the contracting officer shall not request any cost information, except as required by FAR 22.1103, unless proposed prices appear unreasonable or unrealistically low given the offeror's proposed approach and there are concerns that the contractor may default.

1815.403-4 Requiring cost or pricing data.

(b)(2) If a certificate of current cost or pricing data is made applicable as of a date other than the date of price agreement, the agreed date should generally be within two weeks of the date of that agreement.

1815.404 Proposal analysis.

1815.404-2 Information to support proposal analysis.

(a)(1)(A) A field pricing report consists of a technical report and an audit report by the cognizant contract audit activity. Contracting officers should request a technical report from the ACO only if NASA resources are not available.

(B) When the required participation of the ACO or auditor involves merely a verification of information, contracting officers should obtain this verification from the cognizant office by telephone rather than formal request of field pricing support.

(C) When the cost proposal is for a product of a follow-on nature, contracting officers shall ensure that the following items, at a minimum are considered: actuals incurred under the previous contract, learning experience, technical and production analysis, and subcontract proposal analysis. This information may be obtained through NASA resources or the cognizant DCMC ACO or DCAA.

(D) Requests for field pricing assistance may be made on NASA Form 1434, Letter of Request for Pricing-Audit-Technical Evaluation Services.

1815.404-4 Profit.

(b)(1)(i)(a) The NASA structured approach for determining profit or fee objectives, described in 1815.404-471 shall be used to determine profit or fee objectives in the negotiation of contracts greater than or equal to $100,000 that use cost analysis and are:

(1) Awarded on the basis of other than full and open competition (see FAR 6.3);

(2) Awarded under NASA Research Announcements (NRAs) and Announcements of Opportunity (AO's); or

(3) Awarded under the Small Business Innovative Research (SBIR) or the Small Business Technology Transfer Research (STTR) programs.

(b) The rate calculated for the basic contract may only be used on actions under a negotiated contract when the conditions affecting profit or fee do not change.

(c) Although specific agreement on the applied weights or values for individual profit or fee factors shall not be attempted, the contracting officer may encourage the contractor to -

(1) Present the details of its proposed profit amounts in the structured approach format or similar structured approach; and

(2) Use the structured approach method in developing profit or fee objectives for negotiated subcontracts.

(ii) The use of the NASA structured approach for profit or fee is not required for:

(a) Architect-engineer contracts;

(b) Management contracts for operation and/or maintenance of Government facilities;

(c) Construction contracts;

(d) Contracts primarily requiring delivery of materials supplied by subcontractors;

(e) Termination settlements; and

(f) Contracts having unusual pricing situations when the procurement officer determines in writing that the structured approach is unsuitable.

(c)(2) Contracting officers shall document the profit or fee analysis in the contract file.

1815.404-470 NASA Form 634.

NASA Form (NF) 634 shall be used in performing the analysis necessary to develop profit or fee objectives.

1815.404-471 NASA structured approach for profit or fee objective.

1815.404-471-1 General.

(a) The structured approach for determining profit or fee objectives (NF 634) focuses on three profit factors:

(1) Performance risk;

(2) Contract type risk including working capital adjustment; and

(3) Other Considerations which may be considered by the contracting officer to account for special circumstances that are not adequately addressed in the performance risk and contract type risk factors.

(b) The contracting officer assigns values to each profit or fee factor; the value multiplied by the base results in the profit/fee objective for that factor. Each factor has a normal value and a designated range of values. The normal value is representative of average conditions on the prospective contract when compared to all goods and services acquired by NASA. The designated range provides values based on above normal or below normal conditions. Values outside the designated range must not be used. In the negotiation documentation, the contracting officer need not explain assignment of the normal value, but must address conditions that justify assignment of other than the normal value.

1815.404-471-2 Performance risk.

(a) Risk Factors. Performance risk addresses the contractor's degree of risk in fulfilling the contract requirements. It consists of three risk factors:

(1) Technical - the technical uncertainties of performance;

(2) Management - the degree of management effort necessary to ensure that contract requirements are met; and

(3) Cost control - the contractor's efforts to reduce and control costs.

(b) Risk factor weighting, values and calculations. A weighting and value is assigned to each of the risk factors to determine a profit/fee objective.

(c) Values. The normal value is 6 percent and the designated range is 4 percent to 8 percent.

(d) Evaluation criteria for technical risk factor.

(1) In determining the appropriate value for the technical risk factor, the contracting officer shall review the contract requirements and focus on the critical performance elements in the statement of work or specifications. Contracting officers shall consider the -

(i) Technology being applied or developed by the contractor;

(ii) Technical complexity;

(iii) Program maturity;

(iv) Performance specifications and tolerances;

(v) Delivery schedule; and

(vi) Extent of a warranty or guarantee.

(2) Above normal conditions indicating substantial technical risk.

(i) The contracting officer may assign a higher than normal value in those cases where there is a substantial technical risk, such as when -

(A) The contractor is either developing or applying advanced technologies;

(B) Items are being manufactured using specifications with stringent tolerance limits;

(C) The efforts require highly skilled personnel or require the use of state-of-the-art machinery;

(D) The services or analytical efforts are extremely important to the government and must be performed to exacting standards;

(E) The contractor's independent development and investment has reduced the Government's risk or cost;

(F) The contractor has accepted an accelerated delivery schedule to meet the Government's requirements; or

(G) The contractor has assumed additional risk through warranty provisions.

(ii) The contracting officer may assign a value significantly above normal. A maximum value may be assigned when the effort involves-

(A) Extremely complex, vital efforts to overcome difficult technical obstacles that require personnel with exceptional abilities, experience, and professional credentials;

(B) Development or initial production of a new item, particularly if performance or quality specifications are tight; or

(C) A high degree of development or production concurrency.

(3) Below normal conditions indicating lower than normal technical risk.

(i) The contracting officer may assign a lower than normal value in those cases where the technical risk is low, such as when the -

(A) Acquisition is for off-the-shelf items;

(B) Requirements are relatively simple;

(C) Technology is not complex;

(D) Efforts do not require highly skilled personnel;

(E) Efforts are routine; or

(F) Acquisition is a follow-on effort or a repetitive type acquisition.

(ii) The contracting officer may assign a value significantly below normal. A minimum value may be justified when the effort involves -

(A) Routine services;

(B) Production of simple items;

(C) Rote entry or routine integration of Government-furnished information; or

(D) Simple operations with Government-furnished property.

(e) Evaluation criteria for management risk factor.

(1) In determining the appropriate value for the management risk factor, the contracting officer shall review the contract requirements and focus on the critical performance elements in the statement of work or specifications. Contracting officers shall -

(i) Assess the contractor's management and internal control systems using contracting office information and reviews made by contract administration offices;

(ii) Assess the management involvement expected on the prospective contract action; and

(iii) Consider the degree of cost mix as an indication of the types of resources applied and value added by the contractor.

(2) Above normal conditions indicating substantial management risk.

(i) The contracting officer may assign a higher than normal value when the management effort is intense, such as when -

(A) The contractor's value added is both considerable and reasonably difficult; or

(B) The effort involves a high degree of integration and coordination.

(ii) The contracting officer may justify a maximum value when the effort -

(A) Requires large-scale integration of the most complex nature;

(B) Involves major international activities with significant management coordination; or

(C) Has critically important milestones.

(3) Below normal conditions indicating lower than normal management risk.

(i) The contracting officer may assign a lower than normal value when the management effort is minimal, such as when -

(A) The program is mature and many end item deliveries have been made;

(B) The contractor adds minimum value to an item;

(C) The efforts are routine and require minimal supervision;

(D) The contractor fails to provide an adequate analysis of subcontractor costs; or

(E) The contractor does not cooperate in the evaluation and negotiation of the proposal.

(ii) The contracting officer may assign a value significantly below normal. A minimum value may be assigned when -

(A) Reviews performed by the field administration offices disclose unsatisfactory management and internal control systems (e.g., quality assurance, property control, safety, security); or

(B) The effort requires an unusually low degree of management involvement.

(f) Evaluation criteria for cost control risk factor.

(1) In determining the appropriate value for the cost control risk factor, the contracting officer shall -

(i) Evaluate the expected reliability of the contractor's cost estimates (including the contractor's cost estimating system);

(ii) Evaluate the contractor's cost reduction initiatives (e.g., competition advocacy programs);

(iii) Assess the adequacy of the contractor's management approach to controlling cost and schedule; and

(iv) Evaluate any other factors that affect the contractor's ability to meet the cost targets (e.g., foreign currency exchange rates and inflation rates).

(2) Above normal conditions indicating substantial cost control risk.

(i) The contracting officer may assign a value higher than normal value if the contractor can demonstrate a highly effective cost control program, such as when -

(A) The contractor has an aggressive cost reduction program that has demonstrable benefits;

(B) The contractor uses a high degree of subcontract competition; or

(C) The contractor has a proven record of cost tracking and control.

(3) Below normal conditions indicating lower than normal cost control risk.

(i) The contracting officer may assign a lower than normal value in those cases where the contractor demonstrates minimal concern for cost control, such as when -

(A) The contractor's cost estimating system is marginal;

(B) The contractor has made minimal effort to initiate cost reduction programs;

(C) The contractor's cost proposal is inadequate; or

(D) The contractor has a record of cost overruns or the indication of unreliable cost estimates and lack of cost control.

1815.404-471-3 Contract type risk and working capital adjustment.

(a) Risk factors. The contract type risk factor focuses on the degree of cost risk accepted by the contractor under varying contract types. The working capital adjustment is an adjustment added to the profit objective for contract type risk. It applies to fixed-price type contracts that provide for progress payments. Though it uses a formula approach, it is not intended to be an exact calculation of the cost of working capital. Its purpose is to give general recognition to the contractor's cost of working capital under varying contract circumstances, financing policies, and the economic environment. This adjustment is limited to a maximum of 2 percent.

(b) Risk factor values and calculations. A risk value is assigned to calculate the profit or fee objective for contract type. A contract length factor is assigned and applied to costs financed when a working capital adjustment is appropriate. This calculation is only performed when the prospective contract is a fixed-price contract containing provisions for progress payments.

(c) Values: Normal and designated ranges.

Contract Type

Notes

Normal Value (Percent)

Designated Range (Percent)

Firm-fixed-price, no financing

(1)

5

4 to 6

Firm-fixed-price with performance-based payments

(6)

4

2.5 to 5.5

Firm-fixed-price with progress payments

(2)

3

2 to 4

Fixed-price-incentive, no financing

(1)

3

2 to 4

Fixed-price-incentive, with performance-based payments

(6)

2

.5 to 3.5

Fixed-price, redeterminable

(3)

--

--

Fixed-price-incentive, with progress payments

(2)

1

0 to 2

Cost-plus-incentive-fee

(4)

1

0 to 2

Cost-plus-award fee

(4)

.75

.5 to 1.5

Cost-plus-fixed fee

(4)

.5

0 to 1

Time-and-materials

(5)

.5

0 to 1

Labor-hour

(5)

.5

0 to 1

Firm-fixed-price, level-of-effort, term

(5)

.5

0 to 1

 

(1) "No financing," means that the contract either does not provide progress or performance based payments, or provides them only on a limited basis. Do not compute a working capital adjustment

(2) When progress payments are present, compute a working capital adjustment.

(3) For purposes of assigning profit values, treat a fixed-price redeterminable contract as if it were a fixed-price-incentive contract with below normal provisions.

(4) Cost-plus contracts shall not receive the working capital adjustment.

(5) These types of contracts are considered cost-plus-fixed-fee contracts for the purposes of assigning profit values. Do not compute the working capital adjustment. However, higher than normal values may be assigned within the designated range to the extent that portions of cost are fixed.

(6) When performance-based payments are used, do not compute a working capital adjustment.

(d) Evaluation criteria.

