PART 2 (C)
Design - Decision - Contract
April 1961 through June 1961
1961 April
1961 May
1961 June
April 6
The Marshall Space Flight Center announced that 1.640 million pounds of
thrust was achieved in a static- firing of the F-1 engine thrust chamber
at Edwards Air Force Base, Calif. This was a record thrust for a single
chamber.
Baltimore Sun, April 12, 1961; Rocketdyne
Skywriter, April 14, 1961.
April 10
A joint meeting of the Apollo Technical Liaison Groups was held at STG.
NASA Headquarters and STG representatives briefed members of the Groups
on the status of the Apollo program. The individual Liaison Groups were
asked to reexamine the Apollo guidelines in the light of NASA and
contractor studies conducted during the past year and to help gather
detailed technical information for use as background material in the
preparation of the Apollo spacecraft specification.
Minutes of meeting of Apollo Technical Liaison Group, Configurations and
Aerodynamics, April 10 12, 1961.
April 10-12
At the second meeting of the Apollo Technical Liaison Group for
Configurations and Aerodynamics at STG, presentations were made on
Apollo-related activities at the NASA Centers: heatshield tests (Ames
Research Center); reentry configurations (Marshall Space Flight Center);
reentry configurations, especially lenticular (modified) and spherically
blunted, paraglider soft-landing system, dynamic stability tests, and
heat transfer tests (Langley Research Center); tumbling entries in
planetary atmospheres (Mars and Venus) (Jet Propulsion Laboratory); air
launch technique for Dyna-Soar (Flight Research Center); and steerable
parachute system and reentry spacecraft configuration (STG). Work began
on the background material for the Apollo spacecraft specification.
Minutes of meeting of Apollo Technical Liaison Group, Configurations and
Aerodynamics, April 10-12, 1961.
April 10-12
The Apollo Technical Liaison Group for Heating heard reports at STG by
Group members on current studies at the NASA Centers. Recommendations
concerning the spacecraft specification included:
- The contractor should present the design philosophy and criteria to
be used for the heat protection system and discuss the interplay of
thermal and structural design criteria.
- The details of the analysis should be presented: for example, the
methods used in calculating the various modes of the heating load; the
listing of the material properties and ablation effectiveness of
heatshields; and the listing, in terms of temperature or extra heat
protection weight, of the safety factors that had been used.
Minutes of meeting of Apollo Technical Liaison Group, Heating, April 10-
12, 1961.
April 10-12
At STG the Apollo Technical Liaison Group for Human Factors discussed
the proposed outline for the spacecraft specification. Its
recommendations included:
- NASA Headquarters Offices should contact appropriate committees and
other representatives of the scientific community to elicit
recommendations for scientific experiments aboard the orbiting
laboratory to be designed as a mission module for use with the Apollo
spacecraft.
- NASA should sponsor a conference of recognized scientists to suggest
a realistic radiation dosage design limit for Apollo crews.
Minutes of meeting of Apollo Technical Liaison Group, Human Factors,
April 10, 11, and 12, 1961.
April 10-12
The Apollo Technical Liaison Group for Instrumentation and
Communications met at STG and drafted an informal set of guidelines and
sent them to the other Technical Liaison Groups:
- Instrumentation requirements: all Groups should submit their
requests for measurements to be made on the Apollo missions, including
orbital, circumlunar, and lunar landing operations.
- Television: since full-rate, high-quality television for the
missions would add a communications load that could swamp all others and
add power and bandwidth requirements not otherwise needed, other Groups
should restate their justification for television requirements.
- Temperature environment; heat normally pumped overboard might be
made available for temperature control systems without excessive cost
and complexity.
- Reentry communications; continuous reentry communications were not
yet feasible and could not be guaranteed. It was suggested that all
Groups plan their systems as though no communications would exist at
altitudes between about 250,000 feet and 90,000 feet.
- Vehicle reentry and recovery: if tracking during reentry were
desired, it would be far more economical to use a water landing site
along the Atlantic Missile Range or another East Coast site.
- Digital computer : the onboard digital computer, if it were flexible
enough, would permit the examination of telemetry data for bandwidth
reduction before transmission.
- Antenna-pointing information: the spacecraft should have information
relative to its orientation so that any high-gain directive antenna
could be positioned toward the desired location on earth.
The Group then discussed the preparation of material for the Apollo
spacecraft specification.
Minutes of meeting of Apollo Technical Liaison Group, Instrumentation
and Communications, April 10, 11, and 12, 1961.