(1) General. The contracting officer shall consider elements that affect contract type risk such as -

(i) Length of contract;

(ii) Adequacy of cost projection data;

(iii) Economic environment;

(iv) Nature and extent of subcontracted activity;

(v) Protection provided to the contractor under contract provisions (e.g., economic price adjustment clauses);

(vi) The ceilings and share lines contained in the incentive provisions; and

(vii) The rate, frequency, and risk to the contractor of performance-based payments, if provided.

(2) Mandatory. The contracting officer shall assess the extent to which costs have been incurred prior to definitization of the contract. When costs have been incurred prior to definitization, generally regard the contract type risk to be in the low end of the designated range. If a substantial portion of the costs have been incurred prior to definitization, the contracting officer may assign a value as low as 0 percent regardless of contract type.

(3) Above normal conditions. The contracting officer may assign a higher than normal value when there is substantial contract type risk. Conditions indicating higher than normal contract type risk are -

(i) Efforts where there is minimal cost history;

(ii) Long-term contracts without provisions protecting the contractor, particularly when there is considerable economic uncertainty;

(iii) Incentive provisions that place a high degree of risk on the contractor;

(iv) Performance-based payments totaling less than the maximum allowable amount(s) specified at FAR 32.1004(b)(2); or

(v) An aggressive performance-based payment schedule that increases risk.

(4) Below normal conditions. The contracting officer may assign a lower than normal value when the contract type risk is low. Conditions indicating lower than normal contract type risk are:

(i) Very mature product line with extensive cost history;

(ii) Relatively short-term contracts;

(iii) Contractual provisions that substantially reduce the contractor's risk, e.g. economic price adjustment provisions; and

(iv) Incentive provisions that place a low amount of risk on the contractor.

(v) A performance-based payment schedule that is routine with minimal risk.

(e) Costs financed.

(1) Costs financed equal the total costs multiplied by the percent of costs financed by the contractor.

(2) Total costs may be reduced as appropriate when -

(i) The contractor has little cash investment (e.g., subcontractor progress payments are liquidated late in the period of performance);

(ii) Some costs are covered by special funding arrangements, such as advance payments;

(3) The portion financed by the contractor is generally the portion not covered by progress payments. (i.e. - for progress payments: 100 percent minus the customary progress payments rate. For example, if a contractor receives progress payments at 75 percent, the portion financed by the contractor is 25 percent. On contracts that provide progress payments to small business, use the customary progress payment rate for large businesses.)

(f) Contract length factor.

(1) This is the period of time that the contractor has a working capital investment in the contract. It -

(i) Is based on the time necessary for the contractor to complete the substantive portion of the work;

(ii) Is not necessarily the period of time between contract award and final delivery, as periods of minimal effort should be excluded;

(iii) Should not include periods of performance contained in option provisions when calculating the objective for the base period; and

(iv) Should not, for multiyear contracts, include periods of performance beyond that required to complete the initial year's requirements.

(2) The contracting officer -

(i) Should use the following to select the contract length factor:

Period to perform substantive portion (in months)

Contract length factor

21 or less ...

.40

22 to 27 ...

.65

28 to 33 ...

.90

34 to 39 ...

1.15

40 or more ...

1.40

 

(ii) Should develop a weighted average contract length when the contract has multiple deliveries; and

(iii) May use sampling techniques provided they produce a representative result.

(3) Example: A prospective contract has a performance period of 40 months with end items being delivered in the 34th, 36th, 38th and 40th months of the contract. The average period is 37 months and the contract length factor is 1.15.

1815.404-471-4 Other considerations.

(a) Other Considerations may be included by the contracting officer to account for special circumstances, such as contractor efficiencies or unusual acceptance of contractual or program risks that are not adequately addressed in the structured approach calculations described in 1815.404-471-2 or 1815.404-471-3. The total adjustment resulting from Other Considerations may be positive or negative but in no case should the total adjustment exceed + / - 5 percent.

(b) The contracting officer shall analyze and verify information provided by the contractor that demonstrates that the special circumstances being recognized under this section -

(1) Provide substantial benefits to the Government under the contract and/or overall program;

(2) Have not been recognized in the structured approach calculations; and

(3) Represent unusual and innovative actions or acceptance of risk by the contractor.

(c) Examples of special circumstances include, but are not limited to the following:

(1) Consistent demonstration by the contractor of excellent past performance within the last three years, with a special emphasis on excellence in safety, may merit an upward adjustment of as much as 1 percent. Similarly, an assessment of poor past performance, especially in the area of safety, may merit a downward adjustment of as much -1 percent. This consideration is especially important when negotiating modifications or changes to an ongoing contract.

(2) Extraordinary steps to achieve the Government's socio-economic goals, environmental goals, and public policy goals established by law or regulation that are sufficiently unique or unusual may merit an upward adjustment of as much as .5 percent. Similarly, for non-participation in or violation of Federal programs, the contracting officer may adjust the objective by as much as -.5 percent. However, this consideration does not apply to the utilization of small disadvantaged businesses. Incentives for use of these firms may only be structured according to FAR 19.1203 and 19.1204(c).

(3) Consideration of up to 1 percent should be given when contract performance requires the expenditure of significant corporate capital resources.

(4) Unusual requests for use of government facilities and property may merit a downward adjustment of as much as - 1 percent.

(5) Cost efficiencies arising from innovative product design, process improvements, or integration of a life cycle cost approach for the design and development of systems that minimize maintenance and operations costs, that have not been recognized in Performance Risk or Contract Type Risk, may merit an upward adjustment. This factor is intended to recognize and reward improvements resulting from better ideas and management that will benefit the Government in the contract and/or program.

(d) Other considerations need not be limited to situations that increase profit/fee levels. A negative consideration may be appropriate when there is a significant expectation of near-term spin-off benefits as a direct result of the contract.

1815.404-471-5 Facilities capital cost of money.

(a) When facilities capital cost of money is included as an item of cost in the contractor's proposal, it shall not be included in the cost base for calculating profit/fee. In addition, a reduction in the profit/fee objective shall be made in the amount equal to the facilities capital cost of money allowed in accordance with FAR 31.205-10(a)(2) or 1 percent of the cost base, whichever is less.

(b) CAS 417, cost of money as an element of the cost of capital assets under construction, should not appear in contract proposals. These costs are included in the initial value of a facility for purposes of calculating depreciation under CAS 414.

1815.404-472 Payment of profit or fee under letter contracts.

NASA's policy is to pay profit or fee only on definitized contracts.

1815.406 Documentation.

1815.406-1 Prenegotiation objectives.

(b)(i) Before conducting negotiations requiring installation or Headquarters review, contracting officers or their representatives shall prepare a prenegotiation position memorandum setting forth the technical, business, contractual, pricing, and other aspects to be negotiated.

(ii) A prenegotiation position memorandum is not required for contracts awarded under the competitive negotiated procedures of FAR 15.3 and 1815.3.

1815.406-170 Content of the prenegotiation position memorandum.

The prenegotiation position memorandum (PPM) should fully explain the contractor and Government positions. Since the PPM will ultimately become the basis for negotiation, it should be structured to track to the price negotiation memorandum (see FAR 15.406-3 and 1815.406-3). In addition to the information described in FAR 15.406-1 and, as appropriate, 15.406-3(a), the PPM should address the following subjects, as applicable, in the order presented:

(a) Introduction. Include a description of the acquisition and a history of prior acquisitions for the same or similar items. Address the extent of competition and its results. Identify the contractor and place of performance (if not evident from the description of the acquisition). Document compliance with law, regulations and policy, including JOFOC, synopsis, EEO compliance, and current status of contractor systems (see FAR 15.406-3(a)(4)). In addition, the negotiation schedule should be addressed and the Government negotiation team members identified by name and position.

(b) Type of contract contemplated. Explain the type of contract contemplated and the reasons for its suitability.

(c) Special features and requirements. In this area, discuss any special features (and related cost impact) of the acquisition, including such items as--

(1) Letter contract or precontract costs authorized and incurred;

(2) Results of preaward survey;

(3) Contract option requirements;

(4) Government property to be furnished;

(5) Contractor/Government investment in facilities and equipment (and any modernization to be provided by the contractor/Government);

(6) Any deviations, special clauses, or unusual conditions anticipated, for example, unusual financing, warranties, EPA clauses and when approvals were obtained, if required; and

(7) Any risk management issues, e.g., mission success, safety, occupational health, information technology, export control, security, and environmental risks.

(d) Cost analysis. For the basic requirement, and any option, include--

(1) A parallel tabulation, by element of cost and profit/fee, of the contractor's proposal and the Government's negotiation objective. The negotiation objective represents the fair and reasonable price the Government is willing to pay for the supplies/services. For each element of cost, compare the contractor's proposal and the Government position, explain the differences and how the Government position was developed, including the estimating assumptions and projection techniques employed, and how the positions differ in approach. Include a discussion of excessive wages found (if applicable) and their planned resolution. Explain how historical costs, including costs incurred under a letter contract (if applicable), were used in developing the negotiation objective.

(2) Significant differences between the field pricing report (including any audit reports) and the negotiation objectives and/or contractor's proposal shall be highlighted and explained. For each proposed subcontract meeting the requirement of FAR 15.404-3(c), there shall be a discussion of the price and, when appropriate, cost analyses performed by the contracting officer, including the negotiation objective for each such subcontract. The discussion of each major subcontract shall include the type of subcontract, the degree of competition achieved by the prime contractor, the price and, when appropriate, cost analyses performed on the subcontractor's proposal by the prime contractor, any unusual or special pricing or finance arrangements, and the current status of subcontract negotiations.

(3) The rationale for the Government's profit/fee objectives and, if appropriate, a completed copy of the NASA Form 634, Structured Approach--Profit/Fee Objective, and DD Form 1861, Contract Facilities Capital Cost of Money, should be included. For incentive and award fee contracts, describe the planned arrangement in terms of share lines, ceilings, and cost risk.

(e) Negotiation approval sought. The PPM represents the Government's realistic assessment of the fair and reasonable price for the supplies and services to be acquired. If negotiations subsequently demonstrate that a higher dollar amount (or significant term or condition) is reasonable, the contracting officer shall document the rationale for such a change and request approval to amend the PPM from the original approval authority.

1815.406-171 Installation reviews.

Each contracting activity shall establish procedures to review all prenegotiation position memoranda. The scope of coverage, exact procedures to be followed, levels of management review, and contract file documentation requirements should be directly related to the dollar value and complexity of the acquisition. The primary purpose of these reviews is to ensure that the negotiator, or negotiation team, is thoroughly prepared to enter into negotiations with a well-conceived, realistic, and fair plan.

1815.406-172 Headquarters reviews.

(a) When a prenegotiation position has been selected for Headquarters review and approval, the contracting activity shall submit to the Office of Procurement (Code HS) one copy each of the prenegotiation position memorandum, the contractor's proposal, the Government technical evaluation, and all pricing reports (including any audit reports).

(b) The required information described in paragraph (a) of this section shall be furnished to Headquarters as soon as practicable and sufficiently in advance of the planned commencement of negotiations to allow a reasonable period of time for Headquarters review. Electronic submittal is acceptable.

1815.406-3 Documenting the negotiation.

(a)(i) The price negotiation memorandum (PNM) serves as a detailed summary of: the technical, business, contractual, pricing (including price reasonableness), and other elements of the contract negotiated; and the methodology and rationale used in arriving at the final negotiated agreement.

(ii) A PNM is not required for a contract awarded under competitive negotiated procedures. However, the information required by FAR 15.406-3 shall be reflected in the evaluation and selection documentation to the extent applicable.

(iii) When the PNM is a "stand-alone" document, it shall contain the information required by the FAR and NFS for both PPMs and PNMs. However, when a PPM has been prepared under 1815.406-1, the subsequent PNM need only provide any information required by FAR 15.406-3 that was not provided in the PPM, as well as any changes in the status of factors affecting cost elements (e.g., use of different rates, hours, or subcontractors; wage rate determinations; or the current status of the contractor's systems).

1815.407 Special cost or pricing areas.

1815.407-2 Make-or-buy programs.

(e)(1) Make-or-buy programs should not include items or work efforts estimated to cost less than $500,000.

1815.408 Solicitation provisions and contract clauses.

1815.408-70 NASA solicitation provisions and contract clauses.

(a) The contracting officer shall insert the provision at 1852.215-78, Make-or-Buy Program Requirements, in solicitations requiring make-or-buy programs as provided in FAR 15.407-2(c). This provision shall be used in conjunction with the clause at FAR 52.215-9, Changes or Additions to Make-or-Buy Program. The contracting officer may add additional paragraphs identifying any other information required in order to evaluate the program.

(b) The contracting officer shall insert the clause at 1852.215-79, Price Adjustment for "Make-or-Buy" Changes, in contracts that include FAR 52.215-9 with its Alternate I or II. Insert in the appropriate columns the items that will be subject to a reduction in the contract value.

Subpart 1815.5 --Preaward, Award, and Postaward Notifications,
Protests, and Mistakes

1815.504 Award to successful offeror.

The reference to notice of award in FAR 15.504 on negotiated acquisitions is a generic one. It relates only to the formal establishment of a contractual document obligating both the Government and the offeror. The notice is effected by the transmittal of a fully approved and executed definitive contract document, such as the award portion of SF 33, SF 26, SF 1449, or SF 1447, or a letter contract when a definitized contract instrument is not available but the urgency of the requirement necessitates immediate performance. In this latter instance, the procedures in 1816.603 for approval and issuance of letter contracts shall be followed.

1815.506 Postaward debriefing of offerors.

1815.506-70 Debriefing of offerors - Major System acquisitions.

(a) When an acquisition is conducted in accordance with the Major System acquisition procedures in Part 1834 and multiple offerors are selected, the debriefing will be limited in such a manner that it does not prematurely disclose innovative concepts, designs, and approaches of the successful offerors that would result in a transfusion of ideas.

(b) When Phase B awards are made for alternative system design concepts, the source selection statements shall not be released to competing offerors or the general public until the release of the source selection statement for Phase C/D without the approval of the Associate Administrator for Procurement (Code HS).

Subpart 1815.6--Unsolicited Proposals

1815.602 Policy.

(1) An unsolicited proposal may result in the award of a contract, grant, cooperative agreement, or other agreement. If a grant or cooperative agreement is used, the NASA Grant and Cooperative Agreement Handbook (NPG 5800.1) applies.

(2) Renewal proposals, (i.e., those for the extension or augmentation of current contracts) are subject to the same FAR and NFS regulations, including the requirements of the Competition in Contracting Act, as are proposals for new contracts.

1815.604 Agency points of contact.

(a) Information titled "Guidance for the Preparation and Submission of Unsolicited Proposals" is available on the Internet at http://ec.msfc.nasa.gov/msfc/nasahdbk.html. A deviation is required for use of any modified or summarized version of the Internet information or for alternate means of general dissemination of unsolicited proposal information.

1815.606 Agency procedures.

(a) NASA will not accept for formal evaluation unsolicited proposals initially submitted to another agency or to the Jet Propulsion Laboratory (JPL) without the offeror's express consent.

(b)(i) NASA Headquarters and each NASA field installation shall designate a point of contact for receiving and coordinating the handling and evaluation of unsolicited proposals.

(ii) Each installation shall establish procedures for handling proposals initially received by other offices within the installation. Misdirected proposals shall be forwarded by the point of contact to the proper installation. Points of contact are also responsible for providing guidance to potential offerors regarding the appropriate NASA officials to contact for general mission-related inquiries or other preproposal discussions.

(iii) Points of contact shall keep records of unsolicited proposals received and shall provide prompt status information to requesters. These records shall include, at a minimum, the number of unsolicited proposals received, funded, and rejected during the fiscal year; the identity of the offerors; and the office to which each was referred. The numbers shall be broken out by source (large business, small business, university, or nonprofit institution).

1815.606-70 Relationship of unsolicited proposals to NRAs.

An unsolicited proposal for a new effort or a renewal, identified by an evaluating office as being within the scope of an open NRA, shall be evaluated as a response to that NRA (see 1835.016-71), provided that the evaluating office can either:

(a) State that the proposal is not at a competitive disadvantage, or

(b) Give the offeror an opportunity to amend the unsolicited proposal to ensure compliance with the applicable NRA proposal preparation instructions. If these conditions cannot be met, the proposal must be evaluated separately.

1815.609 Limited use of data.

1815.609-70 Limited use of proposals.

Unsolicited proposals shall be evaluated outside the Government only to the extent authorized by, and in accordance with, the procedures prescribed in, 1815.207-70.

1815.670 Foreign proposals.

Unsolicited proposals from foreign sources are subject to NPD 1360.2, Initiation and Development of International Cooperation in Space and Aeronautics Programs.

Subpart 1815.70 -- Ombudsman

1815.7001 NASA Ombudsman Program.

NASA's implementation of an ombudsman program is in NPG 5101.33, Procurement Guidance.

1815.7002 Synopses of solicitations and contracts.

In all synopses announcing competitive acquisitions, the contracting officer shall indicate that the clause at 1852.215-84, Ombudsman, is applicable. This may be accomplished by referencing the clause number and identifying the installation Ombudsman.

1815.7003 Contract clause.

The contracting officer shall insert a clause substantially the same as the one at 1852.215-84, Ombudsman, in all solicitations (including draft solicitations) and contracts. Use the clause with its Alternate I when a task or delivery order contract is contemplated.


development, the procurement officer may authorize the use of a base fee not to exceed 3 percent. Base fee shall not be used when an award fee incentive is used in conjunction with another contract type (e.g., CPIF/AF).

(b) When a base fee is authorized for use in a CPAF contract, it shall be paid only if the final award fee evaluation is "satisfactory" or better. (See 1816.405-273 and 1816.405-275) Pending final evaluation, base fee may be paid during the life of the contract at defined intervals on a provisional basis. If the final award fee evaluation is "poor/unsatisfactory", all provisional base fee payments shall be refunded to the Government.

1816.405-272 Award fee evaluation periods.

(a) Award fee evaluation periods, including those for interim evaluations, should be at least 6 months in length. When appropriate, the procurement officer may authorize shorter evaluation periods after ensuring that the additional administrative costs associated with the shorter periods are offset by benefits accruing to the Government. Where practicable, such as developmental contracts with defined performance milestones (e.g., Preliminary Design Review, Critical Design Review, initial system test), establishing evaluation periods at conclusion of the milestones rather than calendar dates, or in combination with calendar dates should be considered. In no case shall an evaluation period be longer than 12 months.

(b) A portion of the total available award fee contract shall be allocated to each of the evaluation periods. This allocation may result in an equal or unequal distribution of fee among the periods. The contracting officer should consider the nature of each contract and the incentive effects of fee distribution in determining the appropriate allocation structure.

1816.405-273 Award fee evaluations.

(a) Service Contracts. On contracts where the contract deliverable is the performance of a service over any given time period, contractor performance is often definitively measurable within each evaluation period. In these cases, all evaluations are final, and the contractor keeps the fee earned in any period regardless of the evaluations of subsequent periods. Unearned award fee in any given period in a service contract is lost and shall not be carried forward, or "rolled-over," into subsequent periods.

(b) End Item Contracts. On contracts, such as those for end item deliverables, where the true quality of contractor performance cannot be measured until the end of the contract, only the last evaluation is final. At that point, the total contract award fee pool is available, and the contractor's total performance is evaluated against the award fee plan to determine total earned award fee. In addition to the final evaluation, interim evaluations are done to monitor performance prior to contract completion, provide feedback to the contractor on the Government's assessment of the quality of its performance, and establish the basis for making interim award fee payments (see 1816.405-276(a)). These interim evaluations and associated interim award fee payments are superseded by the fee determination made in the final evaluation at contract completion. The Government will then pay the contractor, or the contractor will refund to the Government, the difference between the final award fee determination and the cumulative interim fee payments.

(c) Control of evaluations. Interim and final evaluations may be used to provide past performance information during the source selection process in future acquisitions and should be marked and controlled as "Source Selection Information - See FAR 3.104".

1816.405-274 Award fee evaluation factors.

(a) Explicit evaluation factors shall be established for each award fee period.

(b) Evaluation factors will be developed by the contracting officer based upon the characteristics of an individual procurement. Normally, technical and schedule considerations will be included in all CPAF contracts as evaluation factors. Cost control shall be included as an evaluation factor in all CPAF contracts. When explicit evaluation factor weightings are used, cost control shall be no less than 25 percent of the total weighted evaluation factors. The predominant consideration of the cost control evaluation should be a measurement of the contractor's performance against the negotiated estimated cost of the contract. This estimated cost may include the value of undefinitized change orders when appropriate.

(c)(1) The technical factor, if used, must include consideration of risk management (including mission success, safety, security, health, export control, and damage to the environment, as appropriate) unless waived at a level above the contracting officer, with the concurrence of the project manager. The rationale for any waiver shall be documented in the contract file. When safety, export control, or security are considered under the technical factor, the award fee plan shall allow the following fee determinations, regardless of contractor performance in other evaluation factors, when there is a major breach of safety or security.

(i) For evaluation of service contracts under 1816.405-273(a), an overall fee determination of zero for any evaluation period in which there is a major breach of safety or security.

(ii) For evaluation of end item contracts under 1816.405-273(b), an overall fee determination of zero for any interim evaluation period in which there is a major breach of safety or security. To ensure that the final award fee evaluation at contract completion reflects any major breach of safety or security, in an interim period, the overall award fee pool shall be reduced by the amount of the fee available for the period in which the major breach occurred if a zero fee determination was made because of a major breach of safety or security.

(2) A major breach of safety consists of an accident, incident, or exposure resulting in a fatality or mission failure; or in damage to equipment or property equal to or greater than $1 million; or in any "willful" or "repeat" violation cited by the Occupational Health and Safety Administration (OSHA) or by a state agency operating under an OSHA approved plan.

(3) Security is the condition of safeguarding against espionage, sabotage, crime (including computer crime), or attack. A major breach of security may arise from any of the following: compromise of classified information; illegal technology transfer; workplace violence resulting in criminal conviction; sabotage; compromise or denial of information technology services; damage or loss greater than $250,000 to the Government; or theft.

(d) In rare circumstances, contract costs may increase for reasons outside the contractor's control and for which the contractor is not entitled to an equitable adjustment. One example is a weather-related launch delay on a launch support contract. The Government shall take such situations into consideration when evaluating contractor cost control.

(e) Emphasis on cost control should be balanced against other performance requirement objectives. The contractor should not be incentivized to pursue cost control to the point that overall performance is significantly degraded. For example, incentivizing an underrun that results in direct negative impacts on technical performance, safety, or other critical contract objectives is both undesirable and counterproductive. Therefore, evaluation of cost control shall conform to the following guidelines:

(1) Normally, the contractor should be given a score of 0 for cost control when there is a significant overrun within its control. However, the contractor may receive higher scores for cost control if the overrun is insignificant. Scores should decrease sharply as the size of the overrun increases. In any evaluation of contractor overrun performance, the Government shall consider the reasons for the overrun and assess the extent and effectiveness of the contractor's efforts to control or mitigate the overrun.

(2) The contractor should normally be rewarded for an underrun within its control, up to the maximum score allocated for cost control, provided the average numerical rating for all other award fee evaluation factors is 81 or greater (see 1816.405-275). An underrun shall be rewarded as if the contractor has met the estimated cost of the contract (see 1816.405-274(d)(3)) when the average numerical rating for all other factors is less than 81 but greater than 60.

(3) The contractor should be rewarded for meeting the estimated cost of the contract, but not to the maximum score allocated for cost control, to the degree that the contractor has prudently managed costs while meeting contract requirements. No award shall be given in this circumstance unless the average numerical rating for all other award fee evaluation factors is 61 or greater.

(f) When an AF arrangement is used in conjunction with another contract type, the award fee's cost control factor will only apply to a subjective assessment of the contractor's efforts to control costs and not the actual cost outcome incentivized under the basic contract type (e.g. CPIF, FPIF).