April 10-12
The Apollo Technical Liaison Group for Onboard Propulsion met at STG and
considered preparation of background material for the Apollo spacecraft
specification. It agreed that there were several problem areas for study
before onboard propulsion final specifications could be drafted :
cryogenic propellant storage problems, booster explosion hazards and
assessment thereof, spacecraft system abort modes, propulsion system
temperature control, propellant leakage, ignition in a confined space,
zero suction pump proposals for cryogenic liquid bipropellant main
engine systems, and propellant utilization and measurement system.
Minutes of meeting of Apollo Technical Liaison Group, Onboard
Propulsion, April 10-12, 1961.
April 10-12
The Apollo Technical Liaison Group for Structures and Materials
discussed at STG the preparation of material for the Apollo spacecraft
specification. It decided that most of the items proposed for its study
could not be specified at that time and also that many of the items did
not fall within the structures and materials area. A number of general
areas of concern were added to the work plan: heat protection, meteoroid
protection, radiation effects, and vibration and acoustics.
Minutes of meeting of Apollo Technical Liaison Group, Structures and
Materials, April 10-12, 1961.
April 10-12
The Apollo Technical Liaison Group for Trajectory Analysis met at STG
and began preparing material for the Apollo spacecraft specification. It
recommended:
- STG should take the initiative with NASA Headquarters in delegating
responsibility for setting up and updating a uniform model of
astronomical constants.
- The name of the Group should be changed to Mission Analysis to help
clarify its purpose.
- A panel should be set up to determine the scientific experiments
which could be done on board, or in conjunction with the orbiting
laboratory, so that equipment, weight, volumes, laboratory
characteristics, etc., might be specified
Minutes of meeting of Apollo Technical Liaison Group, Trajectory
Analysis, April 10-12, 1961.
April 10-13
In preparing background material for the Apollo spacecraft specification
at STG, the Apollo Technical Liaison Group for Mechanical Systems worked
on environmental control systems, reaction control systems, auxiliary
power supplies, landing and recovery systems, and space cabin sealing.
Minutes of meeting of Apollo Technical Liaison Group, Trajectory
Analysis, April 10-13, 1961.
April 10-14
Meeting at STG, the Guidance and Control Group changed its name to the
"Apollo Technical Liaison Group for Navigation, Guidance, and
Control." Definitions were established for "navigation"
(the determination of position and velocity), "guidance"
(velocity vector control), and "control" (control of
rotational orientation about the center of gravity - i.e., attitude
control). Work was started on the preparation of the navigation,
guidance, and control specifications for the Apollo spacecraft.
Minutes of meeting of Apollo Technical Liaison Group, Navigation,
Guidance, and Control, April 10-14, 1961.
April 12
NASA Associate Administrator Robert C. Seamans, Jr., established the
permanent Saturn Program Requirements Committee. Members were William A.
Fleming, Chairman; John L. Sloop, Deputy Chairman; Richard B. Canright;
John H. Disher; Eldon W. Hall; A. M. Mayo; and Addison M. Rothrock, all
of NASA Headquarters. The Committee would review on a continuing basis
the mission planning for the utilization of the Saturn and correlate
such planning with the Saturn development and procurement plans.
Memorandum, Seamans to Program Directors, "Establishment of Saturn
Program Requirements Committee," April 12, 1961.
April 12
The Soviet Union launched into orbit the five-ton Vostok I,
with Yuri A. Gagarin as pilot, the first man to make a successful
orbital space flight. The payload included life-support equipment and
radio and television to relay information on the condition of the pilot.
The spacecraft apogee was 187.8 miles, the perigee was 109.5 miles,
inclination 65.07 degrees, and the orbital period 89.1 minutes. After a
108-minute, one-orbit flight, the capsule and pilot reentered and landed
safely in the Soviet Union.
New York Times, April 13, 1961; Instruments and
Spacecraft, p. 170.
April 12
President John F. Kennedy, in his regular press conference, stated that
"no one is more tired than I am" of seeing the United States
second to Russia in space. "They secured large boosters which have
led to their being first in Sputnik, and led to their first putting
their man in space. We are, I hope, going to be able to carry out our
efforts, with due regard to the problem of the life of the men involved,
this year. But we are behind . . . the news will be worse before it is
better, and it will be some time before we catch up. . . ."
Washington Post, April 13, 1961.
April 14
Under questioning by the House Committee on Science and Astronautics,
NASA Associate Administrator Robert C. Seamans, Jr., stated that a
landing on the moon in 1967 might be possible through an all-out crash
program at a cost of $4 to $5 billion a year instead of the current
budget of $1.236 billion.
Washington Post, April 15, 1961.
April 19
A circular, "Manned Lunar Landing via Rendezvous," was
prepared by John C. Houbolt from material supplied by himself, John D.