(g)(1) The contractor's performance against the subcontracting plan incorporated in the contract shall be evaluated. Emphasis may be placed on the contractor's accomplishment of its goals for subcontracting with small business, HUBZone small business, and women-owned small business concerns.

(2) The contractor's performance against the contract target for participation as subcontractors by small disadvantaged business concerns in the SIC Major Groups designated by the Department of Commerce (see FAR 19.201(c)) shall also be evaluated if the clause at FAR 52.219-26, Small Disadvantaged Business Participation - Incentive Subcontracting, is not included in the contract (see FAR 19.1204(c)).

(3) The contractor's achievements in subcontracting high technology efforts as well as the contractor's performance under the Mentor-Protégé Program, if applicable, may also be evaluated.

(4) The evaluation weight given to the contractor's performance against the considerations in paragraphs (g)(1) through (g)(3) of this section should be significant (up to 15 percent of available award fee). The weight should motivate the contractor to focus management attention to subcontracting with small, HUBZone, and women-owned small business concerns, and with small disadvantaged business concerns in designated SIC Major Groups to the maximum extent practicable, consistent with efficient contract performance.

(h) Only the award fee performance evaluation factors set forth in the performance evaluation plan shall be used to determine award fee scores.

(i) The Government may unilaterally modify the applicable award fee performance evaluation factors and performance evaluation areas prior to the start of an evaluation period. The contracting officer shall notify the contractor in writing of any such changes 30 days prior to the start of the relevant evaluation period.

1816.405-275 Award fee evaluation scoring.

(a) A scoring system of 0-100 shall be used for all award fee ratings. Award fee earned is determined by applying the numerical score to the award fee pool. For example, a score of 85 yields an award fee of 85 percent of the award fee pool. No award fee shall be paid unless the total score is 61 or greater.

(b) The following standard adjectival ratings and the associated numerical scores shall be used on all award fee contracts.

(1) Excellent (100-91): Of exceptional merit; exemplary performance in a timely, efficient, and economical manner; very minor (if any) deficiencies with no adverse effect on overall performance.

(2) Very good (90-81): Very effective performance, fully responsive to contract requirements; contract requirements accomplished in a timely, efficient, and economical manner for the most part; only minor deficiencies.

(3) Good (80-71): Effective performance; fully responsive to contract requirements; reportable deficiencies, but with little identifiable effect on overall performance.

(4) Satisfactory (70-61): Meets or slightly exceeds minimum acceptable standards; adequate results; reportable deficiencies with identifiable, but not substantial, effects on overall performance.

(5) Poor/Unsatisfactory (less than 61): Does not meet minimum acceptable standards in one or more areas; remedial action required in one or more areas; deficiencies in one or more areas which adversely affect overall performance.

(c) As a benchmark for evaluation, in order to be rated "Excellent," the contractor must be under cost, on or ahead of schedule, and have provided excellent technical performance.

(d) A scoring system appropriate for the circumstances of the individual contract requirement should be developed. Weighted scoring is recommended. In this system, each evaluation factor (e.g., technical, schedule, cost control) is assigned a specific percentage weighting with the cumulative weightings of all factors totaling 100. During the award fee evaluation, each factor is scored from 0-100 according to the ratings defined in 1816.405-275(b). The numerical score for each factor is then multiplied by the weighting for that factor to determine the weighted score. For example, if the technical factor has a weighting of 60 percent and the numerical score for that factor is 80, the weighted technical score is 48 (80 x 60 percent). The weighted scores for each evaluation factor are then added to determine the total award fee score.

1816.405-276 Award fee payments and limitations.

(a) Interim Award Fee Payments. The amount of an interim award fee payment (see 1816.405-273(b)) is limited to the lesser of the interim evaluation score or 80 percent of the fee allocated to that interim period less any provisional payments (see paragraph (b) of this subsection) made during the period.

(b) Provisional Award Fee Payments. Provisional award fee payments are payments made within evaluation periods prior to an interim or final evaluation for that period. Provisional payments may be included in the contract and should be negotiated on a case-by-case basis. For a service contract, the total amount of award fee available in an evaluation period that may be provisionally paid is the lesser of a percentage stipulated in the contract (but not exceeding 80 percent) or the prior period's evaluation score. For an end item contract, the total amount of provisional payments in a period is limited to a percentage not to exceed 80 percent of the prior interim period's evaluation score.

(c) Fee Payment. The Fee Determination Official's rating for both interim and final evaluations will be provided to the contractor within 45 calendar days of the end of the period being evaluated. Any fee, interim or final, due the contractor will be paid no later than 60 calendar days after the end of the period being evaluated.

1816.406 Contract clauses.

1816.406-70 NASA contract clauses.

(a) As authorized by FAR 16.406(e), the contracting officer shall insert the clause at 1852.216-76, Award Fee for Service Contracts, in solicitations and contracts when an award-fee contract is contemplated and the contract deliverable is the performance of a service.

(b) As authorized by FAR 16.406(e), the contracting officer shall insert the clause at 1852.216-77, Award Fee for End Item Contracts, in solicitations and contracts when an award fee contract is contemplated and the contract deliverables are hardware or other end items for which total contractor performance cannot be measured until the end of the contract. When the clause is used in a fixed-price award-fee contract, it shall be modified by deleting references to base fee in paragraphs (a), and by deleting paragraph (c)(1), the last sentence of (c)(4), and the first sentence of (c)(5).

(c) The contracting officer may insert a clause substantially as stated at 1852.216-83, Fixed Price Incentive, in fixed-price-incentive solicitations and contracts utilizing firm or successive targets. For items subject to incentive price revision, identify the target cost, target profit, target price, and ceiling price for each item.

(d) The contracting officer shall insert the clause at 1852.216-84, Estimated Cost and Incentive Fee, in cost-plus-incentive-fee solicitations and contracts.

(e) The contracting officer may insert the clause at 1852.216-85, Estimated Cost and Award Fee, in award-fee solicitations and contracts. When the contract includes performance incentives, use Alternate I. When the clause is used in a fixed-price award fee contract, it shall be modified to delete references to base fee and to reflect the contract type.

(f) As provided at 1816.402-270, the contracting officer shall insert a clause substantially as stated at 1852.216-88, Performance Incentive, when the primary deliverable(s) is (are) hardware and total estimated cost and fee is greater than $25 million. A clause substantially as stated at 1852.216-88 may be included in lower dollar value hardware contracts with the approval of the procurement officer.

Subpart 1816.5--Indefinite-Delivery Contracts

1816.504 Indefinite quantity contracts.

(a)(4)(ii) ID/IQ service contract values and task order values shall be expressed only in dollars.

(a)(4)(v) See 1815.7003.

1816.505 Ordering.

(a)(2) Task and delivery orders shall be issued by the contracting officer.

(b)(5) The Agency and installation ombudsmen designated in accordance with 1815.70 shall review complaints from contractors on task order contracts and delivery order contracts.

1816.505-70 Task ordering.

(a) The contracting officer shall, to the maximum extent possible, state task order requirements in terms of functions and the related performance and quality standards such that the standards may be objectively measured.

(b) To the maximum extent possible, contracting officers shall solicit contractor task plans to use as the basis for finalizing task order requirements and enable evaluation and pricing of the contractor's proposed work on a performance based approach as described in 1816.404-270(a).

(c) Task order contract type shall be individually determined, based on the nature of each task order's requirements.

(1) Task orders may be grouped by contract type for administrative convenience (e.g., all CPIF orders, all FFP orders, etc.) for contractor progress and cost reporting.

(2) Under multiple awards, solicitations for individual task plans shall request the same pricing structure from all offerors.

(d) Any undefinitized task order issued under paragraph (f) of the clause at 1852.216-80, Task Ordering Procedure, shall be treated and reported as an undefinitized contract action in accordance with 1843-70.

1816.506-70 NASA contract clause.

Insert the clause at 1852.216-80, Task Ordering Procedure, in solicitations and contracts when an indefinite-delivery, task order contract is contemplated. The clause is applicable to both fixed-price and cost-reimbursement type contracts. If the contract does not require 533M reporting (see NPG 9501.2, NASA Contractor Financial Management Reporting System), use the clause with its Alternate I.

Subpart 1816.6--Time-and-Materials, Labor-Hour, and Letter Contracts

1816.603 Letter contracts.

1816.603-370 Approvals.

(a) All requests for authority to issue a letter contract shall include the following:

(1) Proposed contractor's name and address.

(2) Location where contract is to be performed.

(3) Contract number, including modification number, if applicable.

(4) Brief description of the work or services to be performed.

(5) Performance period or delivery schedule.

(6) Amount of letter contract.

(7) Performance period of letter contract.

(8) Estimated total amount of definitive contract.

(9) Type of definitive contract to be executed.

(10) A statement that the definitive contract will contain all required clauses or identification of specific clause deviations that have been approved.

(11) A statement as to the necessity and advantage to the Government of the proposed letter contract.

(12) The definitization schedule described in FAR 16.603-2(c) expected to be negotiated with the contractor.

(b) Requests for authority to issue letter contracts having an estimated definitive contract amount equal to or greater than the Master Buy Plan submission thresholds of 1807.7101 (or modifications thereto) shall be signed by the procurement officer and submitted to the Associate Administrator for Procurement (Code HS) for approval.

(c) Authority to approve the issuance of letter contracts below the Master Buy Plan submission thresholds specified in 1807.7101 is delegated to the procurement officer.

(d) Any modification of an undefinitized letter contract approved by a procurement officer in accordance with paragraph (c) of this section that increases the estimated definitized contract amount to or above the Master Buy Plan submission thresholds must have the prior approval of the Associate Administrator for Procurement (Code HS).


PART 1823
ENVIRONMENT, CONSERVATION, OCCUPATIONAL SAFETY,
AND DRUG-FREE WORKPLACE

TABLE OF CONTENTS

SUBPART 1823.3 HAZARDOUS MATERIAL IDENTIFICATION AND MATERIAL SAFETY DATA

1823.370 Acquisition of potentially hazardous items from or through another Government agency.

SUBPART 1823.5 DRUG-FREE WORKPLACE

1823.570 Drug- and alcohol-free workforce.

1823.570-1 Scope.

1823.570-2 Definitions.

1823.570-3 Contract clause.

1823.570-4 Suspension of payments, termination of contract, and debarment and suspension actions.

SUBPART 1823.70 SAFETY AND HEALTH

1823.7001 NASA solicitation provisions and contract clauses.

SUBPART 1823.71 FREQUENCY AUTHORIZATION

1823.7101 Contract clause.

1823.7102 Procedures.

 

PART 1823
ENVIRONMENT, CONSERVATION, OCCUPATIONAL SAFETY,
AND DRUG-FREE WORKPLACE

Subpart 1823.3--Hazardous Material Identification and Material Safety Data

1823.370 Acquisition of potentially hazardous items from or through another Government agency.

When acquiring supplies or services from or through another Government agency (e.g., see FAR Part 8 and FAR Subpart 17.5), NASA shall request that agency to furnish NASA the data required by FAR Subpart 23.3.

Subpart 1823.5--Drug-Free Workplace

1823.570 Drug- and alcohol-free workforce.

1823.570-1 Scope.

Sections 1823.570 to 1823.570-4 set forth NASA requirements for mandatory drug and alcohol testing of certain contractor personnel under section 203, National Aeronautics and Space Act of 1958, as amended, 42 U.S.C. 2473, 72 Stat. 429; and Civil Space Employee Testing Act of 1991, Public Law 102-195, sec. 21, 105 Stat. 1616 to 1619.

1823.570-2 Definitions.

As used in this subpart employee and controlled substance are as defined in FAR 23.503. The use of a controlled substance in accordance with the terms of a valid prescription, or other uses authorized by law shall not be subject to the requirements of 1823.570 to 1823.570-4 and the clause at 1852.223-74.

"Employee in a sensitive position" means a contractor or subcontractor employee who has been granted access to classified information; a contractor or subcontractor employee in other positions that the contractor or subcontractor determines could reasonably be expected to affect safety, security, National security, or functions other than the foregoing requiring a high degree of trust and confidence; and includes any employee performing in a position designated "mission critical" pursuant to the clause at 1852.246-70. The term also includes any applicant who is interviewed for a position described in this paragraph.

"Use, in violation of applicable law or Federal regulation, of alcohol" includes having, while on duty or during a preemployment interview, an alcohol concentration of 0.04 percent by weight or more in the blood, as measured by chemical test of the individual's breath or blood. An individual's refusal to submit to such test is presumptive evidence of use, in violation of applicable law or Federal regulation, of alcohol.

1823.570-3 Contract clause.

The contracting officer shall insert the clause at 1852.223-74, "Drug- and Alcohol-Free Workforce," in all solicitations and contracts containing the clause at 1852.246-70, "Mission Critical Space Systems Personnel Reliability Program," and in other solicitations and contracts exceeding $5 million in which work is performed by an employee in a sensitive position. However, the contracting officer shall not insert the clause at 1852.223-74 in solicitations and contracts for commercial items (see FAR parts 2 and 12).

 1823.570-4 Suspension of payments, termination of contract, and debarment and suspension actions.

The contracting officer shall comply with the procedures of FAR 23.506 regarding the suspension of contract payments, the termination of the contract for default, and debarment and suspension of a contractor relative to failure to comply with the clause at 1852.223-74. Causes for suspension of contract payments, termination of the contract for default, and debarment and suspension of the contractor are the following:

(a) The contractor fails to comply with paragraph (b), (c), or (d) of the clause at 1852.223-74; or

(b) Such a number of contractor employees in sensitive positions having been convicted of violations of criminal drug statutes or substantial evidence of drug or alcohol abuse or misuse occurring in the workplace, as to indicate that the contractor has failed to make a good faith effort to provide a drug- and alcohol-free workforce.

Subpart 1823.70--Safety and Health

1823.7001 NASA solicitation provisions and contract clauses.

(a) Except as provided in paragraph (b) of this section, the clause at 1852.223-70, Safety and Health, shall be included in all solicitations and contracts for --

(1) Negotiated acquisitions of $1,000,000 or more;

(2) Construction, repair, or alteration in excess of the simplified acquisition threshold;

(3) Acquisitions having, within their total requirement, construction, repair, or alteration tasks in excess of the simplified acquisition threshold; and

(4) Acquisitions regardless of dollar amount when --

(i) Any deliverable contract end item is of a hazardous nature; or

(ii) It can reasonably be expected that hazards will be generated and controlled within the operational environment during the life of the contract and the contracting officer determines that they warrant inclusion of the clause.

(b) The clause prescribed in paragraph (a) of this section may be excluded --

(1) From any contract subject to the Walsh-Healey Public Contracts Act (see FAR Subpart 22.6) or the Service Contract Act of 1965 (see FAR Subpart 22.10) in which the application of either act and its implementing regulations constitute adequate safety and occupational health protection; or

(2) When the contracting officer, with the concurrence of the installation official(s) responsible for matters of safety and occupational health, makes a written determination that the clause is not necessary under the circumstances of the acquisition.

(c) The contracting officer shall insert the provision at 1852.223-73, Safety and Health Plan, in solicitations containing the clause at 1852.223-70. This clause may be modified to identify specific information that is to be included in the plan. After receiving the concurrence of the center safety and occupational health official(s), the contracting officer shall include the plan in any resulting contract.

(d) The contracting officer shall insert the clause at 1852.223-75, Major Breach of Safety or Security, in all solicitations and contracts with estimated values of $500,000 or more, unless waived at a level above the contracting officer with the concurrence of the project manager and the installation official(s) responsible for matters of security, export control, safety, and occupational health. For other contracts, use of the clause is optional.

Subpart 1823.71--Frequency Authorization

1823.7101 Contract clause.

The contracting officer shall insert the clause at 1852.223-71, Frequency Authorization, in solicitations and contracts calling for developing, producing, constructing, testing, or operating a device for which a radio frequency authorization is required.

1823.7102 Procedures.

The contracting officer shall obtain the necessary frequency authorization and other procedural details from the installation's spectrum manager.


(iii) The delegation will impose an abnormal demand on the resources of the contract administration office receiving the delegation; or

(iv) Complex contract management issues are expected, particularly risk management areas identified during program and acquisition planning, e.g., significant or unusual mission success, technical, cost, schedule, safety, security, occupational health, environmental protection, and export control risks.

(2) Procurement officer approval is required to waive a post-award planning conference for contracts meeting any of the criteria in paragraph (1) of this section. The request for procurement officer approval to waive a post-award conference shall address action taken and planned to ensure


PART 1846
QUALITY ASSURANCE

TABLE OF CONTENTS

1846.000 Scope of part.

SUBPART 1846.3 CONTRACT CLAUSES

1846.370 NASA contract clauses.

SUBPART 1846.4 GOVERNMENT CONTRACT QUALITY ASSURANCE

1846.401 General.

1846.470 Contract clause.

SUBPART 1846.6 MATERIAL INSPECTION AND RECEIVING REPORTS

1846.670 Introduction.

1846.670-1 General.

1846.670-2 Applicability.

1846.670-3 Use.

1846.670-4 Multiple shipments.

1846.670-5 Forms.

1846.671 Contract quality assurance on shipments between contractors.

1846.672 Preparing DD Forms 250 and 250c.

1846.672-1 Preparation instructions.

1846.672-2 Consolidated shipments.

1846.672-3 Multiple consignee instructions.

1846.672-4 Correction instructions.

1846.672-5 Invoice instructions.

1846.672-6 Packing list instructions.

1846.672-7 Receiving instructions.

1846.673 Distribution of DD Forms 250 and 250c.

1846.674 Contract clause.

SUBPART 1846.7 WARRANTIES

1846.703 Criteria for use of warranties.

1846.703-70 Additional criteria.

1846.704 Authority for use of warranties.

1846.770 Administration.

 

PART 1846
QUALITY ASSURANCE

1846.000 Scope of part.

The Government has a duty to assure that appropriated funds are spent wisely. That duty is fulfilled in part through surveillance. Surveillance may be conducted through "insight" (i.e., monitoring of selected metrics and/or milestones) or "oversight" (i.e., Government review and concurrence with contractor decisions). The decision to use insight or oversight is based on an assessment of the risk inherent in the activity being surveilled. Surveillance must be conducted whether or not the contract effort has been structured as performance-based.

Subpart 1846.3--Contract Clauses

1846.370 NASA contract clauses.

(a) The contracting officer shall insert the clause at 1852.246-70, Mission Critical Space System Personnel Reliability Program, in solicitations and contracts involving critical positions designated in accordance with 14 CFR 1214.5, Mission Critical Space System Personnel Reliability Program.

(b) The contracting officer shall insert the clause at 1852.246-73, Human Space Flight Item, in solicitations and contracts for human space flight hardware and flight-related equipment if the highest available quality standards are necessary to ensure astronaut safety.

Subpart 1846.4--Government Contract Quality Assurance

1846.401 General.

(a) The quality assurance surveillance plan (QASP) which the project office prepares in conjunction with the statement of work is preliminary. It reflects the Government's surveillance approach relative to the perceived programmatic risk, and is written at a general rather than specific level because the risks will not be completely identified at that time. After contract award, contracting officers shall ensure that the QASP is revised to reflect the risks associated with the successful proposal. This final QASP shall not be included in the contract, but should be periodically reviewed to ensure its currency.

1846.470 Contract clause.

The contracting officer may insert a clause substantially as stated at 1852.246-71, Government Contract Quality Assurance Functions, in solicitations and contracts to specify the location(s) of quality assurance functions.

Subpart 1846.6--Material Inspection and Receiving Reports

1846.670 Introduction.

1846.670-1 General.

(a) This Subpart contains procedures and instructions for use of the Material Inspection and Receiving Report (MIRR) (DD Form 250 series) assurance (CQA).

(b) MIRRs are used to document CQA, acceptance and commercial shipping/packing lists used to evidence Government contract quality of supplies and services, and shipments. MIRRs are not used for--

(1) Shipments by subcontractors not made to the Government;

(2) Shipment of contractor inventory (see FAR 45.601); or

(3) Movement of Government property unless for original acquisition.

1846.670-2 Applicability.

(a) This subpart applies to all deliveries of supplies or services acquired by or for NASA except:

(1) Acquisitions under FAR Part 13;

(2) Negotiated subsistence acquisitions; or

(3) Contracts for which the end item is a technical or scientific report.

(b) The DD Form 250 may be used for imprest fund purchases, purchase orders, delivery orders placed against Federal Supply Schedule contracts, delivery orders placed against indefinite-delivery contracts, or delivery orders placed against blanket purchase agreements, or when the purchasing, requisitioning, or ordering document provides for inspection and/or acceptance.

(c) When NASA provides CQA and/or acceptance services for non-NASA activities, the MIRR shall be prepared in accordance with the instructions of this subpart unless the contract specifies otherwise.

1846.670-3 Use.

The DD Form 250 is a multipurpose report used for --

(a) Providing evidence of CQA at origin or destination;

(b) Providing evidence of acceptance at origin or destination;

(c) Packing list documentation;

(d) Receiving;

(e) Shipping;

(f) Contractor invoice; and

(g) Contractor invoice support.

1846.670-4 Multiple Shipments.

(a) If the "shipped to," "marked for," "shipped from," "CQA," and "acceptance" data are the same for more than one shipment made on the same day under the same contract in a single car, truck, or other vehicle, one MIRR shall be prepared to cover all such shipments.

(b) If the volume of the shipments precludes the use of a single car, truck, or other vehicle, a separate MIRR shall be provided for each vehicle.

1846.670-5 Forms.

(a) Contractors may obtain MIRR forms from the contracting office at no cost.

(b) Contractors may print forms, provided their format and dimensions are identical to the MIRR forms printed by the Government.

1846.671 Contract quality assurance on shipments between contractors.

(a) The supplier's commercial shipping document/packing list shall indicate performance of required CQA actions at subcontract level. The following entries shall be made on the document/packing list:

Required CQA of items has been performed.

__________________________(Signature of Authorized Government Representative)

__________________________(Date)

__________________________(Typed Name and Office)

(b) Distribution for Government purposes shall be one copy each--

(1) With shipment;

(2) For the Government representative at consignee (via mail); and

(3) For the Government representative at consignor.

1846.672 Preparing DD Forms 250 and 250c.

1846.672-1 Preparation instructions.

(a) General.

(1) Dates shall utilize seven spaces consisting of the last two digits of the year, three-alpha month abbreviation, and two digits for the day (e.g., 96SEP24).

(2) Addresses shall consist of the name, street address/P.O. box, city, State, and ZIP code.

(3) The data entered in the blocks at the top of DD Form 250c shall be identical to the comparable entries in Blocks 1, 2, 3, and 6 of the DD Form 250.

(4) Overflow data of the DD Form 250 shall be entered in Block 16 or in the body of the DD Form 250c with block cross reference. Additional DD Form 250c sheets solely for continuation of Block 23 data shall not be numbered or distributed as part of the MIRR.

(b) Classified information. Classified information shall not appear on the MIRR, nor shall the MIRR be classified.

(c) Block 1--PROC. INSTRUMENT IDEN. (CONTRACT). Enter the contract number, with its identifying center prefix, as contained in the contractual document, including any call/order number.

(d) Block 2--SHIPMENT NO.

(1) The shipment number is a three-alpha character prefix and a four-character numeric or alpha-numeric serial number.

(i) The prefix shall be controlled and assigned by the prime contractor and shall consist of three alpha characters for each "shipped from" address (Block 11). The prefix shall be different for each "Shipped From" address and shall remain constant throughout the contract period.

(ii) The serial number for the first shipment under a prime contract from each "shipped from" address shall be 0001; subsequent shipments under that prime contract shall be consecutively numbered. Alpha-numerics shall be used when more than 9,999 numbers are required. Alpha-numerics shall be serially assigned, with the alpha in the first position, followed by the three-position numeric serial number. The alpha-numeric sequence shall be (the letters I and O shall not be used) A001 through A999 (10,001 through 10,999); B001 through B999 (11,001 through 11,999); to Z999.  When this series is completely used, numbering shall revert to 0001.