Bird, Max C. Kurbjun, and Arthur W. Vogeley, who were members of the
Langley Research Center space station subcommittee on rendezvous. Other
members of the subcommittee at various times included W. Hewitt
Phillips, John M. Eggleston, John A. Dodgen, and William D. Mace.
Bird, "Short History of the Development of the Lunar Orbit
Rendezvous Plan at Langley Research Center," p. 3.
April 19
John C. Houbolt and members of the Langley Research Center subcommittee
on rendezvous outlined the objectives of a rendezvous program that would
lead ultimately to a manned lunar landing:
- establish manned and unmanned orbital operations,
- establish techniques for accomplishing space missions through the
orbital assembly of units.
Three key projects were described which would accomplish these
objectives. The first was MORAD (Manned Orbital Rendezvous and Docking).
which would require the use of the Mercury-Atlas and Scout in the 1961-
1963 period. Rendezvous in space between the Mercury spacecraft and
Scout payload would establish confidence in manned rendezvous techniques
and lead to simplification of equipment and increased reliability. The
second key project was ARP (Apollo Rendezvous Phases), in which the
Atlas, Agena, and Saturn boosters would be used in the 1962-1965 period.
This program would accomplish rendezvous with space stations, personnel
transfer, resupply of space laboratory, execution of space maneuvers
after coupling (steps toward lunar landing), and development of
specifications for subsequent orbital and moon missions. The third
project was called MALLIR (Manned Lunar Landing Involving Rendezvous),
in which Saturn and Apollo components would be used during the 1961-1967
period. After qualification of the Saturn components for rendezvous
operations, an early manned lunar landing would take place.
Langley Research Center, "Manned Lunar Landing via
Rendezvous," April 19, 1961.
April 19
An early lunar excursion module was proposed by personell of Langley Research Center as the lunar lander for the suggested Project MALLIR.
The booster requirements for Project MALLIR (Manned Lunar Landing
Involving Rendezvous) would be satisfied by use of the Saturn C-2 as the
basic launch vehicle. The number of boosters needed to achieve a lunar
landing would be substantially reduced by using a combination of earth
orbit and lunar orbit rendezvous. In a Project MALLIR configuration, two
Saturn C-2's would be required. The first would launch the command
module, lunar lander, and propulsion unit for lunar braking. The second
would launch a booster which would rendezvous in earth orbit with the
spacecraft. This booster would be jettisoned after launching the
configuration into a lunar trajectory. After reaching lunar orbit, the
lunar lander would separate from the command module and descend to the
lunar surface. One man would remain behind in the command module
orbiting the moon. After a brief lunar stay, the two men would ascend in
the lunar lander and rendezvous with the command module. The command
module would then boost to return trajectory, leaving behind the lunar
lander, and reenter after jettisoning the propulsion unit. The command
module was estimated to weigh 11,000 pounds, and the lunar lander 11,000
pounds.
"Manned Lunar Landing via Rendezvous."
April 19
Recommendations on immediate steps to be taken so that the three key
projects - MORAD (Manned Orbital Rendezvous and Docking), ARP (Apollo
Rendezvous Phases), and MALLIR (Manned Lunar Landing Involving
Rendezvous) - could get under way were:
- Approve the MORAD project and let a study contract to consider
general aspects of the Scout rendezvous vehicle design, definite
planning and schedules, and tie down cost estimates more exactly.
- Delegate responsibility to STG to give accelerated consideration to
rendezvous aspects of Apollo, tailoring developments to fit directly
into the MALLIR project.
- Let a study contract to establish preliminary design, scheduling,
and cost figures for the three projects.
"Manned Lunar Landing via Rendezvous."
April 20
A conference was held at NASA Headquarters on the relationship between
the Prospector and Apollo programs. Representatives of the Jet
Propulsion Laboratory (JPL) and STG discussed the possible redirection
of Prospector planning to support more directly the manned space
program. The Prospector spacecraft was intended to soft-land about 2,500
pounds on the lunar surface with an accuracy of +/-1 kilometer anywhere
on the visible side of the moon. An essential feature of Prospector was
the development of an automatic roving vehicle weighing about 1500
pounds which would permit detailed reconnaissance of the lunar surface
over a wide area. STG representatives felt that the most useful feature
of the Prospector program lay in its planned ability to soft-land cargo
in close proximity to a desired site. Many applications could be
foreseen, such as the deposit of landing aids and essential material in
support of a manned lunar landing or in continuing support for a manned
lunar expedition. However, the Prospector roving vehicle seemed to be a
much more complicated and heavier piece of hardware than a manned lunar
transport and, for that reason, STG did not support its development. The
planning for Prospector involved JPL in-house studies concerning closer
integration with manned space flight requirements, definitive decisions
on the program within several months, a contractor's study in Fiscal
Year 1962, engineering design in Fiscal Year 1963, and a hardware
contract at a future date. Future Prospector planning would emphasize
its cargo-carrying ability as a prime requirement, JPL representatives
stated.
Memorandum, H. Kurt Strass, Apollo Project Office, to Associate
Director, STG, "Conference at NASA Headquarters Concerning
Relationship Between the Prospector and Apollo Programs, April 20,
1961," May 1, 1961.
April 25
Mercury-Atlas 3 (MA-3) was launched from the Atlantic Missile Range,
carrying a "mechanical astronaut" in an intended unmanned
orbital flight. Forty seconds after liftoff, MA-3 was destroyed by the
range safety officer because the inertial guidance system had failed to
pitch the vehicle over toward the horizon. The spacecraft successfully
aborted and was recovered a short distance off shore.
Swenson et al., This New Ocean, pp. 335-337.
April 25
A conference was held at Lewis Research Center between STG and Lewis
representatives to discuss the research and development contract for the
liquid-hydrogen liquid-oxygen fuel cell as the primary spacecraft
electrical power source. Lewis had been provided funds approximately
$300,000 by NASA Headquarters to negotiate a contract with Pratt &
Whitney Aircraft Division of United Aircraft Corporation for the
development of a fuel cell for the Apollo spacecraft. STG and Lewis
representatives agreed that the research and development should be
directed toward the liquid-hydrogen - liquid-oxygen fuel cell.
Guidelines were provided by STG:
- Power output requirement for the Apollo spacecraft was estimated at
two to three kilowatts.
- Nominal output voltage should be about 27.5 volts.
- Regulation should be within +/- 10 percent of nominal output
voltage.
- The fuel cell should be capable of sustained operation at reduced
output (10 percent of rated capacity, if possible).
- The fuel cell and associated system should be capable of operation
in a space environment.
Lewis planned to request a pilot model of the fuel cell of about 250
watts capacity, capable of unattended operation. Contract negotiations
were expected to be completed by May 2 and the model delivered within 12 months of the contract award.
Memorandum, Preston T. Maxwell, Aeronautical Research Engineer, to
Associate Director (Research and Development), STG, "Conference with
Lewis Research Center Personnel to Discuss R and D Contract for H2-O2
Fuel Cell," April 27, 1961.
April 28
Little Joe 5B was launched from Wallops Island, carrying a production
Mercury spacecraft. In spite of an erroneous trajectory which subjected
the capsule to much greater dynamic pressures than planned, the
spacecraft and escape system performed successfully.
Swenson et al., This New Ocean, pp.
337-338.
April 29
The first successful flight qualification test of the Saturn SA-1
booster took place in an eight-engine test lasting 30 seconds.
Saturn Illustrated Chronology, p. 24.
During the Month
The Douglas Aircraft Company reported that air transport of the Saturn
C-1 second stage (S-IV) was feasible.
Saturn Illustrated Chronology, p. 22.
Anticipating the expanded scope of manned space flight programs, STG
proposed a manned spacecraft development center. The nucleus for a
center existed in STG, which was handling the Mercury project. A program
of much greater magnitude would require a substantial expansion of staff
and facilities and of organization and management controls.
STG Study, "Manned Spacecraft Development Center, Organizational
Concepts and Staffing Requirements," May1, 1961.
May 2
NASA Associate Administrator Robert C. Seamans, Jr., established the Ad
Hoc Task Group for a Manned Lunar Landing Study, to be chaired by
William A. Fleming of NASA Headquarters. The study was expected to
produce the following information:
- All tasks associated with the mission.
- Interdependent time-phasing of the tasks.
- Areas requiring considerable technological advancements from the
current state of the art.
- Tasks for which multiple approach solutions were advisable.
- Important action and decision points in the mission plan.
- A refined estimate by task and by fiscal year of the dollar
resources required for the mission.
- Refined estimates of in-house manpower requirements, by task and by
fiscal year
- Tentative in-house and contractor task assignments accompanying the
dollar and manpower resource requirements.
The study began on May 8 and the final report was submitted on June 16.
Guidelines served as a starting point for the study:
- The manned lunar landing target date was 1967.
- Intermediate missions of multiman orbital satellites and manned
circumlunar missions were desirable at the earliest possible time.
- Man's mission on the moon as it affected the study was to be
determined by the Ad Hoc Task Group - i.e., the time to be spent on the
lunar surface and the tasks to be performed while there.