(2) The shipment number of the initial shipment shall be reassigned when a "replacement shipment" is involved (see (r)(4)(iv) of this section).

(3) The prime contractor shall control deliveries and on the last shipment of the contract shall suffix the shipment number with a "Z" in addition to that required for line items (see Block 17). If the contract final shipment is from other than the prime contractor's plant, the prime contractor may elect (i) to direct the subcontractor to suffix the "Z" or (ii), on receipt of the subcontractor final shipment information, to correct the DD Form 250 covering the last shipment from the prime contractor's plant by adding a "Z" to that shipment number.

(e) Block 3--DATE SHIPPED. Enter the date the shipment is released to the carrier or the date of completion of services. If the shipment will be released after the date of CQA and/or acceptance, enter the estimated date of release. When the date is estimated, enter an "E" after it. Distribution of the MIRR shall not be delayed for entry of the actual shipping date. Reissuance of the MIRR is not required to show the actual shipping date.

(f) Block 4--B/L TCN. When applicable, enter the commercial or Government bill of lading number after "B/L"; and the Transportation Control Number after "TCN."

(g) Block 5--DISCOUNT TERMS.

(1) The contractor may enter the discount in terms of percentages on all copies of the MIRR.

(2) When the MIRR is used as an invoice, see 1846.672-5.

(h) Block 6--INVOICE.

(1) The contractor may enter the invoice number and actual or estimated date on all copies of the MIRR. When the date is estimated, enter an "E" after the date. Do not correct MIRRs other than invoice copies to reflect the actual date of invoice submission.

(2) When the MIRR is used as an invoice, see 1846.672-5.

(i) Block 7--PAGE/OF. Consecutively number the pages comprising the MIRR. On each page, enter the total number of pages of the MIRR.

(j) Block 8--ACCEPTANCE POINT. Enter an "S" for origin or "D" for destination as specified in the contract as the point of acceptance. Enter an alphabetic "O" for other if the point of acceptance is not specified in the contract.

(k) Block 9--PRIME CONTRACTOR. Enter the code and address.

(l) Block 10--ADMINISTERED BY. Enter the code and address of the contracting office cited in the contract.

(m) Block 11--SHIPPED FROM/CODE/FOB.

(1) Enter the code and address of the "shipped from" location. If identical to Block 9, enter "See Block 9."

(2) For performance of services that do not require delivery of items upon completion, enter the code and address of the location at which the services were performed. If the DD Form 250 covers performance at multiple locations or if identical to Block 9, enter "See Block 9."

(3) Enter on the same line and to the right of "FOB" an "S" for origin or "D" for destination as specified in the contract. Enter an alphabetic "O" if the FOB point cited in the contract is other than origin or destination.

(n) Block 12--PAYMENT WILL BE MADE BY. Enter the address of the payment office cited in the contract.

(o) Block 13--SHIPPED TO/CODE. Enter the code and address from the contract or shipping instructions.

(p) Block 14--MARKED FOR/CODE. Enter the code and address from the contract or shipping instructions.

(q) Block 15--ITEM NO. Enter the item number used in the contract. If four or fewer digits are used, position them to the left of the vertical dashed line. Where a six-digit identification is used, enter the last two digits to the right of the vertical dashed line.

(r) Block 16--STOCK/PART NO./DESCRIPTION.

(1) Enter, as applicable, for each item, using single spacing between each line item, the following:

(i) The Federal Stock Number (FSN) or noncatalog number and, if applicable, prefix or suffix. When a number is not provided or it is necessary to supplement the number, include other identification such as the manufacturer's name or Federal Supply Code (as published in Cataloging Handbook H4-1), and part numbers. Additional part numbers may be shown in parentheses. Also enter the descriptive noun of the item nomenclature and, if provided, the Government-assigned management/material control code. In the case of equal-kind supply items, the first entry shall be the description without regard to kind (e.g., "Resistor"). Below this description, enter the contract item number in Block 15 and stock/part number followed by the size or type in Block 16.

(ii) On the next printing line, if required by the contract for control purposes, enter the make, model, serial number, lot, batch, hazard indicator, and/or similar description.

(iii) On the next printing line, enter the FEDSTRIP requisition number(s) when provided in the contract or shipping instructions.

(2) For service items, enter the word "SERVICE" followed by a short description of less than 20 characters. Do not complete items 4, 13, and 14 when material is not shipped.

(3) For all contracts administered by the Defense Contract Management Command, with the exception of fast pay procedures, enter and complete the following:

Gross Shipping Wt.__(State weight in pounds only).

(4) Enter on the next line the following as appropriate (entries may be extended through Block 20). When entries apply to more than one item in the MIRR, enter them only once after the last item and reference the applicable item numbers.

(i) Enter in capital letters any special handling instructions/limits for material environmental control (e.g., temperature, humidity, aging, freezing, and shock).

(ii) When an FSN is required by, but not cited in, a contract and has not been furnished by the Government, shipment may be made at the direction of the contracting officer. Enter the authority for the shipment.

(iii) When Government-furnished property (GFP) is included with or incorporated into the line item, enter "GFP".

(iv) When the shipment consists of replacements for supplies previously furnished, enter in capital letters "REPLACEMENT SHIPMENT" (see paragraph (s)(3) of this section for replacement indicators.)

(v) For items shipped with missing components, enter and complete the following: "Item(s) shipped short of the following component(s): FSN or comparable identification       , Quantity       , Estimated Value       , Authority       ."

(vi) When shipment is made of components that were short on a prior shipment, enter and complete the following: "These components were listed as shortages on Shipment Number       , date shipped       ."

(vii) When shipments involve drums, cylinders, reels, containers, skids, etc., designated as returnable under contract provisions, enter and complete the following: "Return to          , Quantity       , Item         , Ownership (Government/contractor)."

(viii) Enter shipping container number(s), the type, and the total number of the shipping container(s) included in the shipment.

(ix) The MIRR shall be used to record and report the waivers and deviations from contract specifications, including the source and authority for the waiver or deviation (e.g., the contracting office authorizing the waiver or deviation and the identification of the authorizing document).

(x) For shipments involving discount terms, enter "DISCOUNT EXPEDITE" in at least one-inch outline-type letters.

(xi) When test/evaluation results are a condition of acceptance and are not available before shipment, the following note shall be entered if the shipment is approved by the contracting officer: "Note: Acceptance and payment are contingent upon receipt of approved test/evaluation results." The contracting officer shall advise (A) the consignee of the results (approval/disapproval) and (B) the contractor to withhold invoicing pending attachment to its invoice of the approved test/evaluation results.

(xii) The copy of the DD Form 250 required to support payment for destination acceptance (top copy of the four with shipment) or Alternative Release Procedure (ARP) origin acceptance (additional copy furnished to the Quality Assurance Representative (QAR)) shall be identified by entering "PAYMENT COPY" in approximately one-half-inch outline-type letters with "FORWARD TO BLOCK 12 ADDRESS" in approximately one-quarter-inch letters immediately below. Do not obliterate any other entries.

(xiii) A double line shall be drawn completely across the form following the last entry.

(s) Block 17--QUANTITY SHIP/REC'D.

(1) Enter the quantity shipped, using the unit of measure indicated in the contract for payment. When a second unit of measure is used for purposes other than payment, enter the appropriate quantity directly below in parentheses.

(2) Enter a "Z" below the first digit of the quantity when the total quantity of the item is delivered, including variations within contract terms; and all shortages on items previously shipped short are delivered.

(3) If a replacement shipment is involved, enter below the first digit of the quantity the letter "A" to designate first replacement, "B" for second replacement, and so forth. The final shipment indicator "Z" shall not be used when a final line item shipment is replaced.

(t) Block 18--UNIT. Enter the abbreviation of the unit of measure indicated in the contract for payment. When a second unit of measure is indicated in the contract for purposes other than payment or is used for shipping purposes, enter the abbreviation of the second unit of measure directly below in parentheses. Authorized abbreviations are listed in MIL-STD-129, Marking for Shipping and Storage.

(u) Block 19--UNIT PRICE. Enter the unit price on all NASA copies whenever the MIRR is used for voucher or receiving purposes.

(v) Block 20--AMOUNT. Enter the extended amount when the unit price is entered in Block 19.

(w) Block 21--CONTRACT QUALITY ASSURANCE. The words "conform to contract" contained in the printed statements in Blocks A and B relate to contract obligations pertaining to quality and to the quantity of the items on the report. The statements shall not be modified. Notes taking exception shall be entered in Block 16 or on attached supporting documents with block cross reference.

(1) "A. ORIGIN."

(i) The authorized Government representative shall--

(A) Place an "X" when applicable in the appropriate CQA and/or acceptance box(es) to evidence origin CQA and/or acceptance. When the contract requires CQA at destination in addition to origin CQA, an asterisk shall be entered at the end of the statement and an explanatory note in Block 16;

(B) Sign and date; and

(C) Enter the typed, stamped, or printed name of the signer and office code.

(2) "B. DESTINATION."

(i) When acceptance at origin is indicated in Block 21A, no entries shall be made in Block 21B.

(ii) When acceptance or CQA and acceptance are at destination, the authorized Government representative shall--

(A) Place an "X" in the appropriate box(es);

(B) Sign and date; and

(C) Enter the typed, stamped, or printed name of the signer and office code.

(x) Block 22--RECEIVER'S USE. This block shall be used by the receiving activity (Government or contractor) to denote receipt, quantity, and condition. The receiving activity shall enter in this block the date the supplies arrived. For example, when off-loading or in-checking occurs subsequent to the day of arrival of the carrier at the installation, the date of the carrier's arrival is the date received for purposes of this block.

(y) Block 23--CONTRACTOR USE ONLY. This block is provided and reserved for contractor use.

1846.672-2 Consolidated shipments.

When individual shipments are held at the contractor's plant for authorized transportation consolidation to a single destination on a single bill of lading, the applicable DD Forms 250 may be prepared at the time of CQA or acceptance prior to the time of actual shipment (see Block 3).

1846.672-3 Multiple consignee instructions.

The contractor may prepare one MIRR when the identical item(s) of a contract is to be shipped to more than one consignee, with the same or varying quantities, and the shipment requires origin acceptance. Prepare the MIRR using the procedures in this subpart with the following changes:

(a) Blocks 2, 4, 13, and, if applicable, 14 - Enter "See Attached Distribution List."

(b) Block 15 - The contractor may group item numbers for identical stock/part number and description.

(c) Block 17 - Enter the "total" quantity shipped by item or, if applicable, grouped identical items.

(d) Use the DD Form 250c to list each individual "Shipped To" and "Marked For" with--

(1) Code(s) and complete shipping address and a sequential shipment number for each;

(2) Item number(s);

(3) Quantity;

(4) The FEDSTRIP requisition number and quantity for each when provided in the contract or shipping instructions; and

(5) If applicable, bill of lading number and mode of shipment code.

1846.672-4 Correction instructions.

When, because or errors or omissions, it is necessary to correct the MIRR after distribution, it shall be revised by correcting the original master and distributing the corrected form. The corrections shall be made as follows:

(a) Circle the error and place the corrected information in the same block. If space is limited, enter the corrected information in Block 16, referencing the error page and block.

(b) When corrections are made to Blocks 15 or 17, enter the words "CORRECTIONS HAVE BEEN VERIFIED" on page 1. The authorized Government representative shall date and sign immediately below the statement. This verification statement and signature are not required for other corrections.

(c) MIRRs shall not be corrected for Block 19 and 20 entries.

(d) Clearly mark pages of the MIRR requiring correction with the words "CORRECTED COPY", avoiding obliteration of any other entries. Even though corrections are made on continuation sheets only, also mark page 1 "CORRECTED COPY".