- In establishing the mission plan, the use of the Saturn C-2 launch
vehicle was to be evaluated as compared with an alternative launch
vehicle having a higher thrust first stage and C-2 upper-stage
components.
- The mission plan was to include parallel development of liquid and
solid propulsion leading to a Nova vehicle 400,000 pounds in earth orbit
and should indicate when the decision should be made on the final Nova
configuration.
- Nuclear-powered launch vehicles should not be considered for use in
the first manned lunar landing mission.
- The flight test program should be laid out with enough launchings to
meet the needs of the program considering the reliability requirements.
- Alternative approaches should be provided in critical areas - e.g.,
upper stages and mission modes.
Memorandum, Seamans to Directors, Office of Space Flight Programs,
Office of Launch Vehicle Programs, Office of Advanced Research Programs,
and Office of Life Sciences Programs, "Establishment of Ad Hoc Task
Group for Manned Lunar Landing Study," May 2, 1961.
The engineering sketch drawn by John D. Bird of Langley Research Center on May 3, 1961, indicated the thinking of that period: By launching two Saturn C-2's, the lunar landing mission could be accomplished by using both earth rendezvous and lunar rendezvous at various stages of the mission.
May 5
STG completed the first draft of "Project Apollo, Phase A, General
Requirements for a Proposal for a Manned Space Vehicle and System"
[Statement of Work], an early step toward the spacecraft specification.
A circumlunar mission was the basis for planning.
"Apollo Spacecraft Chronology," p. 8.
May 5
In the first American manned space flight, Freedom 7,
piloted by Astronaut Alan B. Shepard, Jr., was launched successfully
from the Atlantic Missile Range. The Redstone rocket boosted the Mercury
capsule to 116.5 miles and a maximum speed of 5,180 miles per hour.
After a flight of 15 minutes and 22 seconds, the landing was made 302
miles downrange from the launch site. Recovery operations were perfect;
there was no damage to the spacecraft; and Astronaut Shepard was in
excellent condition.
Grimwood, Project Mercury: A Chronology, p. 137.
May 7
Albert C. Hall of The Martin Company proposed to Robert C. Seamans, Jr.,
NASA's Associate Administrator, that the Titan II be considered as a
launch vehicle in the lunar landing program. Although skeptical, Seamans
arranged for a more formal presentation the next day. Abe Silverstein,
NASA's Director of Space Flight Programs, was sufficiently impressed to
ask Director Robert R. Gilruth and STG to study the possible uses of
Titan II. Silverstein shortly informed Seamans of the possibility of
using the Titan II to launch a scaled-up Mercury spacecraft.
Interview with Seamans, Washington, D.C., May 26, 1966.
May 8
After study and discussion by STG and Marshal! Space Flight Center
officials, STG concluded that the current 154-inch diameter of the
second stage (S-IV) adapter for the Apollo spacecraft would be
satisfactory for the Apollo missions on Saturn flights SA-7, SA-8, SA-9,
and SA-1 0.
Letter, Robert R. Gilruth, Director, STG, to Marshall Space Flight
Center, Attn: W. M. von Braun, Director, "S-IV Adapter and C-1
Two-Stage Report," May 8, 1961.
A cross-section drawing of the vehicle (D-2) recommended by General Electric's Missile and Space Vehicle Department for the Apollo program during the Apollo feasibility study, completed in May 1961. (G.E. illustration)
A mission sequence to earth landing, developed by G.E. during its Project Apollo feasibility study, including the planned configuration through the lunar-earth trajectory, reentry, and landing. (G.E. illustration)
"TO THE MOON WITH C-1's OR BUST" was the theme of the day at Langley Research Center May 22, 1961. The sketch by John D. Bird on that day portrays the means of completing the lunar mission by launching ten C-1's.
May 15-17
The final reports on the feasibility study contracts for the advanced
manned spacecraft were submitted to STG at Langley Field, Va., by the
General Electric Company, Convair Astronautics Division of General
Dynamics Corporation, and The Martin Company. These studies had begun in
November 1960.
Aeronautical and Astronautical Events of 1961, pp. 20, 23;
"Apollo Spacecraft Chronology," p. 9.
May 22
The second draft of a Statement of Work for the development of an
advanced manned spacecraft was completed, incorporating results from
NASA in-house and contractor feasibility studies.
"Apollo Spacecraft Chronology," p. 9.
May 25
In a special message to Congress on urgent national needs, President
John F. Kennedy called for new, long- range goals for the space program:
"Now it is time to take longer strides - time for a great new American
enterprise time for this nation to take a clearly leading role in space
achievement, which in many ways may hold the key to our future on earth.