(e) Page 1 and only those continuation pages marked "CORRECTED COPY" shall be distributed to the initial distribution. A complete MIRR with corrections shall be distributed to new addressee(s) created by error corrections.

1846.672-5 Invoice instructions.

The Government encourages, but does not require, contractors to use copies of the MIRR as an invoice in lieu of a commercial form. If the MIRR is used as an invoice, four copies shall be prepared and forwarded to the payment office as follows:

(a) Complete Blocks 5, 6, 19, and 20.

(b) Mark, in letters approximately one inch high, the first copy "ORIGINAL INVOICE" and the remaining three copies "INVOICE COPY".

(c) Forward the four copies to the payment office (Block 12 address).

1846.672-6 Packing list instructions.

Copies of the MIRR may be used as a packing list. The packing list copies shall be in addition to the copies of the MIRR required for distribution (see 1846.673) and shall be marked "PACKING LIST".

1846.672-7 Receiving instructions.

When the MIRR is used for receiving purposes, procedures shall be as prescribed by local directives. If acceptance or CQA and acceptance of supplies are required upon arrival at destination, see Block 21B for instructions.

1846.673 Distribution of DD Forms 250 and 250c.

(a) DD Forms 250 and 250c shall be distributed in accordance with installation procedures.

(b) The contractor is responsible for distributing DD Forms 250 and 250c in accordance with the provisions of the contract or instructions of the contracting officer.

1846.674 Contract clause.

The contracting officer shall insert the clause at 1852.246-72, Material Inspection and Receiving Report, in solicitations and contracts, except those using simplified acquisition procedures or where the only deliverable items are technical or scientific reports. Insert the number of copies to be prepared. Paragraph (a) may be changed to specify advance copies or separate distribution of the DD Form 250.

Subpart 1846.7--Warranties

1846.703 Criteria for use of warranties.

1846.703-70 Additional criteria.

In deciding whether to use a warranty clause, at least the following factors shall be considered in addition to those at FAR 46.703:

(a) Cost of correction or replacement, either by the contractor or by another source, in the absence of a warranty;

(b) The warranty as a deterrent against the furnishing of defective or nonconforming supplies;

(c) Whether the contractor's quality program is reliable enough to provide adequate protection without a warranty, or, if not, whether a warranty would cause the contractor to institute an effective quality program;

(d) Reliance on "brand-name" integrity; and

(e) Whether a warranty is regularly given for a commercial component of a more complex end item.

1846.704 Authority for use of warranties.

(1) A warranty clause may be used when it is found to be in the best interests of the Government, after an analysis of the factors listed in 1846.703-70 and FAR 46.703.

(2) Except for the warranty of commercial items (see FAR 12.404 and 46.709), and warranties contained in Federal, military, or construction specifications, the decision to use a warranty clause or to include a warranty provision in a specification other than a Federal, military, or construction specification shall be made only upon the written authorization of the procurement officer or a designee. This decision may be made either for individual acquisitions or classes of acquisitions.

(3) Warranties required by applicable architect-engineer specifications shall be included in construction contracts.

1846.770 Administration.

When notified of a defect in warranted items, the contracting officer should ascertain whether the warranty is currently in effect and ensure that the contractor is given proper and timely notice of the defect.


PART 1852
SOLICITATION PROVISIONS AND CONTRACT CLAUSES

TABLE OF CONTENTS

1852.000 Scope of part.

SUBPART 1852.1 INSTRUCTIONS FOR USING PROVISIONS AND CLAUSES

1852.101 Using Part 52.

1852.103 Identification of provisions and clauses.

1852.103-70 Identification of modified provisions and clauses.

1852.104 Procedures for modifying and completing provisions and   clauses.

SUBPART 1852.2 TEXTS OF PROVISIONS AND CLAUSES

1852.204-75 Security Classification Requirements.

1852.204-76 Security Requirements for Unclassified Automated   Information Resources.

1852.208-81 Restrictions on Printing and Duplicating.

1852.209-70 Product Removal from Qualified Products List.

1852.209-71 Limitation of Future Contracting.

1852.209-72 Composition of the Contractor.

1852.211-70 Packaging, Handling, and Transportation.

1852.214-70 Caution to Offerors Furnishing Descriptive Literature.

1852.214-71 Grouping for Aggregate Award.

1852.214-72 Full Quantities.

1852.215-77 Preproposal/Pre-bid Conference.

1852.215-78 Make or Buy Program Requirements.

1852.215-79 Price Adjustment for "Make-or-Buy" Changes.

1852.215-81 Proposal Page Limitations.

1852.215-84 Ombudsman.

1852.216-73 Estimated Cost and Cost Sharing.

1852.216-74 Estimated Cost and Fixed Fee.

1852.216-75 Payment of Fixed Fee.

1852.216-76 Award Fee for Service Contracts.

1852.216-77 Award Fee for End Item Contracts.

1852.216-78 Firm Fixed Price.

1852.216-80 Task Ordering Procedure.

1852.216-81 Estimated Cost.

1852.216-83 Fixed Price Incentive.

1852.216-84 Estimated Cost and Incentive Fee.

1852.216-85 Estimated Cost and Award Fee.

1852.216-87 Submission of Vouchers for Payment.

1852.216-88 Performance Incentive.

1852.216-89 Assignment and Release Forms.

1852.217-70 Property Administration and Reporting.

1852.217-71 Phased Procurement Using Down-Selection Procedures.

1852.217-72 Phased Procurement Using Progressive Competition Down-Selection Procedures.

1852.219-73 Small Business Subcontracting Plan.

1852.219-74 Use of Rural Area Small Businesses.

1852.219-75 Small Business Subcontracting Reporting.

1852.219-76 NASA 8 Percent Goal.

1852.219-77 NASA Mentor-Protégé Program.

1852.219-79 Mentor Requirements and Evaluation.

1852.223-70 Safety and Health.

1852.223-71 Frequency Authorization.

1852.223-73 Safety and Health Plan.

1852.223-74 Drug- and Alcohol-Free Workforce.

1852.223-75 Major Breach of Safety or Security.

1852.225-8 Duty-Free Entry of Space Articles.

1852.225-70 Export Licenses.

1852.227-11 Patent Rights--Retention by the Contractor (Short Form).

1852.227-14 Rights in Data--General.

1852.227-17 Rights in Data--Special Works.

1852.227-19 Commercial Computer Software--Restricted Rights.

1852.227-70 New Technology.

1852.227-71 Requests for Waiver of Rights to Inventions.

1852.227-72 Designation of New Technology Representative and Patent Representative.

1852.227-84 Patent Rights Clauses.

1852.227-85 Invention Reporting and Rights--Foreign.

1852.227-86 Commercial Computer Software--Licensing.

1852.227-87 Transfer of Technical Data Under Space Station International Agreements.

1852.228-70 Aircraft Ground and Flight Risk.

1852.228-71 Aircraft Flight Risks.

1852.228-72 Cross-Waiver of Liability for Space Shuttle Services.

1852.228-73 Bid Bond.

1852.228-75 Minimum Insurance Coverage.

1852.228-76 Cross-Waiver of Liability for Space Station Activities.

1852.228-78 Cross-Waiver of Liability for NASA Expendable Launch Vehicle Launches.

1852.231-70 Precontract Costs.

1852.231-71 Determination of Compensation Reasonableness.

1852.232-70 NASA Modification of FAR 52.232-12.

1852.232-77 Limitation of Funds (Fixed-Price Contract).

1852.232-79 Payment for On-Site Preparatory Costs.

1852.232-81 Contract Funding.

1852.232-82 Submission of Requests for Progress Payments.

1852.233-70 Protests to NASA.


(c) The contractor hereby agrees to assist NASA in achieving this goal by using its best efforts to award subcontracts to such entities to the fullest extent consistent with efficient contract performance.

(d) Contractors acting in good faith may rely on written representations by their subcontractors regarding their status as small disadvantaged business concerns, Historically Black Colleges and Universities, minority institutions, and women-owned small business concerns.

(End of clause)

1852.219-77 NASA Mentor-Protégé Program.

As prescribed in 1819.7219(a), insert the following clause:

NASA MENTOR-PROTÉGÉ PROGRAM
(MAY 1999)

(a) Prime contractors, including certain small businesses, are encouraged to participate in the NASA Mentor-Protégé Program for the purpose of providing developmental assistance to eligible protégé entities to enhance their capabilities and increase their participation in NASA contracts.

(b) The Program consists of:

(1) Mentor firms, which are large prime contractors with at least one active subcontracting plan or eligible small businesses;

(2) Protégés, which are subcontractors to the prime contractor, include small disadvantaged business concerns, women-owned small business concerns, Historically Black Colleges and Universities, and minority institutions meeting the qualifications specified in NASA FAR Supplement (NFS) 1819.7209.

(3) Mentor-protégé agreements, approved by the NASA Office of Small and Disadvantaged Business Utilization (OSDBU);

(4) In contracts with award fee incentives, potential for payment of additional fee for voluntary participation and successful performance in the Mentor-Protégé Program.

(c) Mentor participation in the Program, described in NFS 1819.72, means providing technical, managerial and financial assistance to aid protégés in developing requisite high-tech expertise and business systems to compete for and successfully perform NASA contracts and subcontracts.

(d) Contractors interested in participating in the program are encouraged to contact the NASA OSDBU, Washington, DC 20546, (202) 358-2088, for further information.

(End of clause)

1852.219-79 Mentor Requirements and Evaluation.

As prescribed in 1819.7219(b), insert the following clause:

MENTOR REQUIREMENTS AND EVALUATION
(MARCH 1999)

(a) The purpose of the NASA Mentor-Protégé Program is for a NASA prime contractor to provide developmental assistance to certain subcontractors qualifying as protégés. Eligible protégés include small disadvantaged business concerns, women-owned small business concerns, Historically Black Colleges and Universities, and minority institutions meeting the qualifications specified in NASA FAR Supplement (NFS) 1819.7209.

(b) NASA will evaluate the contractor's performance on the following factors. If this contract includes an award fee incentive, this assessment will be accomplished as part of the fee evaluation process.

(1) Specific actions taken by the contractor, during the evaluation period, to increase the participation of protégés as subcontractors and suppliers;

(2) Specific actions taken by the contractor during this evaluation period to develop the technical and corporate administrative expertise of a protégé as defined in the agreement;

(3) To what extent the protégé has met the developmental objectives in the agreement; and

(4) To what extent the firm's participation in the Mentor-Protégé Program resulted in the protégé receiving competitive contract(s) and subcontract(s) from private firms and agencies other than the mentor.

(c) Semi-annual reports shall be submitted by the mentor to the NASA Mentor-Protégé program manager, NASA Headquarters OSDBU, to include information as outlined in paragraph (b).

(d) The mentor will notify the OSDBU and the contracting officer, in writing, at least 30 days in advance of the mentor firm's intent to voluntarily withdraw from the program or upon receipt of a protégé's notice to withdraw from the Program;

(e) Mentor and protégé firms will submit a "lessons learned" evaluation to the NASA OSDBU at the conclusion of the contract. At the end of each year in the Mentor-Protégé Program, the mentor and protégé, as appropriate, will formally brief the NASA Mentor-Protégé program manager, the technical program manager, and the contracting officer during a formal program review regarding Program accomplishments as pertains to the approved agreement.

(f) NASA may terminate mentor-protégé agreements for good cause and exclude mentor or protégé firms from participating in the NASA program. These actions shall be approved by the NASA OSDBU. NASA shall terminate an agreement by delivering to the contractor a Notice specifying the reason for termination and the effective date. Termination of an agreement does not constitute a termination of the subcontract between the mentor and the protégé. A plan for accomplishing the subcontract effort should the agreement be terminated shall be submitted with the agreement as required in NFS 1819.7213(h).

(End of clause)

1852.223-70 Safety and Health.

As prescribed in 1823.7001(a), insert the following clause:

SAFETY AND HEALTH
(JULY 2000)

(a) The Contractor shall take all reasonable safety and occupational health measures in performing this contract. The Contractor shall comply with all Federal, State, and local laws applicable to safety and occupational health and with the safety and occupational health standards, specifications, reporting requirements, and any other relevant requirements of this contract.