. . . I believe that this nation should commit itself to achieving the
goal, before this decade is out, of landing a man on the moon and
returning him safely to the earth. No single space project in this
period will be more impressive to mankind, or more important for the
long-range exploration of space; and none will be so difficult or
expensive to accomplish . . . in a very real sense, it will not be one
man going to the moon if we make this judgment affirmatively, it will be
an entire nation. For all of us must work to put him there." The
President also called for the early development of the Rover nuclear
rocket, the acceleration of the use of space satellites for worldwide
communications, and the development of a weather satellite system. For
these and associated projects in space technology, the President
requested additional appropriations totaling $611 million for NASA and
DOD for Fiscal Year 1962.
U.S. Congress, Senate, Committee on Aeronautical and Space Sciences,
Documents on International Aspects of the Exploration and Use of
Outer Space, 1954-1962, Staff Report, 88th Congress, 1st Session
(1963), pp. 202, 203.
Lunar lander sizes under study in May 1962 as various groups were making determinations on the best way to achieve the lunar landing goal.
May 25
Robert C. Seamans, Jr., NASA's Associate Administrator, requested the
Directors of the Office of Launch Vehicle Programs and the Office of
Advanced Research Programs to bring together members of their staffs
with other persons from NASA Headquarters to assess a wide variety of
possible ways of accomplishing the lunar landing mission. This study was
to supplement the one being done by the Ad Hoc Task Group for Manned
Lunar Landing Study (Fleming Committee) but was to be separate from it.
Bruce T. Lundin was appointed Chairman of the study group (Lundin
Committee). The following guidelines were suggested :
- All possible approaches for accomplishing the manned lunar landing
mission in the 1967-1970 period should be considered.
- Primary emphasis should be placed on the launch vehicle portion of
the system: vehicle size and type, the use of rendezvous, etc.
- Nuclear-powered launch vehicles should not be considered for use in
the early manned lunar landing missions.
- Advantages, disadvantages, and problems associated with each
technique should be indicated and, based on these, a relative rating of
the various methods. should be established.
- The time phasing and a rough order of magnitude cost should be
indicated for each method considered.
- The study should be completed at about the same time as the one
under way by the Ad Hoc Task Group on Manned Lunar Landing Study.
The Lundin Committee report was submitted June 10.
Memorandum, Associate Administrator to Directors, Launch Vehicle
Programs and Advanced Research Programs, "Broad Study of Feasible
Ways for Accomplishing Manned Lunar Landing Mission," May 25, 1961;
Rosholt, An Administrative History of NASA, 1958-1963, p.
213.
May 31
STG submitted to NASA Headquarters recommendations on crew selection and
training:
- There would be no need to select crews within the next 12 months,
Pilots could be chosen as required from the astronaut group, permitting
the prospective crewmen to be active in test flying until assigned to
Apollo missions.
- Based on extrapolations from the Mercury program, STG expected that
12 months would be ample time for specialized training before a flight.
- A maximum of 18 astronauts in 1965 would be needed to fulfil the
requirements of the flight schedule.
- All crew members would be experienced flight personnel; special
engineering or scientific capabilities would be provided through crew
indoctrination.
Letter, Robert R. Gilruth, Director, STG, to NASA Headquarters, Attn:
Abe Silverstein, "Apollo Crew Selection and Training," May 31,
1961.
During the Month
The Marshall Space Flight Center began reevaluation of the Saturn C-2
configuration capability to support circumlunar missions. Results showed
that a Saturn vehicle of even greater performance would be desirable.
Saturn Illustrated Chronology, p. 26.
During the Month
Basic concepts of the lunar orbit rendezvous plan were presented to the
Lundin Committee by John C. Houbolt of Langley Research Center.
Bird, "Short History of the Development of the Lunar Orbit
Rendezvous Plan at the Langley Research Center," p. 3.
NASA announced a change in the Saturn C-1 vehicle configuration. The
first ten research and development flights would have two stages,
instead of three, because of the changed second stage (S-IV) and,
starting with the seventh flight vehicle, increased propellant capacity
in the first stage (S-1) booster.
Senate Staff Report, Manned Space Flight Program, p.
199.
June 2
A meeting to discuss Project Apollo plans and programs was held at NASA
Headquarters. Abe Silverstein, Warren J. North, John H. Disher, and
George M. Low of NASA Headquarters and Robert R. Gilruth, Walter C.
Williams, Maxime A. Faget, James A. Chamberlin, and Robert O. Piland of
STG participated in the discussions. Six prime contract areas were
defined: spacecraft (command center), onboard propulsion, lunar landing
propulsion, launch vehicle (probably several prime contracts), tracking
and communications network, and launch facilities and equipment. The
prime contractor for the spacecraft would be responsible for the design,
engineering, and fabrication of the spacecraft; for the integration of
the onboard and lunar landing propulsion systems: and for the
integration of the entire spacecraft system with the launch vehicle. In
connection with the prime contract, STG would:
- Define details for specifications and justify choices
- Prepare a "scope of work" statement for release to
industry by July 1
- Prepare spacecraft specifications for release by August 1
- Set up a contract evaluation team, qualified to evaluate the
technical, management, design, engineering, and fabrication capabilities
of the bidders.
In connection with other projects directly relating to the Apollo
program, STG was to:
- Forward to Marshall Space Flight Center, via the Office of Space
Flight Programs, the spacecraft systems part of a preliminary
development plan for Saturn reentry tests
- Make recommendations on an advanced version of the Mercury capsule
- Designate a liaison member for the Lunar Sciences Subcommittee of
the Space Sciences Steering Committee.
The Office of Space Flight Programs would arrange a meeting with the
Office of Advanced Research Programs, STG, and Langley Research Center
on the Atlas-Agena reentry tests and with the Office of Advanced
Research Programs, Office of Life Sciences Programs, STG, and Ames
Research Center on the biomedical flight program.
Memorandum, Low, Assistant Director for Manned Space Flight Programs, to
Director of Space Flight Programs, "Report of Meeting with Space Task
Group on June 2, 1961," June 6, 1961.
June 5
The Flight Vehicles Integration Branch was organized within STG. Members
included H. Kurt Strass, Robert L. O'Neal, and Charles H. Wilson. Maxime
A. Faget, Chief, Flight Systems Division, also served as temporary
Branch Chief. The Branch was to provide technical aid to STG in solving
compatibility requirements for spacecraft and launch vehicles for manned
flight missions.
Memorandum, Faget to Staff, STG, "Change in Organization of Flight
Systems Division," June 5, 1961.
June 5
Saturn Launch Complex 34 at Cape Canaveral, Fla., was dedicated in a
brief ceremony by NASA. The giant gantry, 310 feet high and weighing
2,800 tons, was the largest movable land structure in North America.
Aeronautical and Astronautical Events of 1961, p. 25.
June 7
A preliminary study of a fin-stabilized solid-fuel rocket booster, the
Little Joe Senior, was completed by members of STG. The booster would be
capable of propelling a full-size Apollo reentry spacecraft to
velocities sufficient to match critical portions of the Saturn
trajectory. The purpose was to provide a simple and fairly inexpensive
means of determining, from flight tests, full-scale configuration
concepts, systems hardware performance, and vehicle structural
integrity. Of particular importance would be the flight testing of the
Apollo spacecraft escape system under simulated maximum conditions. (On
April 6, 1962, NASA submitted a Request for Proposal to bidders on the
Little Joe Senior, by that time renamed Little Joe II.)
NASA Project Apollo Working Paper No. 1020, "A Preliminary Study of a
Fin-Stabilized Solid-Fuel Rocket Booster for Use with the Apollo
Spacecraft," June 7, 1961.
June 10
'The Lundin Committee completed its study of various vehicle systems for
the manned lunar landing mission, as requested on May 25 by NASA
associate Administrator Robert C. Seamans, Jr. The Committee had
considered alternative methods of rendezvous: earth orbit, lunar orbit,
a combination of earth and lunar orbit, and lunar surface. Launch
vehicles studied were the Saturn C-2 and C-3. The concept of a low-
altitude earth orbit rendezvous using two or three C-3's was clearly
preferred by the Committee. Reasons for this preference were the small
number of launches and orbital operations required and the fact that the
Saturn C- 3 was considered to be an efficient launch vehicle of great
utility and future growth.
Lundin Committee, "A Survey of Various Vehicle Systems for the Manned
Lunar Landing Mission," June 10, 1961.
June 16
The Fleming Committee, which had been appointed on May 2, submitted its
report to NASA associate Administrator Robert C. Seamans, Jr., on the
feasibility of a manned lunar landing program. The Committee concluded
that the lunar mission could be accomplished within the decade. Chief
pacing items were the first stage of the launch vehicle and the
facilities for testing and launching the booster. It also concluded that
information on solar flare radiation and lunar surface characteristics
should be obtained as soon as possible, since these factors would
influence spacecraft design. Special mention was made of the need for a
strong management organization.
Ad Hoc Task Group, A Feasible Approach for an Early Manned Lunar
Landing, Part I, "Summary Report of Ad Hoc Task Group
Study," June 16, 1961, pp. 95-96.