(b) The Contractor shall take, or cause to be taken, any other safety, and occupational health measures the Contracting Officer may reasonably direct. To the extent that the Contractor may be entitled to an equitable adjustment for those measures under the terms and conditions of this contract, the equitable adjustment shall be determined pursuant to the procedures of the changes clause of this contract; provided, that no adjustment shall be made under this Safety and Health clause for any change for which an equitable adjustment is expressly provided under any other clause of the contract.

(c) The Contractor shall immediately notify and promptly report to the Contracting Officer or a designee any accident, incident, or exposure resulting in fatality, lost-time occupational injury, occupational disease, contamination of property beyond any stated acceptable limits set forth in the contract Schedule; or property loss of $25,000 or more, or Close Call (a situation or occurrence with no injury, no damage, or only minor damage (less than $1,000) but possesses the potential to cause any category of mishap, or any injury, damage, or negative mission impact) that may be of immediate interest to NASA, arising out of work performed under this contract. The Contractor is not required to include in any report an expression of opinion as to the fault or negligence of any employee. In addition, service contractors (excluding construction contracts) shall provide quarterly reports specifying lost-time frequency rate, number of lost-time injuries, exposure, and accident/incident dollar losses as specified in the contract Schedule.

(d) The Contractor shall investigate all work-related incidents, accidents, and Close Calls, to the extent necessary to determine their causes and furnish the Contracting Officer a report, in such form as the Contracting Officer may require, of the investigative findings and proposed or completed corrective actions.

(e)(1) The Contracting Officer may notify the Contractor in writing of any noncompliance with this clause and specify corrective actions to be taken. The Contractor shall promptly take and report any necessary corrective action.

(2) If the Contractor fails or refuses to institute prompt corrective action in accordance with subparagraph (e)(1) of this clause, the Contracting Officer may invoke the stop-work order clause in this contract or any other remedy available to the Government in the event of such failure or refusal.

(f) The Contractor (or subcontractor or supplier) shall insert the substance of this clause, including this paragraph (f) and any applicable Schedule provisions, with appropriate changes of designations of the parties, in subcontracts of every tier that -

(1) Amount to $1,000,000 or more (unless the Contracting Officer makes a written determination, after consultation with installation safety and health representatives, that this is not required);

(2) Require construction, repair, or alteration in excess of $25,000; or

(3) Regardless of dollar amount, involve the use of hazardous materials or operations.

(g) Authorized Government representatives of the Contracting Officer shall have access to and the right to examine the sites or areas where work under this contract is being performed in order to determine the adequacy of the Contractor's safety and occupational health measures under this clause.

(h) The contractor shall continually update the safety and health plan when necessary. In particular, the Contractor shall furnish a list of all hazardous operations to be performed, and a list of other major or key operations required or planned in the performance of the contract, even though not deemed hazardous by the Contractor. NASA and the Contractor shall jointly decide which operations are to be considered hazardous, with NASA as the final authority. Before hazardous operations commence, the Contractor shall submit for NASA concurrence --

(1) Written hazardous operating procedures for all hazardous operations; and/or

(2) Qualification standards for personnel involved in hazardous operations.

(End of clause)

1852.223-71 Frequency Authorization.

As prescribed in 1823.7101, insert the following clause:

FREQUENCY AUTHORIZATION
(DECEMBER 1988)

(a) Authorization of radio frequencies required in support of this contract shall be obtained by the Contractor or subcontractor in need thereof.

(b) For any experimental, developmental, or operational equipment for which the appropriate frequency allocation has not been made, the Contractor or subcontractor shall provide the technical operating characteristics of the proposed electromagnetic radiating device to the Contracting Officer during the initial planning, experimental, or developmental phase of contractual performance. Procedures furnished by the Contracting Officer shall be followed in obtaining radio frequency authorization.

(c) This clause, including this paragraph (c), shall be included in all subcontracts that call for developing, producing, testing, or operating a device for which a radio frequency authorization is required.

(End of clause)

1852.223-73  Safety and Health Plan.

As prescribed in 1823.7001(c), insert the following provision:

SAFETY AND HEALTH PLAN
(JULY 2000)

The offeror shall submit a detailed safety and occupational health plan as part of its proposal (see NPG 8715.3, NASA Safety Manual, Appendix H). The plan must include a detailed discussion of the policies, procedures, and techniques that will be used to ensure the safety and occupational health of contractor employees and to ensure the safety of all working conditions throughout the performance of the contract. The plan must similarly address safety and occupational health for subcontractor employees for any proposed subcontract whose value is expected to exceed $500,000, including commercial services and services provided in support of a commercial item. Also, when applicable, the plan must address the policies, procedures, and techniques that will be used to ensure the safety and occupational health of NASA employees and the public. This plan, as approved by the Contracting Officer, will be included in any resulting contract.

(End of provision)

1852.223-74 Drug- and alcohol-free workforce.

As prescribed in 1823.570-3, insert the following clause:

DRUG- AND ALCOHOL-FREE WORKFORCE
(MARCH 1996)

(a) Definitions. As used in this clause the terms "employee," "controlled substance," "employee in a sensitive position," and "use, in violation of applicable law or Federal regulation, of alcohol" are as defined in 48 CFR 1823.570-2.

(b)(1) The Contractor shall institute and maintain a program for achieving a drug-and alcohol-free workforce. As a minimum, the program shall provide for preemployment, reasonable suspicion, random, post-accident, and periodic recurring (follow-up) testing of contractor employees in sensitive positions for use, in violation of applicable law or Federal regulation, of alcohol or a controlled substance. The Contractor may establish its testing or rehabilitation program in cooperation with other contractors or organizations.

(2) This clause neither prohibits nor requires the Contractor to test employees in a foreign country. If the Contractor chooses to conduct such testing, this clause does not authorize the Contractor to violate foreign law in conducting such testing.

(3) The Contractor's program shall test for the use of marijuana and cocaine. The Contractor's program may test for the use of other controlled substances.

(4) The Contractor's program shall conform to the "Mandatory Guidelines for Federal Workplace Drug Testing Programs" published by the Department of Health and Human Services (59 FR 29908, June 9, 1994) and the procedures in 49 CFR part 40, "Procedures for Transportation Workplace Drug Testing Programs," in which references to "DOT" shall be read as "NASA", and the split sample method of collection shall be used.

(c)(1) The Contractor's program shall provide, where appropriate, for the suspension, disqualification, or dismissal of any employee in a sensitive position in any instance where a test conducted and confirmed under the Contractor's program indicates that such individual has used, in violation of applicable law or Federal regulation, alcohol or a controlled substance.

(2) The Contractor's program shall further prohibit any such individual from working in a sensitive position on a NASA contract, unless such individual has completed a program of rehabilitation described in paragraph (d) of this clause.

(3) The Contractor's program shall further prohibit any such individual from working in any sensitive position on a NASA contract if the individual is determined under the Contractor's program to have used, in violation of applicable law or Federal regulation, alcohol or a controlled substance and the individual meets any of the following criteria:

(i) The individual had undertaken or completed a rehabilitation program described in paragraph (d) of this clause prior to such use;

(ii) Following such determination, the individual refuses to undertake such a rehabilitation program;

(iii) Following such determination, the individual fails to complete such a rehabilitation program; or

(iv) The individual used a controlled substance or alcohol while on duty.

(d) The Contractor shall institute and maintain an appropriate rehabilitation program which shall, as a minimum, provide for the identification and opportunity for treatment of employees whose duties include responsibility for safety-sensitive, security, or National security functions who are in need of assistance in resolving problems with the use of alcohol or controlled substances.

(e) The requirements of this clause shall take precedence over any state or local Government laws, rules, regulations, ordinances, standards, or orders that are inconsistent with the requirements of this clause.

(f) For any collective bargaining agreement, the Contractor will negotiate the terms of its program with employee representatives, as appropriate, under labor relations laws or negotiated agreements. Such negotiation, however, cannot change the requirements of this clause. Employees covered under collective bargaining agreements will not be subject to the requirements of this clause until those agreements have been modified, as necessary; provided, however, that if one year after commencement of negotiation the parties have failed to reach agreement, an impasse will be determined to have been reached and the Contractor will unilaterally implement the requirements of this clause.

(g) The Contractor shall insert a clause containing all the terms of this clause, including this paragraph (g), in all subcontracts in which work is performed by an employee in a sensitive position, except subcontracts for commercial items (see FAR parts 2 and 12).

(End of clause)

1852.223-75 Major Breach of Safety or Security.

As prescribed in 1823.7001(d), insert the following clause:

MAJOR BREACH OF SAFETY OR SECURITY
(JULY 2000)

(a) Safety is the freedom from those conditions that can cause death, injury, occupational illness, damage to or loss of equipment or property, or damage to the environment. Safety is essential to NASA and is a material part of this contract. A major breach of safety may constitute a breach of contract that entitles the Government to exercise any of its rights and remedies applicable to material parts of this contract, including termination for default. A major breach of safety must be related directly to the work on the contract. A major breach of safety is an act or omission of the contractor that consists of an accident, incident, or exposure resulting in a fatality; or in damage to equipment or property equal to or greater than $1 million; or in any "willful" or "repeat" violation cited by the Occupational Health and Safety Administration (OSHA) or by a state agency operating under an OSHA approved plan.

(b) Security is the condition of safeguarding against espionage, sabotage, crime (including computer crime), or attack. A major breach of security may constitute a breach of contract that entitles the Government to exercise any of its rights and remedies applicable to material parts of this contract, including termination for default. A major breach of security may occur on or off Government installations, but must be related directly to the work on the contract. A major breach of security may arise from any of the following: compromise of classified information; illegal technology transfer; workplace violence resulting in criminal conviction; sabotage; compromise or denial of information technology services; damage or loss greater than $250,000 to the Government; or theft.

(c) In the event of a major breach of safety or security, the Contractor shall report the breach to the Contracting Officer. If directed by the Contracting Officer, the Contractor shall conduct its own investigation and report the results to the Government. The Contractor shall cooperate with the Government investigation, if conducted.

(End of clause)

1852.225-8 Duty-Free Entry of Space Articles.

As prescribed in 1825.1101(e), add the following paragraph (k) to the basic clause at FAR 52.225-8:

(k) The following supplies will be given duty-free entry:

[Insert the supplies that are to be accorded duty-free entry.]

(End of addition)

1852.225-70 Export Licenses.

As prescribed in 1825.1103-70(b), insert the following clause:

EXPORT LICENSES
(FEBRUARY 2000)

(a) The Contractor shall comply with all U.S. export control laws and regulations, including the International Traffic in Arms Regulations (ITAR), 22 CFR Parts 120 through 130, and the Export Administration Regulations (EAR), 15 CFR Parts 730 through 799, in the performance of this contract. In the absence of available license exemptions/exceptions, the Contractor shall be responsible for obtaining the appropriate licenses or other approvals, if required, for exports of hardware, technical data, and software, or for the provision of technical assistance.

(b) The Contractor shall be responsible for obtaining export licenses, if required, before utilizing foreign persons in the performance of this contract, including instances where the work is to be performed on-site at [insert name of NASA installation], where the foreign person will have access to export-controlled technical data or software.

(c) The Contractor shall be responsible for all regulatory record keeping requirements associated with the use of licenses and license exemptions/exceptions.

(d) The Contractor shall be responsible for ensuring that the provisions of this clause apply to its subcontractors.

(End of clause)

ALTERNATE I
(FEBRUARY 2000)

As prescribed in 1825.1103-70(b), add the following paragraph (e) as Alternate I to the clause:

(e) The Contractor may request, in writing, that the Contracting Officer authorize it to export ITAR-controlled technical data (including software) pursuant to the exemption at 22 CFR 125.4(b)(3). The Contracting Officer or designated representative may authorize or direct the use of the exemption where the data does not disclose details of the design, development, production, or manufacture of any defense article.