June 20
Robert C. Seamans, Jr., NASA Associate Administrator, notified the
Directors of Launch Vehicle Program, Space Flight Programs, Advanced
Research Programs, and Life Sciences Programs that Donald H. Heaton had
been appointed Chairman of an Ad Hoc Task Group. It would establish
program plans and supporting resources necessary to accomplish the
manned lunar landing mission by the use of rendezvous techniques, using
the Saturn C-3 launch vehicle, with a target date of 1967. Guidelines
and operating methods were similar to those of the Fleming Committee.
Members of the Task Group would be appointed from the Offices of Launch
Vehicle Programs, Space Flight Program, Advanced Research Programs, and
Life Sciences Programs. The work of the Group (Heaton Committee) would
be reviewed weekly. The study was completed during August.
Memorandum, Seamans to Director, Launch Vehicle Programs, Director,
Space Flight Programs, Director, Advanced Research Programs, and Acting
Director, Life Sciences Programs, "Establishment of Ad Hoc Task Group
for Manned Lunar Landing by Rendezvous Technique." June 20. 1961.
Two methods of landing techniques proposed for the direct ascent mose for the lunar landing mission.
Another John D. Bird engineering sketch shows the potential of the Saturn C-3 for a Lunar mission as visualised in June 1961.
June 23
NASA Associate Administrator Robert C. Seamans, Jr., requested Kurt H.
Debus, Director of the NASA Launch Operations Directorate, and Maj. Gen.
Leighton I. Davis, Commander of the Air Force Missile Test Center, to
make a joint analysis of all major factors regarding the launch
requirements, methods, and procedures needed in support of an early
manned lunar landing. The schedules and early requirements were to be
considered in two phases:
- in line with the Fleming Report, a direct flight to the moon would
be assumed, using the Saturn C-1 and C-3 launch vehicles in early
support phases and liquid- or solid-fueled Nova launch vehicles for the
lunar landing;
- as a possible alternative or parallel program, orbital rendezvous
operations using Saturn C-3 and liquid- fueled Nova.
The analysis should include recommendations on mutual NASA-DOD range
responsibilities, authority, management structures, and other allied
subjects. On June 30, Seamans notified Debus and Davis that the
evaluation of tracking and command stations should not be included in
the study. He stressed that the factors of immediate concern with regard
to launch operations were those of launch site locations, land
acquisition requirements, spacecraft and launch vehicle preparation
facilities, vehicle launch facilities, and other facilities and
requirements at the launch site. (Phase I of the Report was submitted on
July 31.)
Memorandum, Seamans to Commander, AFMTC, and Director, LOD, MSFC,
"National Space Program Range Facilities and Resources
Planning," June 23, 1961; letter, Seamans to Gen. Davis and Dr.
Debus, "National Space Program Range Facilities and Resources
Planning," June 30, 1961.
June 23
NASA announced that the Saturn C-1 launch vehicle, which could place
ten-ton payloads in earth orbit, would be operational in 1964.
Senate Staff Report, Manned Space Flight Program, p. 200.
June 23
NASA announced that further engineering design work on the Saturn C-2
configuration would be discontinued and that effort instead would be
redirected toward clarification of the Saturn C-3 and Nova concepts.
Investigations were specifically directed toward determining
capabilities of the proposed C-3 configuration in supporting the Apollo
mission.
Saturn Illustrated Chronology, pp. 31-32.
June 26
Maxime A. Faget, Paul E. Purser, and Charles J. Donlan of STG met with
Arthur W. Vogeley, Clinton E. Brown, and Laurence K. Loftin, Jr., of
Langley Research Center on a "lunar landing" paper. Faget's
outline was to be used, with part of the information to be worked up by
Vogeley.
Memorandum, Purser to Robert R. Gilruth, "Log for the Week of June
26, 1961."
During the Month
STG completed a detailed assessment of the results of the Project Apollo
feasibility studies submitted by the three study contractors: the
General Electric Company, Convair/Astronautics Division of the General
Dynamics Corporation, and The Martin Company. (Their findings were
reflected in the Statement of Work sent to prospective bidders on the
spacecraft contract on July 28.)
"Apollo Spacecraft Chronology," p. 9.
During the Month
Members of Langley Research Center briefed the Heaton Committee on the
lunar orbit rendezvous method of accomplishing the manned lunar landing
mission.
Manned Lunar-Landing through use of Lunar-Orbit Rendezvous,
p. 5.
Summer
Construction began at Langley Research Center of facilities specifically
oriented toward the Apollo program, including a lunar landing simulator.
Interview with Charles J. Donlan, Langley Research Center, June 20,
1966.